How is completion defined under NEC ECC contracts?

A

Gender terminology, and Client not Employer. Under clause 11.2
NEC3:
Done all work which works information states by completion date.
Corrected notified defects that would prevent Employer from using the works.
NEC4:
Done all work which scope states is to be done by completion date.
Corrected notified defects that would prevent Client from using the works.