Capacity Shortage Alerts Flashcards

1
Q

How many Capacity Shortage Alerts are there, and what are they?

A

There are 4 Capacity Shortage Alerts:

  1. Unit Startup Notification Alert
  2. Maximum Emergency Generation Alert/Load Management Alert
  3. Primary Reserve Alert
  4. Voltage Reduction Alert
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
2
Q

What is the purpose of a Unit Startup Alert Notification?

A

To alert members to place generating units in a state of readiness so that they can be brought online within 48 hours in anticipation of a shortage of operating capacity, stability issues or constrained operations.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
3
Q

What is the trigger for a Unit Startup Alert Notification?

A

When a reliability assessment determines that long lead time generation is needed for a future period.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
4
Q

What is the purpose of a Maximum Emergency Generation/Load Management Alert?

A

To provide an early alert that system conditions may require the use of the PJM Emergency Procedures.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
5
Q

What is the trigger for a Maximum Emergency Generation/Load Management Alert?

A

When Maximum Emergency Generation is called into the operating capacity, or if Demand Response is projected to be implemented. **Operating Reserve Requirement is greater than scheduled Operating Reserve.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
6
Q

What is the purpose of a Primary Reserve Alert?

A

To alert members of the anticipated shortage of Operating Reserve Capacity for a future critical period.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
7
Q

What is the trigger for a Primary Reserve Alert?

A

When the estimated Operating Reserve is less than the forecasted Primary Reserve requirement.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
8
Q

What is the purpose of a Voltage Reduction Alert?

A

To alert members that a voltage reduction action may be required in a future critical period.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
9
Q

What is the trigger for a Voltage Reduction Alert?

A

When the estimated Operating Reserve capacity is less than the forecasted Synchronized Reserve Requirement.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly