1.2 Intro to Markets Flashcards

1
Q

Operating Reserve

A

Generation or load reduction that can be fully utilized within 30 min of request.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
2
Q

Primary Reserve -

NERC equivalent & time? PJM time?

A

NERC Contingency Reserves (available within 15 min)

PJM Primary Reserve available w/in 10 min.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
3
Q

Primary Reserve - 2 categories?

A

Synchronized

Non-synchronized (quick start)

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
4
Q

Synchronized Reserves examples

A
  • Increased output from synched generator
  • reduction in load of pumped hydro synched in pumping mode
  • maximum output from synchronous condenser
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
5
Q

Quick Start (non synched) Reserves examples

A
  • interruptible demand resources
  • run of river hydro
  • industrial combustion turbines
  • diesels
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
6
Q

Supplemental Reserve

A

avail w/in 10-30 min

does not need to be synchronized

How well did you know this?
1
Not at all
2
3
4
5
Perfectly