Quantification and costing (of construction works) (L2) Flashcards
On the Williamsgate project, how do you go about assessing the amount due each month?
o At each assessment date the state of completion for each activity is assessed
o Including assessing if it is free from Defects which would delay or be covered by immediately following work
o This involves attending site with the Supervisor to ascertain this information in addition to reviewing the Defects register
o The Contractor will be paid for each activity if it is complete and free from certain Defects if it is not in a group
o If it is in a group then the Contractor will be paid for the activity when the whole group of activates is complete
When assessing compensation events what rates did you use?
o Rates stated in Contract Data Part 2 for:
People doing manufacture and fabrication and design outside the working areas
Special equipment (for use when it may be difficult to establish a market rate)
Rates for Equipment t listed in CECA i.e. the published list for Equipment
Open market rates for Equipment not listed in CECA
Contractors own people under shorter SSCC under NEC4
Can you talk me through an item you have measured?
o Measured MDPE pipework on Cornhow to Stainburn using CESMM4
o Work Class I which is for the supply, install and jointing of pipes including excavating and backfilling trenches
o The unit of measure was linear meters and
o The pipework was measured along the centre line including
lengths occupied by fittings and valves but not occupied by manholes (wasn’t any connection into manholes or valves just fitting such as bends)
o The depth of trench was measured from the commencing surface to the invert of the pipe
o Diameter of pipe was also required
o Fittings such as bends where measured in number of and in accordance with work class J
How did you quantify this, what items did you measure and what units did you use?
o Quantified – in accordance with CESMM4 and using drawings and materials list
o Measured
MDPE pipework which was measured in Linear meters and also the diameter and
Fittings such as bends and tapping tees which are measured in number
How would you have valued an item for which there was no like rate?
o You would break the items down into its constituent parts and
o Price them individually based on first principles
o Seek supplier quotes where they can be obtained
o And use a similar work as a benchmark
When costing construction works, how would you assess the appropriate labour rate?
o Ensure the rate has been built up in accordance with SCC or SSCC if using NEC
o Identify the type of labour
E.g. unskilled, semi-skilled or skilled
o Use SPONS price book which contains a section on calculating labour rates
o Use rates used on previous and current projects
o Use framework rates if applicable
How would you assess the appropriate level of OH&P?
o Use industry benchmarks – (obtained from SPONS and/ or BCIS)
o Assess project specific conditions such as size, duration, complexity and risk
Complex project with high risks may require specialist equipment and resources which may increase overhead
o Review historical data and past projects
o Evaluate market conditions – competitive market may necessitate reduced profit
o Assess contract requirements – D&B contracts may have higher overhead to cover design
o Review contractual provisions – terms may dictate how OH&P are calculated e.g. item 44 in SCC
Talk me through how you would measure concrete foundations in accordance with NRM2.
o You would use Work Section 11: In-situ concrete works, work item 2 Horizontal work
o The unit of measure is M3 and so you need 3nr dimensions to calculate the volume and measure the concrete foundations, these are:
Centre line distance
Width and
Depth
o To calculate the centre line distance you need
The inner girth dimensions (width and length)
These are then added together and multiply by 2 to get the inner girth distance
Next you need to add the corner distance for outer corners calculated by
* Half the wall thickness multiplied by 2 multiplied by the number of outer corners
This will then give you the centre line
o You then need the width and depth of the concrete foundation to calculate the volume