Quantification and costing (of construction works) (L1) Flashcards
What is cost planning?
- It is a budget distribution technique implemented during the design stage
- It involves a breakdown of the the client’s budget for the building into cost targets for each element of the building
- These cost targets are the recommended expenditure for each element (e.g. substructure, frame, upper floors and roof)
- The resulting elemental cost plan is a statement of how the project team proposes to distribute the available budget among the elements of the building
- This provides a frame of reference from which to develop the design and maintain cost control
- Elemental cost planning is an iterative process, performed in steps of increasing detail as more design information comes available
What is the purpose of cost planning?
- Keep expenditure within client budget
- Ensure clients are provided with value for money
- Make clients and designers aware of the cost consequences of their requirements
- Provide advice to designers that enables them to arrive at balanced designs within budget
- Provide robust cost information with which the client can make informed decisions
What are the formal cost plan stages?
- RIBA Stage 2 Concept Design – Formal Cost Plan 1
- RIBA Stage 3 Spatial Coordination – Formal Cost Plan 2
- RIBA Stage 4 – Technical Design – Formal Cost Plan 3
What are the constituent parts of a cost plan under NRM?
- Facilitating works estimate
- Building works estimate
- Main contractors preliminaries estimate
- Main contractors overheads and profit
- Project Design Fees estimate
- Other project costs estimate
- All of which equal the Base Cost Estimate which should exclude allowances for risk or inflation as these are separate constituents that are added to the Base Cost Estimate
What are standard methods of measurement?
- They are guidelines and protocols used in the measurement and quantification of construction works.
- They provide a structure for the information that should make up descriptions
- Defines units of measure for each item i.e. m, m2, m3, etc
- Provides rules as to what is included in each item
What are the benefits of standard methods of measurement?
- Consistency enabling reliable comparisons and benchmarks.
- Accuracy leading to more accurate cost estimates
- Reduces potential for disputes
- Transparency fostering trust among clients and contractors
What are the risks of deviating from a standard method of measurement?
o Inconsistency across projects – makes benchmarking and using historical data difficult
o Inaccurate cost estimates – due to increased risk of inaccurate measurement which can cause incorrect pricing
o Miscommunication and disputes – due to different interpretations can lead to misunderstanding and disagreement
o Loss of transparency – which may lead to reduced trust if deviations lead to cost and time overruns
What standard methods of measurement exist?
- New Rules of Measurement (NRM)
- Civil Engineering Standard Method of Measurement (CESMM)
- Rail Method of Measurement (RMM)
What are New Rules of Measurement?
- NRM provides a standard set of measurement rules for construction projects and maintenance works
- The NRM suite comprises three separate volumes
- NRM 1: Order of cost estimating and cost planning for capital building works
- NRM 2: Detailed measurement for building works
- NRM 3: Order of cost estimating and cost planning for building maintenance works
What is NRM 1?
- NRM 1 is used during the feasibility and early design stages of a project specifically for producing order of cost estimates and cost plans for capital building works.
When is NRM 1 used?
NRM 1 is used during feasibility and early design stages to produce:
- Initial Cost Estimates to establish if a project is financially viable
- Cost Plans during the design development to guide the design process by ensuring that the project stays in budget
How many group elements are there in NRM 1 and can you give me some examples?
- There are 15 group elements 0-14
- Group element 0 is Facilitating Works
- Group element 1 is Substructure
- Group element 2 is Superstructure
How is NRM 1 set out?
- The rules are tabulated and are based on 4 levels.
- Level 1 to 3 relate to the actual work items and are split into group element, element and sub-element e.g. Superstructure, Frame, Concrete
- Level 4 is the rule of measurement for the each component of the sub-element i.e. columns and beams
What is NRM 2?
- NRM2 is used during the procurement and construction stage specifically for detailed measurement and quantification of building work.
- They provide a standardised approach for producing bills of quantities
When is NRM 2 used?
NRM 2 is used during the procurement and construction stage to:
- Prepare the Bill of Quantities for Tendering and Procurement and to
- Manage and monitor costs throughout the construction phase, including valuing work done, processing payments, and handling variations.
How many work sections are there in NRM 2 and can you give me some examples?
- There are 41 work sections
- Work section 11 is In-situ concrete works
- Work section 12 is Precast/ composite works
- Work section 13 is precast concrete
How is NRM 2 set out?
Each work section is structured as follows.
- The first section sets out the drawing information required to enable measurement
- The First column represents the Item or work to be measured.
- The Second column, lists the unit of measure
- The Third column, Level one lists the information that should be included in the description e.g. dimensions
- The Fourth and Fifth column, Level two and Level three list additional information requirements
- The Sixth column, Notes explains the work included and the measurement approach
What is NRM 3?
- NRM3 is used for order of cost estimating and cost planning for building maintenance works.
- They provide a standardised approach for measuring and estimating the costs of maintenance, repair, and renewal work in existing buildings.
What is CESMM 4?
- The Civil Engineering Standard Method of Measurement 4 (CESMM4) is used for the preparation of bills of quantities in civil engineering projects.
How many work classes are there in CESMM4 and can you give me some examples?
There are 26 main classes of work
- Class J is Pipework – pipes
- Class K is Pipework – fitting and valves
- Class L is Pipework – manholes and pipework ancillaries