I Advised... Flashcards
Advise
1. IC7 - Drafted prelims
Containing site specific info
- Tyseley - drafted EOI prior to tendering
EOI with 5 contractors, 2 of which declined
- Data Centre - prepped tender packs, bespoke pricing template
Inc cover letter, and made a bespoke pricing template
- Havant - Advised architect and client to draw up sketch to show where welfare facilities could go on site. wrote prelims, and raised a query that there is not detail on welfare facilities location.
Helped come to an agreement on best way forward, as there was another contractor, and landlord may have pushed back
- Data Centre - analysed uplift from framework rates on tender return and advised client of costs.
Subsantiation was requested and costs negotiated with supplier
- S278 - advised on doing a retendering process to provide cost certainty, as tender came back higher
a. PTE was more in line with retenders, and reduced cost of initial tenderer.
- S278 - during tender process I made clarification logs and advised client of resolution to disputes
a. To ensure fair tendering process
b. I advised the client through clarification and query meetings, and an interim and final tender report
- Data Centre - Scoring matrix, qual and quant assessment, with help from design team, and provided recommendations to my client on outcome in this report.
a. To form tender recommendation and assess returns, as well as level those returns
- Medical Physics - clients dashboard was inputted to report to board level, adjusted contingency and risks, maintaining a change control tracker.
To ensure clear communication of facts and figures
- Havant - adjusted PSums during construction, i.e. plant deck. Financial reports bi weekly, and agreed and reported on variations
To ensure client was aware of expenditure and money left
- Havant - Final Account agreement
To avoid future disputes and close out the contract
- Enabling Works - Advised client on spending on monthly basis, and found an error with contractor cashflow which showed they were behind, and advised client on lack of expenditure.
a. Could be a risk to client, did deeper digging, but the contractor had just hit some things that slowed progress
- Medical Physics - Variation control template was used, I advised contractor how to sue it and the whole process to be adhered to throughout construction.
a. To ensure communication, and avoid delays and disputes
- Dental Hospital - issued financial statements and cashflows, advising on monthly changes and key risks. I made and presented a dashboard for the client which they used to present to board level.
a. Allowed board members to disseminate high level project information
- Tyseley - produced order of cost estimates and formal cost plans from RIBA 1 to 4, using NRM 1 and 2
Throughout RIBA stages as design developed
- Worcester Breast Unit - valued works using a BQ, and used this to value variations. Client wanted to change floor finish in reception from carpet to vinyl, which I negotiated and informed the CA of these costs
used Bill rates for Omission, and basis of new rate
- Southport - produced a schedule of works template for contractor to use to price
So it offered comparison between tenders
- Enabling Works - quantified and valued topsoil removal during valuations, and agreed final account
To ensure accurate valuation of works done to reduce financial risk to client
- Advised colleague on use of NRM to produce a cost plan, NRM1 would be suited, while using COMP6 as basis.
to ensure right measurement principle was used