Project finance (control and reporting) (L1) Flashcards
What cost control systems are used in the contracting environment?
-Cost Value Reconciliation (CVR)
- Earned Value Analysis (EVA)
What is Cost Value Reconciliation (CVR)?
-CVR is a cost control process that is used during a construction project. It is typically carried out monthly (at the interim valuation date) by the QS and involves comparing cost against value to determine the profitability of the project.
-Cost equals the expenses incurred in performing the works both to date and a forecast
-Value equals the revenue incurred for the work complete both to date and a forecast
-If the value is higher than the cost then the project is in profit.
-If the cost is higher than the value then the project is at a loss.
What is the process of CVR?
-Initial budgeting: establishing the budget of the project scope
-Cost tracking: monitoring actual cost against the budgeted amounts
-Value assessment: valuing work complete at different intervals. Note there are two types of valuations, external and internal. It is likely that the external valuation will contain value that maybe disputed by the client. This value is not included in the interval valuation, that is included in the CVR such that the prudence concept is applied.
-Reconciliation: identifying variance between budget and actual cost and the value, and analysing reasons for differences
-Reporting: generating CVR reports to provide stakeholders with a clear financial status of the project
-Review and action: use insights to make informed decisions and corrective action if necessary
What is the prudence concept?
-Cost should not be understated
-Value should not be overstated
-As it is better to have unexpected financial gain than it is to have an unexpected financial loss.
-The prudence concept ensures the likelihood of the latter is decreased
What is Earned Value Analysis (EVA)?
-EVA is a project management tool used to assess project progress and performance at any point in time.
- It does this comparing the amount and cost of work that was planned to have been complete at a point in time (known as Planned Value) with the actual amount that has been done and what it has actually cost (known as Actual Cost).
-The Earned Value then shows how much of the budget and time should have been spent to get to this point in the project
- So by comparing Earned Value to Planned Value you can see if the project is ahead or behind schedule (known as Schedule Variance) and if it is under or over budget (known as Cost Variance)
What is the difference between CVR and EVA?
-CVR compares value of work done to a point in time with cost incurred to the same point in time
-EVA has an additional dimension of time and
- Shows how much of the budget and time should have been spent to get to this same point in the project
How does regular and frequent cost reporting on a project help in controlling the outturn cost on a project?
-Outturn cost is controlled by recognition of cost changes incurred and planned implementation of future changes
-So regular and frequent cost reporting affords the client and project team with the visibility to recognise this
What is a cost report?
-It is a report that records the cost incurred to date and a forecast of cost to be incurred which may include risk allowances
What is the purpose of cost reporting?
-To inform the client of the likely outturn cost of the project
What should be included in a construction cost report?
-This will somewhat vary dependant on the contract type/ main Option
What should be included in a construction cost report for a lump sum contract?
It should include:
-Tendered total of the Prices
-Implemented CEs
-Unimplemented CEs
-Forecast total of the Prices
-Certified PWDD
-Profile of remaining incomplete activities
-Delay Damages if applicable
-Reasons for movement in outturn and in month
-United Utilities do not include Contractor notified CEs in their cost reports
What should be included in a construction cost report for a Target Cost contract?
Total of the Prices/ Target Cost
Implemented CEs
Unimplemented CEs
Forecast total of the Prices/ Target Cost
Certified PWDD
Forecast PWDD including risk allowances
Forecast Pain/ Gain share
Delay Damages if applicable
Reasons for movement in outturn and variance in month
United Utilities do no include Contractor notified CEs in their cost reports
How are variations/ CEs treated and reported in cost reports?
-If the value of a variation has been agreed with the Contractor it should be identified as so
-If the value of a variation has not been agreed with the Contractor it should be identified separately
-Differences in the valuation of a variation should be recorded, but the final cost report should reflect the PQS assessment
How are loss and/ or expense claims/ contractor notified CEs treated and reported in cost reports?
- The cost report should include both the contractor’s claimed amount and the PQS assessed amount, if instructed to do so.
-However, due to reliance on Contractor to submit details of the loss and expense claim it can be difficult to report a reasonable assessment in the first place.
-If an allowance for loss and/ or expenses has been included it should be stated in the cost report
-Additionally, the QS should make the client aware of the difficulty in reporting a reasonable assessment and of the basis on which the allowance has been made
What measures can be taken to effectively control costs during the construction phase of a project?
-Regular cost reporting which is also forward looking
-Rolling final account
-Effective communication and collaboration
-Proactive risk management
-Proactive management of CEs