Procurement & Tendering Flashcards
Procurement & Tendering
1. What is procurement, and name some examples
a. Overall act of obtaining goods and services. In construction this Traditional, D&B, MC, CM
- What is tendering, and name some examples?
a. The obtaining and selection of prices and providers for the services. In construction this is Open, Single, Two-Stage, Negotiated, Framework
- Can you advise of the advantages and disadvantages of a traditional procurement route?
a. The client is responsible for producing the pricing document, and therefore the quantities in the contract
b. There is no overlap between design, tender and construction
c. Certainty of time is gained at tender stage (can plan ahead)
d. Full competition of tenderers, with full design
e. Control of quality of design, so certainty
f. Don’t get early buildability from contractor
g. Little risk as you get certainty of cost, time and quality
- When might it be appropriate?
a. When client wants certainty of cost, competitiveness, certainty of time but isn’t concerned with a longer tender process, and wants certainty of quality
- What is two stage tendering?
a. When a competitive tender is sought between contractors where they submit their OH&P, prelims CV’s method statements etc based on little design. Then a tenderer is selected to progress to stage 2 which he then submits his full priced tender with 3 quotes on packages, and costs are negotiated. The contractor is paid a pre construction services agreement fee to start building design.
b. Not as competitive as contractor can select the subbie quotes, and as he has the contract In a way and fees may have been paid, it is difficult or costly to get out of, so contractor can increase prices. Although quality of construction and buildability is good due to early engagement, the client could lose control of some of that design
- Can you tell me the difference between Construction management and management Contracting?
a. MC – where a Management Contractor has contracts with subbies and work packages are let. This is usually tendered on minimal design and packages are let as the design progresses based on which work is needing built first.
b. CM – where Construction Manager is appointed by client (expert) to manage subcontracts, the client is signed into these subcontracts directly. A very fast procurement route where the design and tender happens consecutively
- Advantage and disadvantage of Management Contracting?
a. Good when client doesn’t care about cost certainty, but needs an early start on site. Very short programme. Price not known until the last package. Changes to design later on can be expensive.
- Advantage and disadvantage of Construction management?
a. Large complex projects where early start is key. Design tender construction all happens simultaneously. Lots of admin, don’t get cost certainty.
- What is a framework?
a. An agreement between a buyer and suppliers, where the buyer has a long standing arrangement of works over time in the future, where the works are of a similar nature, allowing individual contracts to be let off of these framework agreements.
- What practice notes are you aware of relating to tendering?
a. I am aware of the guidance note - tendering strategies 2015
- What would you do if a tender was returned 1 minute after the deadline?
a. I would not open the tender, as this would give an unfair advantage to this tenderer, as the other tenderers where not aware of this extra time. 1 minute is still past the deadline, and the other tenderers may have submitted much earlier. Fraud, collusion. If private client it is at their discretion to open them. If public, you cannot open them.
- What if the client insisted you open the tenders?
a. I would advise the client that he is free to open them, but would advise this is not what I am going to do, and produce my report based on this tender not being bona fide.
- How has Brexit affected tendering? What legislation is there for tendering?
a. In October 2024, new procurement act comes into force
b. Deliver VFM / public benefit / transparency / integrity
c. New digital platform
Who does the Procurement Act apply to?
Public bodies, such as NHS trusts, schools and government bodies.
- What is the least risky procurement route?
a. It would depend on the construction project, client, and design requirements, but generally speaking traditional is seen as less risky, as you get cost certainty up front with pricing the stage 4 design, and the contractor wont price risk in due to this. There is programme certainty as the design is completed and all accounted for in the contractors programme, so should be minimal Prov Sums etc. There is quality certainty as the client retains this control, and has say over the design.
- What is OJEU?
a. The Official Journal of the European Union, I am aware there are thresholds for advertising.
- Why would traditional and D&B have different tendering timescales?
a. D&B may be longer due to the required design
- Why might D&B have different number of tenderers than traditional?
a. It may have less to give contractors chance they will win the work.
- How do you ensure that the costs returned under a negotiated tender are fair and reasonable?
a. On Havant I requested 3 different quotes from the subcontractor packages such as joinery, M&E, and finishes. I would also compare these rates to recent tendered rates, and in house cost data, more so if I have the data from the same contractor.
- As opposed to the prelims, what other documents did you have to produce for the tender documents on Innovation Centre?
a. I had to produce the contract sum analysis as the main pricing document for the contractor to fill in to form part of the contract. Also created a VE register draft with early VE ideas from the design team. I created a schedule of all contract documentation, which acted as a table of contents. I produced a tender clarification log to include in the pack for tenderers to fill in their clarifications and queries.