QUIZ: Generator Operator Requirements - Manual 14D Flashcards
1
Q
- Who assigns a commercial plant or unit name prior to its incorporation in the PJM model?
a. NERC
b. FERC
c. PJM
d. MISO
A
c. PJM
2
Q
- Telecommunications (voice and data) circuits, which must be reliable and secure, should be tested regularly and/or monitored online, with special attention given to emergency channels.
a. True
b. False
A
a. True
3
Q
- MOCs are required to be staffed on which of the following basis?
a. 3 hours a day/5 days a week
b. 8 hours a day/3 days a week
c. 12 hours a day/2 days a week
d. 24 hours a day/7 days a week
A
d. 24 hours a day/7 days a week
4
Q
- The dispatch voice system is designed to provide voice communications during normal circumstances. Should the PJM primary All Call System, Ring Down, Manual Dial, and Facsimile Communication fail, the following systems provide alternative communication capabilities in the event the normal system is not effective for some reason. Which of the following is NOT an alternative method identified?
a. Business voice system
b. Emergency radio
c. Cellular phones
d. Satellite phones
A
b. Emergency radio
5
Q
- What is the data system to connect remote assets and PJM to satisfy real-time, market and other data transactions?
a. Gulfstream
b. Jetstream
c. OASIS
d. eTAG
A
b. Jetstream
6
Q
- New generators of more than how many MWs or any new capacity resource intending to set real-time LMP must be explicitly modeled in the PJM EMS network model?
a. 5 MWs
b. 10 MWs
c. 25 MWs
d. 100 MWs
A
b. 10 MWs
7
Q
- The PJM wholesale energy market includes both day-ahead and real-time markets.
a. True
b. False
A
a. True
8
Q
- The balancing market rebidding period runs from?
a. 0800-1000
b. 1200-1400
c. 1400-1600
d. 1600-1800
A
d. 1600-1800
9
Q
- What is an internet based system that allows PJM dispatchers and participants to view current and projected system data and emergency procedures information as well as market information?
a. eDATA
b. eDART
c. eSYS
d. eVID
A
a. eDATA
10
Q
- Energy generated for a predetermined period by a new resource interconnecting with the PJM balancing authority for the first time is called?
a. Useless energy
b. Test energy
c. Pass energy
d. Fail energy
A
b. Test energy
11
Q
- A generator is responsible for switching all equipment it owns, operates, or controls.
a. True
b. False
A
a. True
12
Q
- A generator must notify PJM and the LCC of the intent to remove equipment from service by what time, three working days prior?
a. 0800
b. 1000
c. 1400
d. 1600
A
b. 1000
13
Q
- A unit is considered fuel limited when it is not capable at running at its maximum capacity for how many hours?
a. 24 hours
b. 48 hours
c. 72 hours
d. 96 hours
A
c. 72 hours
14
Q
- PJM will issue which of the following for black start generation resources every five years, which would be open to all existing and potential new black start units on a voluntary basis?
a. RFP
b. WDS
c. RLB
d. HSN
A
a. RFP
15
Q
- The Interconnection Coordination (IC) Project Manager coordinates the activities of PJM Internal Coordination (Operations Planning, System Operations, Member Relations, PJMnet, EMS) and the Generation Owner to complete the Generator Markets and Operations activities during this phase.
a. True
b. False
A
a. True