Throughput Accounting (1) Flashcards

1
Q

What is theory of constraints?

A

A production system where key financial concept is maximisation of throughput while keeping conversion and investment costs to a minimum

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
2
Q

What is throughput contribution?

A

Sales revenue - direct material cost

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
3
Q

What is throughput contribution per unit?

A

Sales price per unit - direct material cost per unit

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
4
Q

Key financial concept of theory of constraints?

A

Turn materials into sales as quickly as possible, thereby maximising net cash generated from sales

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
5
Q

What happens in throughput accounting?

A

All operational expenses except materials are assumed to be fixed costs

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
6
Q

What is a bottle neck resource?

A

A process which has a lower capacity than preceding or subsequent activities, thereby limiting throughput

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
7
Q

What is a binding constraint?

A

When one process will inevitably act as a bottleneck

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
8
Q

What is bottleneck resource also known as?

A

A binding constraint

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
9
Q

What is the only way to increase throughput?

A

Increase the capacity of the bottleneck constraint. “Elavating the bottleneck?

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
10
Q

1st step in Goldratt?

A

Identify the binding constraint/bottleneck

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
11
Q

2nd step in Goldratt?

A

Exploit. The highest possible output must be achieved from the binding constraint

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
12
Q

3rd step in Goldratt?

A

Subordinate. Operations prior to the binding constraint should operate at the same speed as it so that WIP does not build up

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
13
Q

4th step in Goldratt?

A

Elevate the system’s bottleneck. Steps should be taken to increase resources or improve its efficiency

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
14
Q

5th step in Goldratt?

A

Return to Step 1. The removal of one bottleneck will create another elsewhere in the system

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
15
Q

Goldratt theory and one bottleneck resource?

A

As there is one bottleneck resource, all other resources in production aren’t bottlenecks and they will all have idle capacity

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
16
Q

Why should idle time should be accepted?

A

Since all operational costs are fixed, idle time is not costing any money

17
Q

What should be done with resources that aren’t bottlenecks?

A

Should not be used beyond the amount required for maximum achievable throughput, given the bottleneck resource

18
Q

What happens when using non-binding constraints beyond the amount required for maximum achievable throughput?

A

Leads to a build up of inventories

19
Q

Inventories in traditional cost accounting?

A

Improving efficiency and creating more inventory will increase profits. Higher inventories reduce cost of sales and increase reported profits

20
Q

Inventory levels in theory of constraints?

A

Using non-bottleneck resources above the amount required for maximum throughput is wasteful. It doesn’t increase throughput, only increases unused inventory levels