Quantification and costing (of construction works) (L1) Flashcards

1
Q

What is cost planning?

A
  • It is a budget distribution technique implemented during the design stage
  • It involves a breakdown of the the client’s budget for the building into cost targets for each element of the building
  • These cost targets are the recommended expenditure for each element (e.g. substructure, frame, upper floors and roof)
  • The resulting elemental cost plan is a statement of how the project team proposes to distribute the available budget among the elements of the building
  • This provides a frame of reference from which to develop the design and maintain cost control
  • Elemental cost planning is an iterative process, performed in steps of increasing detail as more design information comes available
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
2
Q

What is the purpose of cost planning?

A
  • Keep expenditure within client budget
  • Ensure clients are provided with value for money
  • Make clients and designers aware of the cost consequences of their requirements
  • Provide advice to designers that enables them to arrive at balanced designs within budget
  • Provide robust cost information with which the client can make informed decisions
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
3
Q

What are the formal cost plan stages?

A
  • RIBA Stage 2 Concept Design – Formal Cost Plan 1
  • RIBA Stage 3 Spatial Coordination – Formal Cost Plan 2
  • RIBA Stage 4 – Technical Design – Formal Cost Plan 3
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
4
Q

What are the constituent parts of a cost plan under NRM?

A
  • Facilitating works estimate
  • Building works estimate
  • Main contractors preliminaries estimate
  • Main contractors overheads and profit
  • Project Design Fees estimate
  • Other project costs estimate
  • All of which equal the Base Cost Estimate which should exclude allowances for risk or inflation as these are separate constituents that are added to the Base Cost Estimate
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
5
Q

What are standard methods of measurement?

A
  • They are guidelines and protocols used in the measurement and quantification of construction works.
  • They provide a structure for the information that should make up descriptions
  • Defines units of measure for each item i.e. m, m2, m3, etc
  • Provides rules as to what is included in each item
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
6
Q

What are the benefits of standard methods of measurement?

A
  • Consistency enabling reliable comparisons and benchmarks.
  • Accuracy leading to more accurate cost estimates
  • Reduces potential for disputes
  • Transparency fostering trust among clients and contractors
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
7
Q

What are the risks of deviating from a standard method of measurement?

A

o Inconsistency across projects – makes benchmarking and using historical data difficult
o Inaccurate cost estimates – due to increased risk of inaccurate measurement which can cause incorrect pricing
o Miscommunication and disputes – due to different interpretations can lead to misunderstanding and disagreement
o Loss of transparency – which may lead to reduced trust if deviations lead to cost and time overruns

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
8
Q

What standard methods of measurement exist?

A
  • New Rules of Measurement (NRM)
  • Civil Engineering Standard Method of Measurement (CESMM)
  • Rail Method of Measurement (RMM)
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
9
Q

What are New Rules of Measurement?

A
  • NRM provides a standard set of measurement rules for construction projects and maintenance works
  • The NRM suite comprises three separate volumes
  • NRM 1: Order of cost estimating and cost planning for capital building works
  • NRM 2: Detailed measurement for building works
  • NRM 3: Order of cost estimating and cost planning for building maintenance works
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
10
Q

What is NRM 1?

A
  • NRM 1 is used during the feasibility and early design stages of a project specifically for producing order of cost estimates and cost plans for capital building works.
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
11
Q

When is NRM 1 used?

A

NRM 1 is used during feasibility and early design stages to produce:

  • Initial Cost Estimates to establish if a project is financially viable
  • Cost Plans during the design development to guide the design process by ensuring that the project stays in budget
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
12
Q

How many group elements are there in NRM 1 and can you give me some examples?

A
  • There are 15 group elements 0-14
  • Group element 0 is Facilitating Works
  • Group element 1 is Substructure
  • Group element 2 is Superstructure
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
13
Q

How is NRM 1 set out?

A
  • The rules are tabulated and are based on 4 levels.
  • Level 1 to 3 relate to the actual work items and are split into group element, element and sub-element e.g. Superstructure, Frame, Concrete
  • Level 4 is the rule of measurement for the each component of the sub-element i.e. columns and beams
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
14
Q

What is NRM 2?

A
  • NRM2 is used during the procurement and construction stage specifically for detailed measurement and quantification of building work.
  • They provide a standardised approach for producing bills of quantities
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
15
Q

When is NRM 2 used?

A

NRM 2 is used during the procurement and construction stage to:

  • Prepare the Bill of Quantities for Tendering and Procurement and to
  • Manage and monitor costs throughout the construction phase, including valuing work done, processing payments, and handling variations.
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
16
Q

How many work sections are there in NRM 2 and can you give me some examples?

A
  • There are 41 work sections
  • Work section 11 is In-situ concrete works
  • Work section 12 is Precast/ composite works
  • Work section 13 is precast concrete
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
17
Q

How is NRM 2 set out?

A

Each work section is structured as follows.
- The first section sets out the drawing information required to enable measurement
- The First column represents the Item or work to be measured.
- The Second column, lists the unit of measure
- The Third column, Level one lists the information that should be included in the description e.g. dimensions
- The Fourth and Fifth column, Level two and Level three list additional information requirements
- The Sixth column, Notes explains the work included and the measurement approach

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
18
Q

What is NRM 3?

A
  • NRM3 is used for order of cost estimating and cost planning for building maintenance works.
  • They provide a standardised approach for measuring and estimating the costs of maintenance, repair, and renewal work in existing buildings.
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
19
Q

What is CESMM 4?

A
  • The Civil Engineering Standard Method of Measurement 4 (CESMM4) is used for the preparation of bills of quantities in civil engineering projects.
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
20
Q

How many work classes are there in CESMM4 and can you give me some examples?

A

There are 26 main classes of work
- Class J is Pipework – pipes
- Class K is Pipework – fitting and valves
- Class L is Pipework – manholes and pipework ancillaries

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
21
Q

How is CESMM4 set out?

A

o There are 26 main work classes
o Each work class comprises up to 3 divisions to classify work at greater levels of detail E.g. Work Class I – Pipework – Pipes contained 3 divisions of classification
* The first classifies the different types of pipe e.g. clay, concrete, etc
* The second classifies different pipes by their diameter and the
* Third by if they are laid in trenches or not and if so the depth
o Each division also has measurement, definition, coverage and additional description rules

22
Q

What are measurement rules under CESMM4?

A

Set out conditions and method of how work will be measured and quantified e.g. centre line for pipes

23
Q

What are definition rules under CESMM4?

A

They define the extent and limits of the class of work

24
Q

What are coverage rules under CESSM4?

A

They state what is included in the measure

25
Q

What are additional description rules under CESMM4?

A

o It is where a separate item shall be stated were work comprises of different additional features e.g different specifications for pre-cast units

26
Q

What is SPONS?

A

SPONS is a series of 4 pricing books covering the most frequently specified items in
- Building Works
- External and landscaping works
- Civil engineering and highway works
- M&E works

27
Q

What is BCIS?

A

The BCIS is an independent provider of cost and price information for the construction industry which can be used for the purposes of benchmarking

28
Q

What is a Bill of Quantities

A
  • It is a list of items and quantities of the work
  • Usually prepared by the clients consultants and
  • Priced by the Contractor
  • Client holds the risk that the quantities are accurate and for any errors in their preparation against the stated measurement rules
29
Q

What are the objectives of a Bill of Quantities:

A

o To provide information on the type and quantity of work to enable tenders to be prepared and compared and
o Manage and minitor costs during the construction stage, including valuing works done, processing payments and hanfling variations

30
Q

What are cost checks?

A
  • They take place during the design stages and
  • Involve comparing the current estimated costs against the cost targets previously set for the elements of the building
31
Q

What are the different sources of cost data?

A
  • BCIS
  • SPONS
  • In-house cost data
  • Previous projects
  • Specialist sub-contractors and suppliers
32
Q

What factors may necessitate adjustment of the prices/ cost data?

A

o Time to account for inflation between the base date of cost data and the current estimate base date
o Location
o Specification if necessary
o If in-house cost data (i.e. cost analyses and benchmark analyses) has been used for unit rates they should be adjusted to reflect prices current at the estimate base date (i.e. adjusted to remove construction inflation allowances made by the main Contractor)

33
Q

Why do you need to adjust the prices/ cost data for time?

A

o To account for inflation between the base date of cost data and the current estimate base date

34
Q

How do you adjust the prices/ costs date for time?

A

o This can be done through the use of Tender Price Indices to account for inflation between the base date of costs data and the current estimate base data
o The TPI at the base data of cost data is deducted from the TPI at the estimate base date which is then divided by the estimate base date TPI which is then multiplied by 100.

35
Q

How would you take account of inflation when preparing a cost estimate/ cost plan?

A
  • Through the use of Tender Prices Indices to account for construction inflation and tender price inflation
36
Q

Why does inflation need to be accounted for when preparing a cost estimate/ cost plan?

A

o To account for
 Tender inflation – between the estimate base date and tender return date and
 Construction inflation – between the tender return date to mid-point of the construction period

37
Q

What is meant by the base date within in a cost estimate?

A
  • The base date refers to the date on which rates and prices contained within a cost estimate or cost plan are based on
38
Q

What are the typical items to be included in a cost plan report?

A
  • Project title
  • Project Description
  • Status of cost plan
  • Statement of cost (i.e. estimate)
  • Details of drawings, specifications and other information on which cost plan was based
  • Cost plan summary (elemental breakdown)
  • Inclusions and exclusions
  • Estimate base date ( i.e. to which inflation has been applied)
  • Reasons for changes to previous cost targets
  • Value engineering proposals
  • Recommendations
  • Completed cost plan as an addendum to the cost report
39
Q

What are indices?

A
  • Construction indices are tools used to measure and track changes in the cost of construction, labour, materials and other expenses over time.
  • They provide valuable information to contractors, clients and government to understand and manage the economic dynamics of the construction sector
40
Q

What is a contract sum analysis?

A

o It is an alternative pricing document to a Schedule of Works or Bill of Quantities
o Generally prepared by the Contractor as part of their tender on a Design and Build project (e.g. Activity Schedule)
o It breaks down the Contractors price into a form allowing the client to analyse it and to compare it to other tenders
o May then be used to as a basis for calculating interim payments

41
Q

What is a pricing document?

A

o It is used in the tendering process
o It breaks down the costs associated with the project
o Serves as the basis for determining the contract sum and comparing tenders
o The type of pricing document depends on the form of contract and chosen procurement route e.g. traditional, JCT SBC – Bill of Quants

42
Q

What different forms of pricing documents are you aware of?

A

o Activity Schedule
o Bill of Quantities
o Contract Sum Analysis
o Schedule of works/ rates

43
Q

What is a provisional sum?

A

o A sum of money (usually estimated by the cost consultant) for an item of work that cannot be described and given in quantified terms.
o A provisional sum will either be ‘Defined’ or ‘Undefined’

44
Q

What is a defined provisional sum?

A

o A defined provisional sum is a sum of money for an item of work which is not completely designed, but information in regards to the nature and extent of the work can be provided
o A defined provisional sum is also accounted for within the contractor’s price (for preliminaries) and programme

45
Q

What information is needed for a provisional sum to be considered defined?

A

o Nature and extent of the work
o Statement of how and where work is fixed to the building
o Quantity that indicates extend of work and
o Any limitations

46
Q

What information is needed for a provisional sum to be considered defined?

A

o Nature and construction of the work
o Statement of how and where work is fixed to the building
o Quantity that indicates extend of work and
o Any limitations

47
Q

What is an undefined provisional sum?

A

o An undefined provisional sum is a sum of money for an item of work which is not completely designed and the information required for a defined provisional sum cannot be provided.
o An undefined provisional sum is not accounted for in the contractor’s price and programme which means that the client is taking the risk for the whole works and the contractor maybe entitled to an extension of time and additional payment

48
Q

What is the difference between defined and undefined provisional sums?

A

o Defined provisional sum is accounted for within contractor price (for preliminaries) and programme
o Undefined provisional sum is not accounted for in the contractors price (for preliminaries) and programme
o Define is used when information in regards to the nature and extend of work can be provided
o Undefined is when information in regards to the nature and extend of work cannot be provided

49
Q

What is the reason for the Contractor revising the Activity Schedule?

A
  • If the Contractor changes a planned method of working at his discretion and the activities on the Accepted Programme no longer relate to the operations on the Activity Schedule
50
Q

What are the reasons for a Project Manager not accepting a revised Activity Schedule?

A

*It does not comply with the Accepted Programme
* any changed Prices are not reasonably distributed between activities and
* the total of the Prices is changed

51
Q

Please list 5 preliminaries items?

A

*Temporary accommodation
*Plant
*Fencing and security
*Temporary works
*Temporary utilities (e.g. power and water )