Construction technology and environmental services (L3) Flashcards

1
Q

On the Williamsgate project how did you go about costing the change?

A

o The CE was assessed in accordance with clause 63.1 and the Shorter SCC
o Mainly involved liaising with the design team to confirm which components would become subject to Regulation 31 and thus needed changing
o Following which the forecast defined cost of such components to be omitted needed to be agreed with the Contactor – this involved reviewing various supplier and subcontract quotations against the current design
o Subsequently the forecast defined cost of the new Regulation 31 compliant components needed to be agreed – again this involved reviewing various supplier and subcontract quotations and liaising with the design team
o The additional design time also needed to be assessed which again involved obtaining a breakdown from the contractor and reviewing this with the design team

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
2
Q

How did you assess the time impact?

A

o The time impact was assessed in accordance with clause 63.3
o This involved input from the Project Manager, Supervisor, Engineering disciplines and the planner
o It involved obtaining supplier lead in times and subcontractor programmes such that the Accepted Programme could be impacted (i.e. various activities and logic) and the impact on planned Completion assessed
o In summary, it involved accounting for and incorporating design time, component lead in times and subcontract installation activities onto the Accepted Programme

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
3
Q

Did you consider factors other than cost/time?

A

o Not specifically, but by having input from other project team members, factors such as
 Health and safety
 Regulations and
 While life cost
o Were considered

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
4
Q

What was the cost implication of this advice?

A

o I am employed by the client and so other than my salary there was no direct cost to the client for this advice other than my salary
o However, I book my time to projects and the time spent on this matter would have covered within my normal time allocation/ forecast for this project

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
5
Q

What other factors did you consider other than cost?

A

o N/A?

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
6
Q

On the Franklaw project, why were these planning conditions not reflected in the Work information?

A

o The contract was awarded before planning consent was fully obtained due to the need of achieving a regulatory date
o Hence why the matter was listed an additional Employer’s risk

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
7
Q

How did you go about ascertaining the costs associated with the tarmac access road?

A

o The CE was assessed in accordance with clause 63.1 and 63.3 of the NEC3 ECC
o This involved obtaining a quotation form the Contractor together with a breakdown of the subcontractor’s quotation for the works
o Given that stone was included already with the scope, the assessment related to the extra over cost only of installing tarmac

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
8
Q

Were there any life cycle implications to be considered?

A

o The requirement for tarmac was stipulated by the Local Authority
o However, in terms of life cycle costing – despite the initial capital expenditure being more slightly more expensive compared to just stone, the life cycle cost of tarmac is lower due to reduced maintenance requirements

How well did you know this?
1
Not at all
2
3
4
5
Perfectly