Contract practice Flashcards

1
Q

What are other key elements should the contract have?

A
  • An offer.
  • Acceptance,
  • Consideration.
  • Intent
  • Legality
  • Capacity
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
2
Q

How does a performance bond provide security to the client?

A

• If the contractor was unable to complete the works the client can claim on the performance bond to ensure the works get completed. Generally, the bond can finance the current contractor, or fund/hire another contractor to finish the works.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
3
Q

What are the differences between NEC4 and NEC3?

A
  • Terminology – Employer becomes Client, Works Information becomes ‘scope’
  • Early warnings – Risk register renamed to Early warning register to separate it from project risk register
  • Default periods for managing early warning I,e the Project Manager prepares a first early warning register within one week of the starting date. Regular early warning meetings are then to be held starting within two weeks of the starting date.
  • Programme period- if the client doesn’t reply to the programme submission it is seen as accepted
  • Application for payment - Contractors are obliged to apply for payment rather than PM assessing what’s due
  • Two new forms of contract , Design Build and operate Contract – Alliance contract
  • Dispute resolution – senior representative are set out in the contract before it reaches adjudication.
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
4
Q

What is a collateral warranty?

A
  • Creates a contractual relationship with a third party that would not otherwise be there due to privity of contract.
  • Only the parties of the contract can sue each other to enforce rights and liability and prevents the third party from doing so.
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
5
Q

What is a The Contracts (Rights of Third Parties) Act?

A

• It enables a Third party to enforce a term of the contract if the contract expressly provides that he may

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
6
Q

What is the difference between Collateral warranties and third-party rights?

A
  • Third party right must expressly name in the contract for Third party rights to be enforceable.
  • Collateral warranties take longer, and they are heavy administrative
  • Collateral warranty is a contract that passes down all the contractual obligations, third party rights you can only enforce a term of contract and not the whole contract itself.
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
7
Q

Can you list 5 different bonds used on a project?

A
  • Performance bond
  • Advance payment bond
  • Retention bond
  • Offsite material bond
  • Tender bond
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
8
Q

What is a performance bond?

A
  • It is a form of security provided by the contractor to a developer or employer.
  • In the event that the contractor doesn’t perform then the performance bond pays for the employer to reinstate a new contractor.
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
9
Q

Who might need a collateral warranty?

A

• Employer in a big project might want a collateral warranty with a contractor’s subcontractor if the contractor goes into liquidation and the employer might want the subcontractor to correct any defects.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
10
Q

What does CECA stand for?

A

• Civil Engineering Contractors Association

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
11
Q

What is a letter of intent?

A
  • It is a letter from an employer to a contractor used that details the employer’s intention to enter into a formal written contract for works described
  • It typical asks the contractor to begin those works before the formal contract is executed
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
12
Q

Why would a letter of intent be used?

A
  • To start works until final contract is agreed

* Long lead materials might be ordered which will benefit the contract

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
13
Q

What is a parent company guarantee?

A

• It is when a company ensures the performance of a subsidiary contractor to the client

It is a form of security requested by clients to protect them in the even of default on a contract by a contractor that is controlled by a parent company.
• If such event happens, the parent company is required to remedy the breach, meeting all the contractor’s obligations under the contract.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
14
Q

When might the employer want a performance bond?

A
  • If they are new or unapproved
  • Public project
  • If there is a concern of financial position of the company
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
15
Q

What is an Alternative to performance bond?

A

• Parent company guarantees

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
16
Q

What is a Tender bond?

A
  • Requested by the employer when inviting contractor to bid

* In the event that a successful bidder fails to enter a contract

17
Q

What is a retention bond?

A
  • Retention bonds are way of avoiding problems associated with retention recovery
  • Retention money are actually paid, but if there is any defect and the retention money need to be use the bond is triggered
18
Q

What is advance payment bond?

A

• In the event that a contractor does not provide the materials that he was paid in advance for, the advance payment bond comes in effect and reimburses the client.

19
Q

What is retention?

A
  • A percentage of the sums certified for payment under the construction contract (typical 5%) is held by the employer during the construction phase.
  • Payment released when defect period is over
20
Q

What are defects?

A

• Part of the works that are not according to the works information or the applicable law or the contractors design which the project manager has accepted.

21
Q

What are patent and latent defect?

A
  • Patent – can be seen in reasonable inspection wall cracks

* Latent- cannot be seen in a reasonable inspection – foundations

22
Q

Why is defect period 12 months?

A

• To allow works to go through all the months of the year.

23
Q

What is professional negligence?

A
  • When a professional fails to perform their responsibilities to the required standard or breaches duty of care
  • This leads to financial loss, physical damage, injury to the client or costumer
24
Q

What is Public Liability insurance?

A

• Public liability insurance protects against liability for injury or damage to third parties and their properties. Ex if a brick falls on someones car and he makes a claim

25
Q

What is Employer Liability Insurance?

A

• The insurance it for paying compensation amount and legal costs if an employee claims compensation for a work-related illness or injury.

26
Q

What are bonds?

A

• It is an arrangement where contractual duty owed by one party to another is backed up by a third party.
They are used as protection for example in the event a contractor does not perform, a performance bond will provide money to the client to reinstate a contractor to carry on with the works.

27
Q

Performance bond vs PI insurance?

A
  • A professional Indemnity insurance policy is coverage against errors or omissions done by a professional that resulted in a loss for the client or customer
  • A Performance bond is a guarantee of compensation for monetary loss because of the failure of one party to meet his obligations as stipulated in the contract
28
Q

What is on demand and a conditional bond?

A
  • On demand bond is when the bond pays an amount of money set out in the bond immediately on demand in writing without the need to do any checks to assess the contractor’s liability unless the demand is fraudulent.
  • Conditional bond is only required to be paid to the contractor if the contractor if certain conditions have been fulfilled
29
Q

What is duty of care?

A

• It is a legal obligation of an individual to carry out their services in a reasonable standards in order to prevent any sort of harm to others.

30
Q

What is included in the letter of intent?

A
  • Description of the works,
  • Date of possession
  • Date of completion
  • Method of payment
  • Expiry date of a letter
31
Q

What are the two types of letters of intent?

A
  • Comfort letter

* Instruction to proceed with consent to spend

32
Q

What is an assignment?

A
  • A process where the benefit of the contract is transferred from one party to another, but the burden stays with the original party.
  • A bank getting the benefit of a contract from an employer just in case it goes into financial troubles.
33
Q

What is novation?

A

• Under design and build contract it is when the designed team that originally put the initial design together for the client are transferred to the contractor for continuity