Regulatory Reporting Requirements (XI1.ID2) Flashcards

1
Q

XI1.ID2

What are the two conditions that would require a 1 hour report to the NRC?

A
  • Emergency Event (any declaration of……:)
    • Unusual Event
    • Alert
    • Site Area Emergency
    • General Emergency
  • Non-Emergency Event
    • Deviation from license (T.S.) via 10 CFR 50.54 X
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
2
Q

XI1.ID2

What are the conditions that warrant 4 hour report to NRC?

A
  • Initiation of a T.S. Required shutdown
  • ECCS actuation that results or should have resulted in a discharge into the RCS (via a valid actuation signal) *
  • Rx trip from criticality *
  • Any news release that may generate national attention

* unless trip or ECCS is part of a pre-planned evolution (testing, normal shutdown trip)

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
3
Q

XI1.ID2

What are the conditions that warrant an 8 hour NRC report notification?

A
  • Condition of plant seriously degraded (fission prod barriers)
  • plant in unanalyzed condition (that significantly degrades plant “system safety function(s)”)
  • valid actuation of following: (unless part of planned evolution)
    • RPS
    • Cnmt Isolation
    • ECCS
    • AFW
    • Cnmt heat removal/ depressurization
    • DG’s
  • condition that could have prevented a safety function from being executed had an actuation taken place
  • contaminated, injured man transported to offsite facility
  • loss of major assessment capability (CR ind, MET tower, etc.)
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
4
Q

XI1.ID2

What are the defined “System Safety Functions” that if lost/degraded requires a report to the NRC?

Who is responsible to make an immediate notification to the NRC if conditions warrent?

A
  • shutdown Rx and maintain in a safe s/d condition
  • remove residual heat
  • control release of radioactive material
  • mitigate the consequences of an accident

Shift Manager

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
5
Q

XI1.ID2

What is the “Event discovery date” when it comes to makeing reports to the NRC?

When does it start?

A
  • it is the date and time the clock for reports due to the NRC starts

start times

  • date/time tech, engineer, supervisor identifies problem
  • if engineering eval is required to determine operability/compliance the date is whenever resonable expectation the equipment operability no longer exists (eval starts to go south)
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
6
Q

10 CFR 55/ XI1.ID2

Other than a change to an “operators” medical conditins, what else concerning that operator required a 30 day report to the NRC?

A
  • Permanent re-assignment
  • termination
  • felony conviction
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
7
Q

XI1.ID2

Other than 50.54 x and emergency class declaration, what else will required “immediate” notification to NRC?

A
  • lost/ stolen special nuc material. (>1000 x 10CFR20)
  • overexposure / excessive release
  • termination of emergency class
  • safety limit violation
How well did you know this?
1
Not at all
2
3
4
5
Perfectly