Plant testing and test controls Flashcards
1
Q
according to OP1.ID4
what qualifies a test or evolution to be a IPTE
(infrequently performed test or evolution)?
A
Activity performed less freqently than quarterly and if not properly conducted properly may result in high probability:
- significantly reduce safety margins
- introduce plant transients
- introduce plant trips
2
Q
For tests required by Tech Specs is there a grace period that allows due date to be extended?
If so by how much?
A
yes, 25% grace period if plant conditions prevent test performance before due date
3
Q
according to AD13.DC2 (gauge oscillations during performance of tests on safety related pumps) what is the maximum oscillation allowed before action must be taken to reduce?
A
2% of gauge span
4
Q
what is criteria for suspension of a test?
A
- jeopardizes reactor safety
- jeopardizes personnel safety
- could damage equipment
- could violate license requirement