1.2 Intro to Markets Flashcards
1
Q
Operating Reserve
A
Generation or load reduction that can be fully utilized within 30 min of request.
2
Q
Primary Reserve -
NERC equivalent & time? PJM time?
A
NERC Contingency Reserves (available within 15 min)
PJM Primary Reserve available w/in 10 min.
3
Q
Primary Reserve - 2 categories?
A
Synchronized
Non-synchronized (quick start)
4
Q
Synchronized Reserves examples
A
- Increased output from synched generator
- reduction in load of pumped hydro synched in pumping mode
- maximum output from synchronous condenser
5
Q
Quick Start (non synched) Reserves examples
A
- interruptible demand resources
- run of river hydro
- industrial combustion turbines
- diesels
6
Q
Supplemental Reserve
A
avail w/in 10-30 min
does not need to be synchronized