Project finance (control and reporting) Flashcards
What is an Actual Cost?
It is the amount of monay paid in order to undertake the scope of works. i.e incurred labour, material, equipment
What is an Accrual?
It is the difference between the total liability and the amounts that have already been paid out.
Value of works that are complete but are not yet paid but the business is liable for.
Why is cost reporting done on a Regular Basis?
It is done on regular basis to give the business the best available cost data to base its decisions on.
How does cost reporting give a client a tool to base its decision making?
Tracks all issues relating to cost on the project
Budget forecast cost, expenditure to date.
What is the purpose of cost reporting?
It is to inform the client/business likely outturn cost of the construction project,
What does the cost report include?
A construction cost report captures historic and forecast costs incurred under a construction contract.
Why is a CVR a tool to base decision making?
As an update CVR provides the best available date to base its decision making.
What can a client do if the forecasted final cost is above the allocated budget?
- You can omit elements in the remaining construction work
- Reduces the scale of elements of remaing construction work
- Reduce the specification of elements of remaining construction work.
What are factors affecting outturn construction costs?
- Contractor instructions
- Anticipated instructions/early warnings
- Additional cost arising from delays to programme or the disruption to the performance of the contract works
- Fluctuations – inflation for example
- Risk allowances for works or services whose quantity and specification are unknown.
What is a CVR?
It is a document that captures the amount of work done to date and the amount of cost incurred date. These two are compared to determine the profit or loss of the company at that point in time.
It can include other cost data like budget, final anticipated cost, the cost to date, risk allowances for a business to make decisions and to understand the progress of the works.
What are legal constraints on the cost of the project?
- Building regulations 2010 i.e., gain permission to start building
- Town and Country Planning Act 1990 i.e., to start doing engineering works
What is post-contract cost control?
- Post contract control refers to how the budget is managed after awarding the works.
- One example is undertaking forecasting and reporting on a monthly using cost reports like the CVR in order to monitor budget overruns or under spends.
What is Cost reporting?
- It’s a regular process to inform the client or other parties about cost data such as the final anticipated cost, the actual cost, and the variances of budget VS final anticipated final cost.
- It actual costs, estimated forecasted costs, risk allowances
What is a Change control procedure?
- Change control procedure can be in the form a number of registers tracking various different changes occurred and which suppliers /subcontractors might have might affected with that change.
- Big projects might have a change manager responsible for all change.
What is an effective change control system?
• A clear and effective communications system like CEMAR, Aconex