Contract administration (L1) Flashcards
What standard forms of contract are you aware of?
- NEC
- JCT
- FIDIC
- IChemE
Can you name some contracts from the JCT suite of contracts?
- JCT Standard Building Contract (with Qunats, Without Qunats or with Approx Quants versions)
- JCT Intermediate Building Contract (with Contractor’s Design version)
- JCT Minor Works Contract (with Contractor’s Design version)
- JCT Design and Build Contract
- JCT Major Project Construction Contract
- JCT Management Building Contract
- JCT Construction Management Contract
Contract families contain main and sub-contracts
Can you name some contracts from the NEC suite of contracts?
- NEC Engineering and Construction Contract (ECC) - Main Options A-F
- NEC Engineering and Construction Subcontract (ECS) - Main Options A-E
- NEC Engineering and Construction Short Contract (ECSC) - Hybrid between Option A and Option B
- NEC Engineering and Construction Short Subcontract (ECSS) - Hybrid between Option A and Option B
- NEC Professional Services Contract (PSC) - Main Options A, C and E
Note: The client can include the requirement for the Contractor to be doing some element or all of the design by including such requirements within the scope/ works information. This avoids the need for a separate ‘design and build’ option within the NEC family of contracts.
What are the Main Option clauses under the NEC Engineering and Construction Contract?
There are 6:
- Main Option A: Priced contract with Activity Schedule
- Main Option B: Priced contract with Bills of Quantities
- Main Option C: Target contract with Activity Schedule
- Main Option D: Target contract with Bill of Quantities
- Main Option E: Cost reimbursable contract
- Main Option F: Management contract
Can you give me some examples of Secondary Option clauses under the NEC Engineering and Construction Contract?
- X5: Sectional completion
- X6: Bonus for early completion
- X7: Delay Damages
- X16: Retention
What are the core clauses of an NEC3 ECC contract?
1 - General
2 - The Contractor’s main responsibilities
3 - Time
4 - Testing and Defects
5 - Payment
6 - Compensation Events
7 - Title
8 - Risks and Insurance
9 - Termination
Describe the difference between statutory provisions and contract provisions?
- Statutory provisions are set out by law
- Contract provisions relate to the contract in questions and therefore only apply to a specific project
What is the difference between NEC and JCT?
- The main difference between the 2 forms is its usage
- NEC can be used for building and civil engineering projects whereas JCT is specifically for building projects
How is a contract under hand different from a deed?
- A deed is signed by the parties and witnesses, whereas a simple contract under hand is signed just by the parties
- The other main difference is the limitation period - simple contracts under hand have a limitation period of 6 years from when the breach occurred whereas a deed has 12 years
What is your understanding of a latent defect?
- Latent defects are defects that are not readily identifiable upon inspection and only come to fruition some time after completion and may take some years to become identifiable
- A claim in contract can only be brought within the limitation period from when the breach occurred which is 6 years if the contract is under hand and 12 years if the contract was executed as a deed
What are the main parts of the JCT contract?
- Recitals
- Articles
- Contract particulars
- Attestation
- Conditions divided into 9 sections (7 for minor works)
- Schedules
What are the sections of a JCT Standard Building Contract ?
Section 1- Definition and interpretation
Section 2 - Carrying out the works
Section 3- Control of the works
Section 4 - Payment
Section 5 - Variations
Section 6 - Injury, damage and insurance
Section 7 - Assignment, Thurs Party Rights and collateral Warranties
Section 8 - Termination
Section 9 - Settlement of disputes
What is set-off/ contra-charge?
Set off/ contra-charge are any monies owed to the employer by the contractor which are deducted against any payment due to the contractor
What are the role and responsibilities of the Project Manager under NEC?
- Contract Data Part One identifies who the PM is
- They play a key role in administering the contract on behalf of the client
- Duty to act impartially and in accordance with the contract
- Acceptance of submissions from the Contractor e.g. design and programme or if not accepting give reasons as to why
- Giving instructions e,g. for additional work or to stop work
- Replying to, notifying, assessing and implementing CEs
- Responding to and notifying early warnings and updating the risk/ early warning register
- Assessing the amount due at each assessment date
- The Project Manager can also delegate their actions after notifying the Contractor
What are the main elements that could be issued to the Project Manager for acceptance under NEC4?
- Design
- Programme
- Subcontractor and contract conditions
- CE Quotations
- Revised Activity Schedule (Option A only)
- Additional Working Areas
- Changes in Key Perons
- Acceleration Quotations