Stakeholder Management Flashcards

0
Q

Stakeholder Analysis is a technique of systematically gathering and analyzing __________ and ________ information to determine whose interests should be taken into account throughout the project?

A

Quantitative; Qualitative

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
1
Q

What grid is defined as the Level of authority combined with active involvement?

A

Power/Influence Grid (Authority = Power & involvement = Influence)

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
2
Q

Wheh should the Stakeholder Register be created and updated?

A

Created during project initiation, updated throughout the project

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
3
Q

What is the document that contains the relevant details pertaining to project stakeholders called?

A

Stakeholder Register

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
4
Q

What Plan contains information on how to effectively manage stakeholders and their engagement throughout the project?

A

Stakeholder Management Plan

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
5
Q

Engagement level of stakeholders can be classified as:

Unaware __________ Neutral
Supportive __________

A

Resistant

Leading

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
6
Q

Current and desired engagement can be documented using which type of matrix?

A

Stakeholder Engagement Assessment Matrix

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
7
Q

Which project document is used to document and monitor matters under discussion or in dispute between project stakeholders?

A

Issue Log

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
8
Q

Face-To-Face meeting is the best method for resolving?

A

Issues

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
9
Q

What are some activities that the project manager engages in to manage stakeholders?

A

Engage Stakeholders
Manage expectations
Address concerns
Clarity/resolve issues

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
10
Q

Does the Manage Stakeholder Engagement process involve resolving of issues with project stakeholders?

A

Yes

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
11
Q

What is the key input that captures changes that need to be communicated to stakeholders?

A

Change Log

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
12
Q

What grid reflects the level of authority combined with the level of concern?

A

Power/Interest (Authority = Power & Concern = Interest)

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
13
Q

What grid is defined as Active involvement combined with the ability to effect changes to the project?

A

Influence/Impact (Involvement = Influence & ‘changes to the project’ = Impact)

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
14
Q

________ __________ is an important tool used in the Identify Stakeholders process.

A

Stakeholder Analysis

How well did you know this?
1
Not at all
2
3
4
5
Perfectly