Quantification of costing Flashcards
What is the new rules of measurement and why are they beneficial?
- They are documents that provide a standard set of measurement rules and guidance for the cost management of construction projects and maintenance works.
- Provide consistency across the industry and greater accuracy.
- Parties will price on the same basis which might prevent misunderstanding and disputes
What are the volumes of NRM and could you please expand on each one?
- NRM1 is on the quantification of building works and preparing cost estimates and cost plans.
- NRM2 provide guidance in the preparation of bill of quantities (i.e how to prepare BoQs, defines the information required that is needed to prepare it, descripe key components)
- NRM3 provides guidance on the quantification and description of maintenance works for the purpose of preparing initial order of cost estimates.
What is risk are dealt with under NRM?
- Employer change risk
- Employer other risk
- Design development risk
- Construction risk
What is a bill of quantities?
• It is a document that provides a list of items alongside their description, quantity and rate that are required to complete the works.
Benefits of bill of quantities?
- Cost and time effective if you have to quantify the same design
- Provides an extensive clear statement of work to be executed
- Strong basis for budget control and accurate cost reporting
- Source for real-time cost data.
What is benchmarking, and why would you use it?
• Benchmarking when you use of historical data from projects of similar nature and they act as a point of reference in order to compare it with other similar projects and also prepare a cost estimate.
How would you benchmark for your client?
- Produce a clear document which shows the various cost plan elements side-by-side with the benchmark projects
- I would identify items which re considered abnormal and I would then endeavour to justify cost anomalies for flag items.
What is a provisional sum?
- It is an estimate of a works that is included in the contract price. This is because the item was not sufficiently defined at the contract sign off.
- It might be works that the employer may or may not wish to be carried out
Can you name what pricing documents you can use at tender stage?
- Bill of quantities
- Schedule of rates
- Contract sum analysis
- Schedule of work
- Priced activity schedule
What pricing option can you use for construction contracts?
- Lump sum
- Cost-plus
- Remeasurement
- Target cost
What are key advantages and disadvantages of remeasurement contracts?
Advantages
• Since the work is tendered in approximate quantities, the contractors will submit competitive prices in their tender
• The contractor’s risk is lower than lump sum
Disadvantages
• Less cost certainty until the project is complete
• A client will bear more risk than lump sum.
What are contractor preliminaries?
- Items which cannot be allocated to a specific element, sub-element or component.
- Items which are necessary to complete the works but not part of the works after the works are complete i.e staff costs, site establishment, security, temporary works, hire of equipment
How do you evaluate interim valuations?
- Go to site and conduct/review the valuation with the contractor
- Check work done, materials on site and materials off site
- Value prelims
- Agree Compensation events
- Valuation amount
How do you value materials off-site?
- Requesting a vesting certificate : proof that ownership will transfer to employment on payment
- Ensure insurance was in place
- Materials clearly marked
What is a vesting certificate?
• It is a document evidencing the transfer of ownership of good or materials from one party to another on payment