s Flashcards

1
Q

Which tool is consistently used to document the roles and responsibilities of a project?

The Role Administration Matrix

The Responsibility Assignment Matrix

The Staffing Management Plan

The Responsibility and Role Hierarchy

A

The Responsibility Assignment Matrix

The Responsibility Assignment Matrix (RAM) is used to document the roles and responsibilities of project team members. A type of RAM is the RACI chart, where the letters stand for Responsible, Accountable, Consult, and Inform.

There is no tool called the Role Administration Matrix.

There is no tool called the Responsibility and Role Hierarchy.

The Staffing Management Plan is a component of the Human Resource Plan. It forecasts what types of staff will work on a project, when they will be needed, how they will be recruited, and when they will be released from the project.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
2
Q

A real estate developer is preparing to begin work on a subdivision that will consist of 20 single-family homes. This will be a large undertaking, requiring the expertise of architects, construction managers, marketers, financial specialists, and attorneys. The developer recruits one person from each area to provide guidance and support throughout the work.

What is this team known as?

Coordinating committee

Stakeholders

Steering committee

Stockholders

A

Steering committee

A steering committee is a group of people who provide guidance to the project manager, program manager, or portfolio manager.

A stakeholder is someone who is affected by a project or who affects a project. Each person is a stakeholder, but the scenario mentions nothing about them working together in a coordinated fashion.

Stockholders own shares in a company; this is an incorrect term to describe the steering committee.

Coordinating committee is not the accepted project management term.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
3
Q

A project manager has decided to level the resources on a project.

Which of the following is not an advantage of resource leveling?

It shows when a resource might not be fully allocated to work on the project.

It can minimize overtime charges.

It results in a maximum number of work hours each day for a resource.

It can delay the finish date of the project.

A

It can delay the finish date of the project.

Resource leveling can delay the finish date of a project; this is a disadvantage.

Minimizing overtime charge can be an advantage of leveling.

Having resources work the maximum numbers of work hours each day is an advantage from a time management aspect.

Showing when a resource might not be fully allocated to work on a project is a positive as this can then be addressed if it needs to be.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
4
Q

What step will a project manager take to help prevent cash flow problems?

Make efforts to engage the finance department to put in place a cash flow forecast

Request additional funding from project sponsors

Use the contingency reserves of other projects

Make sure that customers are financially stable

A

Make efforts to engage the finance department to put in place a cash flow forecast

The finance department is the ultimate source of money for a project, and it is important to keep them aware of the financial needs of the project. If the project manager creates an initial forecast of cash flow and updates it throughout the project, the finance department will be kept in-tune with project cash needs.

Using the contingency reserves of other projects is unethical.

The financial stability of customers can change during a project, and it is not possible to walk away from a project if the customer is meeting the financial obligations of the project by paying invoices in a timely manner. If this is not the case, terms in the contract might be grounds to stop work and/or to close the project.

Additional funding should not be requested simply to solve cash flow problems.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
5
Q

The project to replace the bridge over the Troubled Waters stream has team members from the Public Works Department and six vendors, each with their own team. The project manager needs to keep this large group of stakeholders informed about the project.

Which plan contains the methods to do this?

Project management plan

Staffing management plan

Human resource plan

Communication plan

A

Communication plan

The communication plan keeps the stakeholders informed about the project. It identifies the audience (who), the types of information they should receive (what), the frequency (when), and the communication method and technology (how) that will be used.

The staffing management plan is part of the human resource plan that forecasts what types of staff will work on a project, when they will be needed, how they will be recruited, and when they will be released from the project.

The project management plan details how a project will be executed to achieve the specified objectives. It contains the communication plan and the human resource plan, and the human resource plan contains the staffing management plan.

The human resource plan provides guidance on how the human resources required for a project should be defined, staffed, managed, controlled, and eventually released after the end of the project.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
6
Q

Which of the following is true of project archives?

Should be handed to the sponsor at the end of the project

Should be updated only at the end of the project

Should include key information such as baselines and performance data

Should never contain computerized records because they may not be retrievable in later software versions

A

Should include key information such as baselines and performance data

Archives should contain data that can be useful when re-visiting a project after it is closed. Baselines (original as well as changes that were made during the project) and performance data relating to schedule and cost should be included.

Computerized records should be retained, and, if possible, the software that generated them should be archived also.

The sponsor is not the recipient of the project archives. There should be a formal repository where they are kept.

Archives should be updated throughout the project.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
7
Q

When you created your project plan, the sponsor wanted you to focus on completing the project in three months. Now, after four weeks, the sponsor is more concerned about how much the project will cost. He asks you to cut the cost by at least 10%.

To do this, you will likely need to do which of the following?

Use lower cost resources and extend the schedule

Extend the schedule

Hire more resources to get done earlier

Use higher skilled resources to get done earlier

A

Use lower cost resources and extend the schedule

Using lower cost resources can decrease the cost, but it will also extend the schedule.

Using higher cost resources to get done earlier might work, but cannot be guaranteed to do so.

Hiring more resources will increase cost even if they might finish sooner.

Just extending the schedule does not reduce the cost.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
8
Q

You have moved into executing the project plan for the Customer Resource Management (CRM) system and management announces that it is forming a project management office (PMO) and you now report to the PMO.

Which of the following is not a way in which your project is likely to be affected?

You will need a new team.

There might be a delay in project approvals.

You will need to review and update the stakeholder register.

You will need to update the communication plan.

A

You will need a new team.

It is likely that your team would still report to the same functional managers they did prior to the reorganization, so the team should not be affected.

You will have new/different stakeholders, which will affect the communication plan.

The project management office (PMO) management will likely need time to become acquainted with the active projects, which would delay decision-making.

Your stakeholders have changed, which means updates to the stakeholder register.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
9
Q

You are working on an external contract project to update the operating system on more than 1000 computers at an organization. The contract provides a penalty for taking more than three months to finish the work.

Which of the following is an example of accepting the risk?

Right now, the schedule looks like it will take three months, so you hire three new resources.

Right now, the schedule looks like it will take three months, so you leave it at that.

You purchase completion insurance to offset the penalty amount.

Right now, the schedule looks like it will take three months, so you do market research to see who might be available to hire if the schedule starts to slip.

A

Right now, the schedule looks like it will take three months, so you leave it at that.

Accept for negative risk means not doing anything proactively, which is what this option does.

Hiring new resources is an avoidance strategy to be sure to be done within the three-month time frame.

Having resources ready to go if needed is a mitigation strategy. It lowers the probability of missing the deadline if the schedule starts to slip and the additional resources are needed.

Insurance is a transfer response strategy.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
10
Q

Which of the following are the techniques that are used to acquire a team?

Acquisition, negotiation, networking, virtual team

Negotiation, interpersonal skills, networking, pre-assignment

Acquisition, negotiation, virtual team, pre-assignment

Interpersonal skills, negotiation, virtual team, acquisition

A

Acquisition, negotiation, virtual team, pre-assignment

Acquisition, negotiation, virtual team, and pre-assignment are techniques used for acquiring a team.

Negotiation, interpersonal skills, networking, pre-assignment is incorrect because interpersonal skills and networking are not techniques for acquiring a team.

Acquisition, negotiation, networking, virtual team is incorrect because networking is not a technique for acquiring a team.

Interpersonal skills, negotiation, virtual team, acquisition is incorrect because interpersonal skills is not a technique for acquiring a team.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
11
Q

You are finalizing a contract with a vendor for development of your new website and have a few remaining questions.

When you contact the vendor representative you’ve been dealing with, which of the following would you not need to consider?

Culture

Language

Intra-organizational communication patterns

Inter-organizational communication patterns

A

Intra-organizational communication patterns

Intra-organizational communication patterns are a consideration when you are communicating within your organization, not with an external person.

Inter-organizational communication patterns are a consideration because the vendor works for a different company, which may communicate differently than your company.

Language is a consideration because the vendor may speak a different language.

Culture is a consideration because the vendor may be from another culture.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
12
Q

You have moved into executing the project plan for the Customer Resource Management (CRM) system and the vendor you selected has split its company into two organizations.

What will likely happen to your project?

It will continue with a contract with the new company.

It will be canceled.

The project will be put on hold.

You and your team will be fired.

A

It will continue with a contract with the new company.

It is likely that a project already in execution would have been negotiated into the new company’s contract portfolio and will continue as planned.

The de-merger of the vendor will not affect your employment.

It is likely that a project already in execution would have been negotiated into the new company’s contract portfolio and will continue as planned.

Although the conversion would be postponed if the project was just starting, if you’re already executing, it would be a chance for the new company to prove it can still complete the work in progress.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
13
Q

In the Monitoring and Controlling phase of a project, where does information come from?

Project management plan and expert judgment

Project management plan and work performance information

Performance reports and expert judgment

Scope baseline

A

Project management plan and work performance information

Information for Monitoring and Controlling will come from the project management plan and work performance information. Remember that work performance information includes any data relating to the project.

Performance reports utilize work performance information, and if a report has been written, Monitoring and Controlling have been completed for whatever was the subject of the report. Expert judgment is not the best source of information upon which to make a decision about Controlling.

The scope baseline does not contain any data about actual conditions, and hence is not a source of information regarding Monitoring and Controlling.

Expert judgment is not the best source of information upon which to make a decision about Controlling.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
14
Q

A manager is using a tool to help determine which projects to execute, and to ensure that they match the strategic objectives of an organization.

What is the name of this tool?

Balanced scorecard

Dashboard

Key Performance Indicators (KPIs)

Key Performance Parameters (KPPs)

A

Balanced scorecard

A balanced scorecard is used in portfolio management to help determine which projects to execute, and to ensure that they match the strategic objectives of an organization.

Key Performance Parameters (KPPs) are key system capabilities that must be met for a system to meet its goals. KPPs are used in project management.

Key Performance Indicators (KPIs) in project management consist of tools that indicate if the project is meeting specific goals.

Dashboards are graphical summaries of project measures, often a collection of multiple KPIs.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
15
Q

Trey Research, Inc. and TailSpin Toys are exploring a joint venture, where Trey would design a robotic cat laser toy for TailSpin to manufacture and sell. Both companies would share in the eventual profits. Executives of the two companies have written a document that outlines the purpose of the joint venture, the roles and responsibilities of each company, financial considerations of the venture, and confidentiality considerations.

What is this document called?

Service Level Agreement (SLA)

Statement of Work (SOW)

Purchase Order (PO)

Memorandum of Understanding (MOU)

A

Memorandum of Understanding (MOU)

A Memorandum of Understanding (MOU) is an agreement between two or more parties to form a business partnership. It is not legally binding, but is used where the parties do not wish to enter into a formal contract.

A Service Level Agreement (SLA) is a contract between an organization that provides a service and the user of the service. The Trey/TailSpin Toys document does not fit this definition because the two companies are forming a joint venture.

A Statement of Work (SOW) is a document that describes the products or services that the project will supply, defines the business need that it is designed to meet, and specifies the work that will be done during the project.

A purchase order is a commercial document that is sent from a buyer to a seller, indicating types, quantities, and agreed prices for goods and services.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
16
Q

You are developing a new purchasing system for a client and want to know which constraint will have the greatest impact on the success of the project.

Which risk technique should you use?

Monte Carlo Simulation

Decision-tree analysis

Expected Monetary Value (EMV)

Sensitivity analysis

A

Sensitivity analysis

Sensitivity analysis looks at how sensitive various constraints (time, cost, scope) are to the success of the project.

Decision-tree analysis is used to determine best options, not to see which parameters are most important.

Monte Carlo Analysis is a special type of simulation that creates a range of, and probabilities for, potential results for time, cost, etc.

Expected Monetary Value (EMV) attaches quantifiable incomes and costs as impacts, allowing you to select the best option, not to see which parameters are most important.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
17
Q

The Public Works Dept. director has asked to see what the team has been working on for the past two weeks, after the charter for the new bridge over the Troubled Waters stream was approved.

What is the name of the comprehensive document that is used during project Execution, Monitoring And Controlling, and Closing?

Integration plan

Project framework

Execution plan

Project management plan

A

Project management plan

The project management plan contains all of the information needed to guide the project through Execution, Monitoring and Controlling, and Closing.

There is no document called the execution plan.

There is no document called the integration plan.

The project framework is not a document, but a model that is used to manage projects.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
18
Q

You are working on moving the in-house Human Resources Management System (HRMS) to a cloud self-service provider. One of your team members submitted a change request that will increase the project budget by 15%. You are creating a back-out plan in case the change is approved and implemented but doesn’t work as intended.

What process are you performing?

Regression analysis

Identify approval authority

Obtain approval

Regression plannin

A

Regression planning

You perform regression planning as part of evaluating a change to determine how to back it out if it doesn’t work.

You obtain approval after you identify approval authority.

You determine the levels of authority required for approving various sizes of changes after you perform regression planning.

Regression analysis is a quality process.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
19
Q

33

A

Key Performance Indicators (KPIs)

These are examples of Key Performance Indicators (KPIs). They represent a snapshot of how a project is doing at a point in time.

Key Performance Parameters (KPPs) are used by the U.S Department of Defense and other federal government organizations to specify critical performance goals of a system that will be acquired from outside the government.

Earned Value Management (EVM) is a common way to evaluate the performance of a project in terms of scope, schedule, and cost. EVM has a number of metrics associated with it, but they are not called Earned Value Indicators.

A wiki is a website where documents can be stored and collaboratively modified using a web browser. Links to other documents stored within and outside of the wiki can be included.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
20
Q

Alpine Ski House owns and operates three ski lodges in the Rocky Mountains. The company wants to expand, and the board of directors has authorized the construction of five new facilities in the Sierra Nevada Mountains of California and Nevada. The directors have a strategic objective of being the preferred go-to resorts for seniors and retirees within 10 years. Projects related to this goal that are under consideration include obtaining venture-capital financing, new marketing campaigns, acquiring new land, completing facility construction, and establishing franchises; they may be completed separately for each of the five new ski resorts.

What type of project organizational structure will be involved at the corporate level?

Mega-project

Program

Portfolio

Multiple-project

A

Portfolio

The expansion projects will be managed as a portfolio. All the projects will be tied to the strategic objective of being the preferred go-to resorts. Within the portfolio will be programs, projects within each program, and eventually operations to manage each new lodge.

A program is a group of related projects. All of the projects are related, but the link to a strategic objective makes the new venture a portfolio.

There is no multi-project management structure within the project management framework.

There is no mega-project management structure within the project management framework.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
21
Q

You are working on an update to the corporate website and project execution has started.

As your team members work with one another, what is an advantage of communicating via instant messaging?

The communication is considered unofficial.

The communication cannot be saved or forwarded.

The communication is immediate.

The communication content is limited.

A

The communication is immediate.

Communication with instant messaging is immediate.

A disadvantage of instant messaging is that it may be viewed as unofficial/unimportant.

A disadvantage of instant messaging is that it has limited content capabilities, such as formatting, attachments, and sometimes message lengths.

Instant messages can be saved or forwarded.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
22
Q

In the absence of the project manager in a large project, which of the following stakeholders would make time- and resource-scheduling decisions?

Individual resources

Work package owners

Sponsor

Project coordinator

A

Project coordinator

The project coordinator would make decisions about time and the scheduling of work.

The sponsor does not have day-to-day project management responsibilities

Work package owners do not have responsibility for scheduling their own work. This should come from a higher level.

Individual resources do not have responsibility for scheduling their own work. This should come from a higher level.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
23
Q

37

A

75 percent

The correct value is 75 percent. The Pareto chart would show that the top three problems accounted for 300 occurrences out of the 400 total occurrences, or 75 percent.

55 is incorrect because the table shows that the top three problems accounted for 300 occurrences out of the 400 total occurrences, or 75 percent.

90 is incorrect because the table shows that the top three problems accounted for 300 occurrences out of the 400 total occurrences, or 75 percent.

50 is incorrect because the table shows that the top three problems accounted for 300 occurrences out of the 400 total occurrences, or 75 percent.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
24
Q

Ten steps are necessary to fill a bottle of water in an automated process. These steps start with placing an empty bottle onto a moving conveyer, and end with the filled bottle being placed into a carton after it has been checked by a photocell and confirmed to be full. Bottles are being consistently underfilled by 10 percent.

What tool would the quality engineer use to look for the cause of this problem?

Process flow diagram

Scatter chart

Run chart

Histogra

A

Process flow diagram

A process flow diagram, or flowchart, is a diagram that shows the inputs, steps, and outputs of a process. It would be used to examine which step in the filling process is the source of the problem.

A scatter chart, or scatter diagram, is used to examine the correlation between an independent variable and a dependent variable. It will not help find the source of the problem.

A run chart is a line graph showing plotted data points in chronological order. It will show trends in a process or improvements over time, but it would not pinpoint the source of the problem.

A histogram is a bar chart that can show the frequency distribution of the amount of water in the bottles, but it will not show the source of the problem.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
25
Q

You are executing, monitoring, and controlling your project, so you are comparing the amount of scope that should have been done by now to what has been done.

You are conducting:

Variance analysis

Inspection

Decomposition

Quality control

A

Variance analysis

When you are comparing a plan to actual data and looking for differences, you are conducting variance analysis.

Quality control compares the deliverables to the requirements, not scope of work completed to that which should have been completed.

Inspection examines deliverables for defects. It does not analyze scope progress.

Decomposition is the process used to create a Work Breakdown Structure (WBS), not analyze progress on its tasks.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
26
Q

Which of the following is the best indicator of project performance?

The budget for developing the software was $150,000, and the actual amount spent was $120,000.

Three experienced project team members were replaced by inexperienced staff because they left the company.

A new regulation might be published before the project ends, and if so, the project plan will need to be revised.

There have been 15 change requests, 10 of which were approved.

A

The budget for developing the software was $150,000, and the actual amount spent was $120,000.

The best performance indicator of the choices given would be budgeted versus actual spending for a component of the project. It is quantitative and verifiable.

Data on the number of change requests is not a measurable indicator of how the project is progressing.

The replacement of experienced team members with inexperienced ones does not indicate anything about project performance. The inexperienced team members might have done quality work at less cost, or poor work at more cost—there is not enough information given to form any conclusions.

The new regulation might not be published; this is a risk, not an indicator of performance.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
27
Q

Who provides standard documentation and templates for projects?

Project Management Office (PMO)

Project Management Institute (PMI)

Senior management of the organization

Sponsor

A

Project Management Office (PMO)

The Project Management Office (PMO) within an organization provides the documentation and templates that projects can use so projects within the organization have the same “look and feel.”

Sponsors are champions for their projects, but they do not provide documentation and templates for them to use.

Senior management resolves conflicts between projects and day-to-day business operations.

The Project Management Institute (PMI) publishes a standard for project management and a framework that projects can use, but it does not provide sample documents or templates.

28
Q

A client has requested a three-week delay in the order-entry system project due to unanticipated hardware issues at their headquarters’ office. The project manager has incorporated the delay into the project management plan.

In which document will the delay be best shown?

Gantt chart

Work breakdown Structure (WBS)

Responsible Accountable Consult Inform (RACI) matrix

Run chart

A

Gantt chart

The Gantt chart depicts schedule information, with activities and links between them. The delay can be shown as a three-week lag between the last activity scheduled to finish before the delay and the first activity scheduled to start after the delay.

The WBS does not show time, so the delay will not be apparent.

The RACI matrix contains information about resources, not schedule data.

The run chart is a line graph showing plotted data points in chronological order. It is used in quality control and not for showing a project schedule.

29
Q

You are developing a new website for your organization and you are starting to identify and prioritize risks. You are meeting with the team and they are throwing out potential risks as fast as possible while you document them.

What specifically are you doing?

Reviewing the documentation on previous project risks

Using the Delphi technique to identify risks

Interviewing the team to gather a list of risks and probabilities

Using the brainstorming technique to come up with all the risks

A

Using the brainstorming technique to come up with all the risks

Brainstorming is an information gathering technique that allows groups to create a list of potential risk events.

Delphi technique is an information gathering technique that allows groups to come to a consensus.

Documentation review is an identification technique, but not part of the brainstorming technique.

Interviewing is an information gathering technique that allows you to work with a wide cross section of stakeholders to determine potential risks, not usually just the team.

30
Q

Which conflict resolution technique solves the root cause of a problem?

Avoiding

Confronting

Smoothing

Forcing

A

Confronting

Confronting a conflict is the only technique that solves the root cause of a problem. The parties dig to explore and find the true cause of the problem, then to find a solution that removes the problem from further consideration.

Forcing does not solve the root cause of a problem; it simply mandates a course of action.

Smoothing attempts to minimize a problem, by convincing the parties that they do not really have a disagreement.

Avoiding leaves the problem in place and simply does nothing about it.

31
Q

The sponsor of the robotic cat laser project has asked to see a project dashboard every two weeks.

Which of the following are examples of dashboard information?

Number of milestones due next month, date when charter approved

Issue log, number of activities completed last week

Project percent complete, number of milestones completed

Project percent complete, project requirements list

A

Project percent complete, number of milestones completed

Project percent complete and the number of milestones completed to date are two examples of information that might be included on a dashboard.

A list of project requirements is not indicative of project status and does not constitute information found on a dashboard; the other choices are valid examples.

An issue log is a project management deliverable and not a dashboard item; the other choices are valid examples.

Specific dates of project management deliverables will not appear on a dashboard; the other choices are valid examples.

32
Q

You are bidding on an external contract project to update the operating system on more than 1000 computers at an organization. You realize you don’t have enough resources to complete the project as specified, so you partner with another firm to split the work.

This is an example of which type of response strategy?

Exploit

Share

Enhance

Accept

A

Share

Share means you are splitting the benefits of the opportunity with others in some way, which you are doing by splitting a contract.

Enhance means nudging the opportunity a little to encourage it to happen, but doesn’t make it happen.

Accept for positive risk means you’re ready to make use of it if it occurs, but you don’t do anything proactively to change its probability of occurring.

Exploit means proactively going after an opportunity to make it a reality.

33
Q

An engineer working on the Awesome Computers wireless network upgrade project asks the project manager to clarify some of the scheduling terms, specifically predecessor and successor.

What determines whether a task is a predecessor to another task, if the two tasks are linked together?

The scheduling software will determine which task is the predecessor.

A task that has a higher risk than the other task is always the predecessor.

A task that drives the relationship with the other task is always the predecessor.

A task that occurs earlier in time than the other task is always the predecessor.

A

A task that drives the relationship with the other task is always the predecessor.

A predecessor task is defined as one that logically comes before another one. Logically means driving the relationship.

In most relationships, the earlier (in time) task is the predecessor. However in a start-to-finish relationship, when the predecessor starts the successor can finish. This means that the successor task started before the predecessor started. This demonstrates that predecessor does not always mean starts earlier in time.

Relative risk of two tasks does not determine precedence.

Software does not determine which task is the predecessor; it is determined by the type of relationship, which a software user will input.

34
Q

You are working on a project to upgrade the enterprise resource planning (ERP) system, which includes a purchasing system and a new sales system. The project will take nearly a year, and three months in, management decides that at least the new sales system component must be implemented by year-end, two months earlier than originally planned.

This is an example of what type of change?

Funding change

Scope change

Requirements change

Timeline change

A

Timeline change

Timeline changes increase or decrease the schedule.

A funding change increases or decreases the budget/cost.

Requirements changes affect the parameters that define the deliverables.

A scope change increases or decreases the work the project must accomplish.

35
Q

A health care consultancy has a help desk that businesses can subscribe to. The standard contract states that 95 percent of the help desk calls will be answered with less than 10 minutes of hold time, or one percent of the monthly subscription fee will be refunded.

This is an example of what?

Express warranty

Service Level Agreement (SLA)

Implied warranty

Letter of intent

A

Service Level Agreement (SLA)

A Service Level Agreement (SLA) is a contract between an organization that provides a service and the user of the service. The contract specifies what the customer will receive and the performance standards or level of service the provider is obligated to meet.

A letter of intent is a document that outlines an agreement between two parties before the agreement is finalized.

An express warranty is an explicit promise that goods or services will meet a predetermined standard. The standard is specified either in a formal warranty or in the manufacturer’s description of the product.

An implied warranty is an unwritten promise that goods or services will meet a predetermined standard.

36
Q

Two network administrators are having a disagreement about a technical issue that can delay the finish date of the project, and they seek help from the project manager.

Which of the following actions should the project manager propose?

Tell the team members that their problem does not seem very significant and to work around it.

Meet with the network administrators and learn what is causing them to disagree.

Read any technical documentation about the issue.

Tell the two people to find a solution by themselves, as they are more technically savvy about the problem.

A

Meet with the network administrators and learn what is causing them to disagree.

Until the root cause of the problem has been identified, there is little hope that any solution will be the correct one. The network administrators should find the cause of their disagreement, and then work on developing a resolution to it. This is an example of confronting a problem.

Telling the network administrators to solve the problem by themselves is a case of the project manager avoiding the problem. This will erode his or her credibility and will not necessarily lead to the best solution.

Reading technical documents will help, but this step does not go far enough toward finding the root cause of the problem.

By declaring that the problem is not significant, the project manager is using smoothing, which would be the wrong technique if the problem is truly important.

37
Q

The project team has been working diligently to meet all of the milestones of their project. Acceptance of the interim and final deliverables is a key objective.

What should the deliverables be compared to?

The initial cost estimate

The actuals

The variance

The current baselines

A

The current baselines

Deliverables should be measured against the current baselines: scope, schedule, and time. Changes to the project will cause these baseline values to change, and the most recent approved baselines should be used.

Actuals represent the present state of a deliverable and not a comparison to anything.

Variances are the difference between planned and actual values and are an indication of deviations in scope, schedule, and time. They need to be compared to something, and that will be the current baselines.

The initial cost estimate was developed before much (if any) planning was done, and it is not indicative of the current state of the project. Also, cost is only one of the project objectives.

38
Q

Who sets the standards and practices for managing projects within an organization?

Project Management Office (PMO)

Senior management of the organization

The Project Management Institute (PMI)

A group of senior project managers appointed by senior management of the organization

A

Project Management Office (PMO)

Project management standards and practices are set by the Project Management Office (PMO), and standards and practices are used by all projects governed by the PMO.

A group of senior project managers does not have the authority to set standards and practices.

Senior management does not set project management standards and practices.

The PMI publishes A Guide to the Project Management Body of Knowledge (PMBOK Guide), an ANSI Standard which serves as a general framework for managing projects. Organizations are not required to follow it.

39
Q

You are working on a project to upgrade the enterprise resource planning (ERP) system, which includes a purchasing system and a new sales system. You are planning the kick-off meeting and you have remote stakeholders who work from home, some in rural areas without broadband connectivity.

Which is the best method for holding the kick-off meeting?

Voice conference/Teleconference

In-person meeting

Video conference

Instant message meeting

A

Voice conference/Teleconference

Voice conferences (Teleconferences or audio-only web conferences) would allow team members without broadband to still actively participate.

Video conference meetings would not be possible without broadband connectivity. The latency would be too great to hold effective conversations.

It would be difficult to bring remote workers to in-person meetings on more than a few significant occasions such as kick-off or closing meetings.

Instant messaging is not designed for meetings.

40
Q

The team to build a new home for the town mayor is behind schedule, and the mayor is threatening to fire the team and bring in another contractor to finish the job. To avoid this, the project manager decides to add more resources to activities on the critical path.

What is this called?

Staff augmentation

Crashing

Rolling-wave planning

Fast-tracking

A

Crashing

Crashing shortens the project schedule for the least incremental cost by adding resources to activities on the critical path.

Fast-tracking (doing activities in parallel, with a lead time) is used to shorten the project schedule. Adding resources is not fast-tracking.

Rolling-wave planning is a scheduling technique in which work to be accomplished in the near term is planned in more detail than work in the future. This will not shorten the schedule.

Staff augmentation is not a project management term, but a standard definition would say that it means adding staff. This will not shorten the schedule.

41
Q

Which tool is appropriate for analyzing and communicating the relationships between process steps?

Trend analysis

Process flow diagram

Control charts

Scatter chart

A

Process flow diagram

A process flow diagram, or flowchart, is a diagram that shows the inputs, steps, and outputs of a process.

A control chart depicts the variability of process data over time. It includes a target mean value and upper and lower control limits; values that exceed these limits are indicative of an out-of-control process.

A scatter chart, or scatter diagram, is used to examine the correlation between an independent variable and a dependent variable.

A trend analysis forecasts future outcomes based upon historical data.

42
Q

62

A

26 Weeks

The duration of the critical path is 27 weeks. It is calculated by adding the durations of each activity on each path and selecting the path with the longest duration. The critical activities are ABCE.

ABE is 17 weeks.

ADE is 13 weeks.

ACE is 20 weeks.

43
Q

Which of the following statements is not true about the Initiation phase of a project?

It justifies the reasons for undertaking the project.

It specifies the high-level scope of what will be undertaken in the project.

It assigns the project manager.

It identifies the type of contract that is part of the procurement plan

A

It identifies the type of contract that is part of the procurement plan.

The purpose of Initiating is to kick off the project. Contracts are first introduced in planning when the procurement plan is prepared.

The other options are true about Initiating.

44
Q

The original project plan you created contained six deliverables each requiring equal effort and duration. Through formal change control, another four deliverables - equal in effort and duration - were added to the plan. You have completed one of the original deliverables and two of the new.

Based solely on the progress of the deliverables, you can tell the stakeholders that the project is currently:

30% complete

50% complete

75% complete

Impossible to tell at this point

A

30% complete

You have completed three of a total of ten deliverables of equal effort and duration, which means you are 30% complete.

Since all deliverables are of equal effort and duration, you need to add the new approved deliverables to the count, so three of ten are complete, not three of six.

You are not just counting the four new deliverables; you are counting all ten of the deliverables of equal effort and duration.

Since all deliverables are of equal effort and duration, this can be calculated by adding the total number of original deliverables to the new deliverables and then dividing the actuals by ten.

45
Q

In a weak matrix organization, who has more power?

Functional managers

Project coordinators

Project managers

Program managers

A

Functional managers

In a weak matrix organization, functional managers have more power than project managers.

Program managers manage multiple project managers, and the scenario does not address programs.

Project managers have more power in a strong matrix organization.

Project coordinators support project managers, and in a weak matrix organization would have less power than functional managers.

46
Q

Which tool is used to collect, archive, and distribute project information so that project performance can be determined?

The project management plan

The communications plan

The communications and feedback system

The Project Management Information System (PMIS)

A

The Project Management Information System (PMIS)

The Project Management Information System (PMIS) is an automated or manual system used by a project team to gather, analyze, communicate, and store project information. It is used to determine project performance.

The communications plan is a document that describes the project team’s approach to communicating project information.

There is no communications and feedback system.

The project management plan is a comprehensive document that describes how the project will be executed, monitored, and controlled. It is not a tool.

47
Q

Who has the responsibility to “market” a project to stakeholders who either see no benefit to the project or who are opposed to it?

Team members

Sponsor

Project manager

Functional managers

A

Sponsor

The sponsor is the “champion” of the project, and he or she is responsible for its success. One of a sponsor’s roles is to minimize the impact of negative stakeholders so the project can move forward.

The project manager can work with any negative stakeholders, but he or she will benefit from a more senior person like a sponsor who is more influential.

Functional managers are responsible for providing resources to the project. They should be positive about the project, but it is not their responsibility to build buy-in from reluctant stakeholders.

Team members are responsible for completing their assigned tasks. They should be positive about the project, but it is not their responsibility to build buy-in from reluctant stakeholders.

48
Q

Which statement best describes a project?

Something that produces multiple products, services, or results

Something that produces a unique product, service, or result and does not have a start date or end date

Something that produces a unique product, service, or result and is ongoing

Something that produces a unique product, service, or result and has a start date and end date

A

Something that produces a unique product, service, or result and has a start date and end date

A project produces a unique product, service, or result and has a start date and end date; for example writing a new book.

An operation is ongoing, without start or end dates; for example filling customer orders for a book.

Multiple projects, not a single project, produce multiple products, services, or results; for example translating a book written by a single author into multiple languages.

Something that produces a product, service, or result and does not have a start date or and end date is neither a project nor an operation; it has no definition in the realm of project management.

49
Q

A project manager is developing a definitive cost estimate.

Which of the following would be most beneficial?

A cost estimate from a previous project

Work Breakdown Structure (WBS)

Scope

Target cost estimate from the sponsor

A

Work Breakdown Structure (WBS)

A definitive cost estimate is intended to be very accurate, so it is based on detailed information about the project. The WBS forms the basis for this estimate because it includes the cost for each work package.

A cost estimate from a previous project will not give the level of accuracy needed for a definitive estimate because the two projects will not be identical enough to provide a high degree of accuracy in the estimate.

The scope statement does not contain the level of detail needed for a definitive estimate.

A sponsor’s target, while possibly very specific, contains no detail about the scope or the WBS that results from it.

50
Q

During the Monitoring and Controlling phase, which two types of data are compared to produce which result?

The quality management plan and deliverables are used to prepare change requests.

The sponsor’s goals and the project objectives are used to prepare a compromised scope.

The budget and actual expenditures are used to find the final project cost.

The project management plan and work performance information are used to generate variances.

A

The project management plan and work performance information are used to generate variances.

The project management plan and work performance information are used to generate variances. Remember that work performance information includes any data about the project and its status. For example, comparing the cost spent on a task with what was to be spent according to the plan will result in the cost variance.

A forecast of the final cost is not a calculation that involves the budget and actual expenditures; it must also consider how much work has been done and how much additional work will be needed to finish the project.

Goals and objectives are not compared during Monitoring and Controlling because neither represents actual data.

Change requests result from the quality management plan and quality control measurements, not deliverables.

51
Q

Fabrikam has entered into a contract with AdventureWorks Cycles to manufacture components for the new high-speed braking system. Of the three basic types of contracts—fixed-price, cost-reimbursable, and time-and-material—which type has the most risk for the vendor, Fabrikam?

Time-and-material

Cost-reimbursable

There is no way to know without more information.

Fixed-price

A

Fixed-price

A fixed-price contract is the riskiest for the vendor. The scope is very specific, and the buyer knows exactly what they want and have requested. Any cost overrun must be borne by the vendor.

A time-and-material contract is the riskiest for the buyer. The buyer pays for the cost of materials and a time-based (hourly or daily) labor rate. Any cost overruns are borne by the buyer because neither the time nor the costs are fixed.

A cost-reimbursable contract is the riskiest for the buyer. The buyer pays for the cost of materials and a fee to compensate the vendor. Any cost overruns are borne by the buyer because the costs of materials are not fixed.

No more information is needed to determine which contract type is riskiest for either the buyer or the vendor.

52
Q

The project team for the WingTip Toys mini-drone project is using bottom-up estimating to build a schedule.

Which of the following is not an advantage to the project if they use this type of estimate?

It helps the team buy in to the project.

It includes supporting details about the activities in the schedule.

It is time-consuming to create.

It is more accurate than other techniques.

A

It is time-consuming to create.

Bottom-up estimating takes more time than other techniques which is not a benefit. If the team needs to create an estimate quickly, another technique should be used.

All other options are advantages.

53
Q

Which of the following is a role of a project coordinator?

Support the project manager and assist in administrative tasks

Serve as liaison between multiple projects

There is no project coordinator position in a project

As a member of a Project Management Office (PMO) steering committee, review all projects for conformance with PMO practices

A

Support the project manager and assist in administrative tasks

The project coordinator supports and assists the project manager, as dictated by the size and complexity of a project. Not all projects have project coordinators.

The project coordinator is a member of a single project team, and is not responsible for cross-project coordination.

The project coordinator is not a member of the Project Management Office.

The project coordinator is a legitimate role in a project team.

54
Q

What is true of lessons learned during the project?

Should consist of only things that went well during project execution

Should be documented throughout the project

Should consist of only project data

Should be documented only in the closeout report

A

Should be documented throughout the project

It is essential to document lessons learned throughout the duration of the project, so none are forgotten. This is especially important with long projects.

If lessons learned are not documented until project closeout, many can be lost due to poor memories.

Lessons learned should include project management issues as well as project deliverable issues.

Although it is natural to want to forget things that did not go well, these negative points can be useful to future projects as well as the positive points.

55
Q

You have moved into executing the project plan for the new website design when your company announces that it is being acquired by another company.

Which of the following is not a way in which your project is likely to be affected?

The project will be put on hold.

Your project budget will be increased.

You may have a new sponsor who will want to make changes in your direction.

The project will be canceled.

A

Your project budget will be increased.

If there is an effect on budget from the acquisition, it would likely decrease it, not increase it.

In an acquisition, your company is subsumed by another, which will likely have its own website already.

Depending on how management has changed because of the merger, there may be a new sponsor who may want to change the project.

While the company finalizes its new goals, it is very likely the new website project will be put on hold.

56
Q

Another higher priority project has been started that requires the highly skilled resources assigned to your project. They will not be available to you for two weeks.

Which of the following is not an option for your project?

Keep the resources working on your project

Postpone the current project until the resources are available

Hire temporary resources to continue the work of the reassigned resources

Continue working on the project tasks not being performed by those resources

A

Keep the resources working on your project

Management has reassigned the resources, so you cannot override the decision and keep your resources working on your project.

Presuming there are other tasks not assigned to, and not dependent on, the tasks assigned to the pulled resources, work on those other tasks can continue.

If all the remaining work on the project depends on the work of the pulled resources, it would be necessary to stop until they become available.

Depending on the budget, you may be able to hire temporary replacements for your resources.

57
Q

You are developing a new payroll system for your organization and you are starting to identify and prioritize risks. You are using a hierarchical chart showing risk categories by common sources.

This is referred to as a(n):

Risk Breakdown Structure (RBS)

Work Breakdown Structure (WBS)

Ishikawa diagram

Risk Probability and Impact Matrix

A

Risk Breakdown Structure (RBS)

The hierarchical chart that organizes risk categories by their sources is called a Risk Breakdown Structure (RBS).

Work Breakdown Structures (WBS) are hierarchical charts that organize a project’s work by deliverable, phase, or type of work.

An Ishikawa diagram shows the cause and effect of a variety of problems.

A Risk Probability and Impact Matrix shows how you might evaluate risks, but not identify or categorize them.

58
Q

You are working on a project to upgrade the enterprise resource planning (ERP) system, which includes a purchasing system and a new sales system. There is concern that the new system will not be implemented in time to meet the demand for Halloween candy orders, which is historically your biggest sales season. You decide to delay implementation to August, which is past the July rush for Halloween orders.

This is an example of which type of risk response?

Mitigate

Accept

Avoid

Transfer

A

Avoid

By moving the implementation date, you avoid the potential effect on sales.

Mitigate lowers the chance of, or the effects of, a risk event.

Accept means you do nothing proactively.

Transfer gives the risk to someone else, usually by purchasing insurance.

59
Q

You are working on moving the in-house Human Resources Management System (HRMS) to a cloud self-service provider. Your vendor has noted that it will not have your servers online until two weeks after it was supposed to get them online.

This is an example of what type of change?

Requirements change

Funding change

Scope change

Timeline change

A

Timeline change

Timeline changes increase or decrease the schedule.

A funding change increases or decreases the budget/cost.

Requirements changes affect the parameters that define the deliverables.

A scope change increases or decreases the work the project must accomplish.

60
Q

You are working on a project to upgrade the Human Resources Management System (HRMS). You are going to be using a new in-house server that is being installed as its own project.

Which of the following is not within the scope of the server project?

Training the server administrators

Connecting the new server to the rest of the network servers

Creating a server backup plan

Installing the Human Resources Management System (HRMS)

A

Installing the Human Resources Management System (HRMS)

The installation of the Human Resources Management System (HRMS) is within the scope of your project, not the server project.

Creating a server backup/recovery plan is within the scope of the server project.

The training for the server is within the scope of the server project.

Connecting the new server to any existing servers is within the scope of the server project.

61
Q

You are working on a project to select and install a new Customer Relationship Management (CRM) system.

Which of the following would not be considered stakeholders in this project?

Regional Managers of Sales and Marketing

Vice President of Sales and Marketing

Accounts Payable clerks

Salespeople

A

Accounts Payable clerks

Accounts Payable clerks work with financial systems to pay vendors, and do not work with customers.

Regional Sales and Marketing Managers would be stakeholders because they and their teams would work heavily with customers and customer data.

The Vice President of Sales and Marketing would likely be the sponsor of a new Customer Relationship Management (CRM) system, and the most important stakeholder.

Salespeople would be required to use the new system to track all customer contact and would be the end users of the new system.

62
Q

You are working on an update to the corporate website and you are close enough to open it for beta testing.

What is NOT a good method for getting a large number of people outside the company to volunteer to be beta testers?

Send an email

Post a note on your Facebook page

Post a call for volunteers on LinkedIn

Tweet to your followers

A

Send an email

Although it is easy to email, you would need to have the email addresses of everyone you wanted to notify.

A post on any/all of the popular social media sites is a good way to quickly attract a large number of participants without having to know any contact information.

63
Q

You are working on moving the in-house Human Resources Management System (HRMS) to a cloud self-service provider. One of your key team members leaves the organization and you hire a new consultant.

This is an example of what type of change?

Quality change

Resource change

Risk event

Requirements change

A

Resource change

A resource change can affect a number of the project’s constraints. In this case it will likely affect cost and schedule as the new consultant comes up to speed.

A quality change increases or decreases the work needed to assure and control quality.

A risk event that occurs can affect a number of the project’s constraints. This change is specific to personnel.

Requirements changes affect the parameters that define the deliverables.

64
Q

Ten steps are necessary to fill a bottle of water in an automated process. These steps start with placing an empty bottle onto a moving conveyer, and end with the filled bottle being placed into a carton after it has been checked by a photocell and confirmed to be full. Bottles are being consistently underfilled by 10 percent.

What tool would the quality engineer use to look for the cause of this problem?

Process flow diagram

Scatter chart

Run chart

Histogram

A

Process flow diagram

A process flow diagram, or flowchart, is a diagram that shows the inputs, steps, and outputs of a process. It would be used to examine which step in the filling process is the source of the problem.

A scatter chart, or scatter diagram, is used to examine the correlation between an independent variable and a dependent variable. It will not help find the source of the problem.

A run chart is a line graph showing plotted data points in chronological order. It will show trends in a process or improvements over time, but it would not pinpoint the source of the problem.

A histogram is a bar chart that can show the frequency distribution of the amount of water in the bottles, but it will not show the source of the problem.

65
Q

Who should sign off on the completion of the project?

Organization’s manager of quality assurance

Sponsor and an external client, if there is one

Senior management

Project manager

A

Sponsor and an external client, if there is one

One of the responsibilities of the project sponsor is to confirm that the objectives and requirements were met. This is accomplished with a formal signed document. If an external client was involved, a member of that organization should also sign a statement that the project met the organization’s project objectives.

Senior management is not in the formal chain of command for the project.

The project manager should not sign off that the project was completed successfully; this is a sponsor responsibility.

The manager of quality assurance is not in the project’s chain of command.

66
Q

You are working on a new purchasing system project and are getting ready to end the project. You want to have a meeting with your key team members and other stakeholders to review how the project went, to document lessons learned, and to celebrate project success, but most of them do not want to travel to your location.

Why might you still schedule and hold an onsite meeting?

Only the stakeholders who can make it should be there anyway.

People who do not want to travel would not participate in a virtual meeting either.

You are the project manager and it is your decision.

Closing out the project in person helps build relationships needed for subsequent projects.

A

Closing out the project in person helps build relationships needed for subsequent projects.

Even though you are closing the project, it is likely the stakeholders will work together again, and this is a good way to maintain positive relationships.

Although it is certainly true that you can do as you want, meeting in person is a better idea because it is likely the stakeholders will work together again, and this is a good way to maintain positive relationships.

The input from all the stakeholders is important and it is likely the stakeholders will work together again, so meeting in person is a good way to maintain positive relationships.

It might be the case that some of the stakeholders may not participate even in a virtual environment, but, more importantly, it is likely the stakeholders will work together again and meeting in person is a good way to maintain positive relationships.