Programming and Planning Flashcards

1
Q

Why does RIBA exist?

A

Organises process of briefing, designing, construction and operating into 8 stages. Explains outcomes and tasks at each stage.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
2
Q

What is a programme, and why do we need one?

A

Reflects scope of work and sequence activities. Helps to identify risks and minimise delays.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
3
Q

What information does a programme typically show?

A

Activities.
Duration.
Milestones.
Float.
Critical path.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
4
Q

What is lag between activities?

A

When first activity completes and there is a delay before second activity starts.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
5
Q

Example of a lagged activity on a new build?

A

Time to let concrete to set.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
6
Q

Can critical path activities have float?

A

No, the entire project will be delayed.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
7
Q

Examples of typical programmes milestones?

A

Planning permission.
RIBA stage 3.
Start on site.
Watertight building.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
8
Q

Difference between jagged and straight drop line on programme.

A

Jagged drop - percentage entered for each task.
Straight drop - Helps determine impact on critical path.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
9
Q

How would you put together a programme for a new project?

A

Understand purpose of the programme and detail required.
Identify activities.
Assign durations to activities.
Summarise by RIBA stage.
Identify critical path.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
10
Q

What is a concurrent delay?

A

Two or more delays caused by different parties, occuring independently of eachother in the same period.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
11
Q

Benefits of assigning resources to specific programme activities?

A

Identifies resource requirements and pinch points in the programme.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
12
Q

What options help to facilitate acceleration?

A

Re-sequencing.
Longer hours.
More resources.
Alternative construction methods.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
13
Q

NEC reasons for rejecting a programme?

A

Not covering scope.
Unrealistic.
Not practicable.
Doesn’t include required information.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
14
Q

NEC programme timeline?

A

Usually submitted every 4 weeks.
2 weeks to review.
If no response received, 1 more week given, then deemed as accepted.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
15
Q

Which float is owned by the contractor?

A

Terminal Float and TRA (free float) owned by contractor.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly