Quantification and costing (of construction works) (L3) Flashcards

1
Q

On the Thirlmere Service Reservoir, when advising on the CE for omission of fencing, was the Contractor satisfied that your advised method was suitable?

A

o Yes
o Given that the time for preparing a forecast Defined Cost assessment is unrecoverable for a Contractor under an Option A

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
2
Q

Why did you consider this was the best option?

A

o Due to the time it would take producing a forecast defined cost assessment being unduly lengthy in relation to the value of the compensation event
o I also calculated a cost per m based on the Price from the activity schedule and compared this to a similar item for fencing in SPONS, which was rebased for both time and location to use as a benchmark

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
3
Q

What are the advantages and disadvantages of a Contract Sum Analysis as a pricing document?

A

o Advantages include:
 Transparency – provides a breakdown of costs aiding understanding of the contract sum
 Simplifies valuation of variations/ CEs - can be used to more easily price and value variations/ CE
 Supports payment valuation – in lump sum contracts (e.g. Option A)
o Disadvantages include:
 Time-consuming to prepare – due to itemising every section of work
 Limited detail – for description of activities can cause issues with payments
 Potential disputes – if costs allocated to certain elements are seen as unrealistic

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
4
Q

Tell me about a specific variation/ CE you have successfully agreed.

A

o On the Thirlmere Service Reservoir project, the PM gave an instruction and notified a CE which removed the requirement from the Contractor to provide fencing
o My task was to agree the assessment of this CE
o Due to the time it would take producing a forecast Defined Cost assessment being unduly lengthy in relation to the value of the CE, I proposed to use the Price from the Activity Schedule
o Both the Project Manager and Contractor where happy with such proposal and agreed to use the Price from the Activity Schedule as the basis for assessing the CE

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
5
Q

Tell me about a time you have advised on the most suitable pricing document.

A

o On the NSW Bushfire Clean-up project the nature of the work was known but could not be quantified due to the unknown number of properties requiring attention
o We needed to procure consultants and sub-contractors to undertake the works and at speed
o Due to this combination, I advised that a schedule of rates should be used as the pricing document when procuring professional services and subcontractors to undertake the required works
o This allowed us to quickly procure consultants and subcontractors and to obtain rates for all likely activities that may form part of the clean-up works

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
6
Q

Tell me about a time you have advised on the most suitable method of measurement.

A

o I have not had the opportunity to advise on the most suitable method of measurement.
o However, I am aware that NRM1 is used during the feasibility and design development stages for cost estimates and cost planning
o NRM2 is used during procurement and construction for detailed measurement of building works and
o NRM3 is used for cost estimates and cost planning of building maintenance works
o However, I have had the opportunity to advise on the most suitable means of costing construction works for example
o On the Thirlmere Service Reservoir project, the PM gave an instruction and notified a CE which removed the requirement from the Contractor to provide fencing
o My task was to agree the assessment of this CE
o Due to the time it would take producing a forecast Defined Cost assessment being unduly lengthy in relation to the value of the CE, I proposed to use the Price from the Activity Schedule as the method of costing the works
o Both the Project Manager and Contractor where happy with such proposal and agreed to use the Price from the Activity Schedule as the method of costing the works

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
7
Q

In terms of negotiating the final account how would you deal with an item that you could not agree on, say the value of a variation?

A

o In the event that a final account cannot be settled amicably through negotiation
o It would be advisable for the parties to consider other alternative dispute resolution options such as mediation and conciliation
o The presence of a third party may help put perspective on issues
o If resolution is still not reached then adjudication would be the first formal step for resolving the dispute
o It should be noted that negotiation or agreements outside of the contract terms should only be carried out where formally instructed to by the employer

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
8
Q

What are the different options considered for assessing prolongation costs?

A

o Fluctuations – increases in the cost of staff costs, materials or plant arising from general inflation as a result of the delay
o Tine-related costs/ preliminaries – associated with having to remain on site longer due to the delay such as:
 Site establishment
 Running costs
 Staff and labour