Name the type of person in a Weak Matrix organization that has some power provided to manage projects; acts as a ___________ who can make some decisions or may still be an expeditor without and _____________ making authority.

A

Coordinator; Decision

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
1
Q

In a Balanced Matrix who controls the budget?

A

Controlled by functional and project managers.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
2
Q

A project life cycle includes all the phases required for a project to create a product, service, or result, e.g. in IT projects, a sample project life cycle may include Initiation, High Level Design, Low Level Design, coding, unit testing, Integration Testing, UAT, and rollout. The project life cycle is ________ specific and can be different for each project.

A

industry

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
3
Q

Stakeholders exert ________ over the project.

A

Influence

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
4
Q

Ongoing activities which help in sustaining business are called _________.

A

Operations

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
5
Q

What are the three Characteristics of a project.

A
  1. Unique
  2. Temporary
  3. Progressively elaborated
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
6
Q

The project manager must try to identify _____ stakeholders and determine _____ requirements.

A

all; all

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
7
Q

The probability of successfully completing a project is lowest at the _______ of the project.

A

Beginning

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
8
Q

In the functional organizational structure, there is no dedicated project manager. The person plays the role of an __________ (without any decision-making authority).

A

Expeditor

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
9
Q

A project life cycle is made up of ___________. A project management life cycle is made up _____________.

A

Phases, Process Groups

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
10
Q

Phase-end reviews can also be called:

A

Phase gates - Kill points - Phase exits - Toll gates - Milestones - Decision gates

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
11
Q

Name the Outputs for the Integration Knowledge Area.

I saw the cat queen have creamy rich pies and scones

A

Initiating - Develop Project Charter; Planning - Develop PMP; Executing - Direct & Manage Project Work; Monitor & Control - Monitor & Control Project Work, Perform Integrated Change Control (PICC); Close - Close Project or Phase

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
12
Q

Name the Outputs for the Scope Knowledge Area (People Can Defiantly ā€œCā€ - with a Scope).

I SAW the cat queen have creamy rich pies and scones

A

Planning - Plan Scope Management, Collect Requirements, Define Scope, Create WBS; Monitor & Control - Validate Scope, Control Scope

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
13
Q

Name the Output of the Time Knowledge area. (Plant Dat Seed - In Time).

I saw THE cat queen have creamy rich pies and scones

A

Planning - Plan Schedule Management, Define Activities, Sequence Activities, Est Activity Resources, Develop Schedule; Monitor & Control - Control Schedule

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
14
Q

What are the Outputs of the Cost Knowledge Area (Police Eat Doughnuts - at a Cost)

I saw the CAT queen have creamy rich pies and scones

A

Planning - Plan Cost Management, Estimate Costs, Determine Budget; Monitor & Control - Control Costs

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
15
Q

What are the Outputs to the Quality Knowledge Area.

I saw the cat QUEEN have creamy rich pies and scones

A

Planning - Plan Quality Management; Executing - Perform QA; Monitor & Control - Control Quality

16
Q

What are the outputs to the Human Resources (Another Delicious Mouse)

I saw the cat queen HAVE creamy rich pies and scones

A

Planning - Plan HR Management; Executing - Acquire Project Team, Develop Project Team, Manage Project Team

17
Q

What are the Outputs to the Communications Knowledge Area.

I saw the cat queen have CREAMY rich pies and scones

A

Planning - Plan Communications Management; Execute - Manage communication; Monitor & Control - Control Communications

18
Q

What are the Outputs to the Risk Knowledge Area (PIPPoP)

I saw the cat queen have creamy RICH pies and scones

A

Planning - Plan Risk Mgt; Identify Risks, Perform Qualitative Analysis, Perform Quantitative Risk Analysis, Plan Risk Responses; Monitor & Control - Control Risks

19
Q

What are the Outputs to the Procurement Knowledge Area.

I saw the cat queen have creamy rich PIES and scones

A

Planning - Plan Procurement Mgt; Executing - Conduct Procurements; Monitor & Control - Control Procurements; Closing - Close Procurements

20
Q

What are the Outputs for the Stakeholder Knowledge area.

I saw the cat queen have creamy rich pies and SCONES

A

Initiating - ID Stakeholders; Planning - Plan Stakeholder Mgt; Executing - Manage Stakeholder Engagement; Monitor & Control - Control Stakeholder Engagement