Outages Flashcards
Hot Line Ticket Rule
Bucket 1
Hotline work 5 days or less submitted by 0800 3 days prior
To Be On Time
1 Month Rule
Bucket 2
Outages 5 days or less submitted on 1st of the month prior to start date
To Be On Time
6 Month Rule
Bucket 3
Outages greater than 5 days but less than 30 days submitted prior to 1st day of month 6 months prior to the outage
To Be On Time
30 Day Rule
Bucket 4
Outages greater than 30 days submitted prior to Feb 1st or 6 months prior, whichever is more restrictive.
To Be On Time
Criteria for Transmission Outage Acceleration
Exceeds 5 days
Cost more than $500,000 in congestion costs
eDART Color : Magenta
Unavailable - System Impacts
eDART Color: Orange
Conflicts - Mismatch
eDART Color: Yellow
EMS Tripped
eDART Color: Red
Congestion Expected
Priorities of Outages
Emergency (Forced)
On Time - Planned
Late