Conflict avoidance, management and dispute resolution procedures (L1) Flashcards
What are the main conflict avoidance processes?
- Clear contract documentation - ensuring contracts documents are clear and unambiguous (e.g. capturing the specific details of the project and avoiding generic specifications)
- Record keeping - contemporaneous records of labour, plant, materials used on the project
- Regular reporting and proactivity - Regular monitoring of cost, progress and quality is important for the success of any project and allows issues to addressed early to keep the project on track
- Partnering and Alliancing - encourages cooperation, team working and problem solving between project participants
- Good payment practices
What is partnering?
- It is a concept that can be applied to many procurement routes (it is not itself a procurement route)
- It is a set of collaborative processes which emphasise the importance of common goals
- It can be implemented independently of the contract as a separate partnering charter or
- integrated into the contract to reinforce the partnering arrangement
- It is based on negotiation rather than competitive tendering
What are the advantages of partnering?
- Fewer disputes
- Early supply chain involvement
- Based on open-book and win/win culture
- Integration of design process with construction process
What are the disdvanatges of partnering
- Potential for abuse by one party
- Requires more client resource to compensate for the less competitive environment
- To be most effective, it needs be practised and learnt over a number of projects
- Direct cost of workshops, training staff and intensive involvement of management staff to establish the partnering approach
What dispute resolution techniques are you aware of?
- Negotiation (informal)
- Mediation and conciliation (informal)
- Expert determination (formal)
- Adjudication (formal)
- Arbitration (formal)
- Litigation (formal)
- Dispute Boards (formal)
What are the three distinct process that all dispute resolution techniques are built upon?
- Negotiation - whereby the Parties work between themselves to resolve the dispute
- Mediation and conciliation - whereby the parties are assisted by a third-party offering a non-binding view on the matter
- An adjudicative process - whereby the final outcome is determined by a third party who decision is binding on the parties
What is dispute resolution?
- Actions and processes taken to resolve contractual disagreement between parties
What is negotiation?
- It is a process whereby the parties work between themselves to resolve any issues or differences.
- It relies upon the parties finding common ground.
- It is more than just a dispute resolution procedure, it can be used to negotiate building contracts in the first place.
What is mediation and conciliation?
- The Parties agree on an independent third party to facilitate discussions between them, with the goal of reaching a settlement
- This can take an evaluative style whereby the mediator or conciliator evaluate the information and offers a view that is non-binding
- The power to settle remains with the parties but the process is led by the mediator
What is adjudication?
- Adjudication is a statutory form of dispute resolution that is available in the UK
- It is a relatively simple and efficient method of resolving disputes without engaging in lengthy and expensive court proceedings
- Adjudication relies on an independent third party who considers the claims of both parties
- A binding decision is made which can be appealed either through litigation or arbitration
- It has the advantages of being time sensitive with a decision being made within 28 days
What enforces the requirement for a construction contract to contain provisions for adjudication?
The Housing grants, Construction and Regeneration Act 1996 (aka Construction Act)
Which contracts does adjudication apply to?
It applies to all construction contracts entered into after the act commenced within England, Scotland and Wales
What if a construction contract does not contain provisions for adjudication?
- Parties still have statutory right to adjudication
- If there is no reference to the process in the construction contract, terms from Scheme for Construction Contracts 1998 will be implied
When can a dispute be referred to adjudication?
At any time
What happens if a dispute has been referred to adjudication?
- Referral Notice: Referring party serves it’s Referral Notice within 7 days of the Notice of Adjudication to the adjudicator and other party setting out their case (together with supporting docs)
- Response: Within 7 days of Referral Notice, Responding Party Party services its Response (together with supporting docs)
- Reply and Rejoinder: Adjudicator may permit Referring Party to reply to service a Rejoinder
- Decision: The adjudicator must give their decision within 28 days of the dispute being referred to them (can be extended by 14 days with agreement of Referring Party)