Chapter 5 Flashcards
A Project Schedule is used for ________
Waterfall Projects
Sprint Planning is used for _________
Agile Projects
Work Breakdown Structure is apart of ________
Scope Planning
WBS
Work Breadown Structure
A deliverables-oriented hierarchy that defines all the work of the project.
Work Breakdown Structure (WBS)
The process of breaking down the high-level deliverables into smaller, more manageable work
Decomposition
What is the basis for estimating activity duration, assigning resources to activities, estimating work effort, and creating a budget.
Work Breakdown Structure (WBS)
Contains additional details of the deliverables than the Scope Statement does.
Work Breakdown Structure (WBS)
A Work Breakdown Structure (WBS) starts with the project itelsf at which level?
Topmost
What is the lowest level of any Work Breakdown Structure (WBS) called?
Work Package Level
Which level of a Work Breakdown Structure (WBS) are resources, time, and cost estimates determined?
Work Package Level (Lowest Level)
Each level in the Work Breakdown Structure (WBS) should have a ___________.
Unique Identifier
In a Work Breakdown Structure (WBS), what is a numeric identifier known as?
Code of Accounts
What is this image an example of?
Code of Accounts
Where the Work Breakdown Structure (WBS) levels and work ocmponent descriptions are documented
WBS Dictionary
Where should these be recorded?
WBS Dictionary
Defines how to project is executed, how you’ll measure performance, and how it’s closed
Project Management Plan
All the documents and plans you’ll be using for a project make up the __________.
Project Management Plan
Together, the scope, schedule, and cost baseline make up what’s called the ___________.
Performance Measurement Baseline
Once you have approval and sign-offs, the project management plan is __________.
Baselined
Once you have an approved Scope Statement, a Work Breakdown Structure (WBS), and a WBS Dictionary, you have what is known as the ___________.
Scope Baseline
When is the project schedlue developed?
After the Work Breakdown Structure (WBS) is completed
What documents the planned start and finish dates of each of the tasks included on the project?
The Schedule
The total project duration is calculated once the ________ is complete
Schedule
The total project duration is calculated once the ________ is complete
Schedule
What is the foundation for developing a project schedule?
Defining the list of tasks required to complete the project deliverables
Where should each acvtivity you’ve defined be placed?
Activity List/Task List
The process of identifying dependency relationships between project activities and filing them in proper order
Sequencing
___________ are relationships between activities
Dependencies
A relationship between a project task and some factor outside the project that drives the scheduling of that task
External Dependency
A relationship between tasks within an individual project or within the organization
Internal Dependencies
Dependencies directly related to the type of work being performed. (AKA Hard Logic)
Mandatory Dependencies
A dependency that is defined by the project team and is usually a process-or-procedure-driver. (AKA Soft Logic)
Discretionary Dependency
An activity that comes before another activity
Predecessor
An activity that comes after athe activity in question
Successor
What is established so you can sequence tasks properly?
Logical Relationship
What are the four Logical Relationships?
Finish-to-Start
Start-to-Finish
Finish-to-Finish
Start-to-Start
FS
Finish-to-Start
SS
Start-to-Start
SF
Start-to-Finish
FF
Finish-to-Finish
A relationship where the successor activity cannot begin until the predecessor activity has completed. (The most frequently used Logical Relatinship)
Finish-to-Start
A relatipnship where the predecessor activity must start before the successor activity can finish
Start-to-Finish
A relatinpship where the predecessor activity must finish before the successor activity finishes
Finish-to-Finish
A relationship where the predecessor activity must start before the successor activity can start
Start-to-Start
What is the next step after the activity dependency relationships have been identified?
Creating a network diagram
Depicts the project activities and the interrelationships among these activities
Network Diagram
What is the most commonly used network diagram method?
Precedence Diagramming Method (PDM)