Q

according to OP1.ID4

what qualifies a test or evolution to be a IPTE

(infrequently performed test or evolution)?

A

Activity performed less freqently than quarterly and if not properly conducted properly may result in high probability:

  • significantly reduce safety margins
  • introduce plant transients
  • introduce plant trips
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
2
Q

For tests required by Tech Specs is there a grace period that allows due date to be extended?

If so by how much?

A

yes, 25% grace period if plant conditions prevent test performance before due date

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
3
Q

according to AD13.DC2 (gauge oscillations during performance of tests on safety related pumps) what is the maximum oscillation allowed before action must be taken to reduce?

A

2% of gauge span

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
4
Q

what is criteria for suspension of a test?

A
  • jeopardizes reactor safety
  • jeopardizes personnel safety
  • could damage equipment
  • could violate license requirement
How well did you know this?
1
Not at all
2
3
4
5
Perfectly