I Advised... Flashcards

Advise

1
Q

1. IC7 - Drafted prelims

A

Containing site specific info

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
2
Q
  1. Tyseley - drafted EOI prior to tendering
A

EOI with 5 contractors, 2 of which declined

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
3
Q
  1. Data Centre - prepped tender packs, bespoke pricing template
A

Inc cover letter, and made a bespoke pricing template

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
4
Q
  1. Havant - Advised architect and client to draw up sketch to show where welfare facilities could go on site. wrote prelims, and raised a query that there is not detail on welfare facilities location.
A

Helped come to an agreement on best way forward, as there was another contractor, and landlord may have pushed back

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
5
Q
  1. Data Centre - analysed uplift from framework rates on tender return and advised client of costs.
A

Subsantiation was requested and costs negotiated with supplier

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
6
Q
  1. S278 - advised on doing a retendering process to provide cost certainty, as tender came back higher
A

a. PTE was more in line with retenders, and reduced cost of initial tenderer.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
7
Q
  1. S278 - during tender process I made clarification logs and advised client of resolution to disputes
A

a. To ensure fair tendering process
b. I advised the client through clarification and query meetings, and an interim and final tender report

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
8
Q
  1. Data Centre - Scoring matrix, qual and quant assessment, with help from design team, and provided recommendations to my client on outcome in this report.
A

a. To form tender recommendation and assess returns, as well as level those returns

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
9
Q
  1. Medical Physics - clients dashboard was inputted to report to board level, adjusted contingency and risks, maintaining a change control tracker.
A

To ensure clear communication of facts and figures

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
10
Q
  1. Havant - adjusted PSums during construction, i.e. plant deck. Financial reports bi weekly, and agreed and reported on variations
A

To ensure client was aware of expenditure and money left

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
11
Q
  1. Havant - Final Account agreement
A

To avoid future disputes and close out the contract

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
12
Q
  1. Enabling Works - Advised client on spending on monthly basis, and found an error with contractor cashflow which showed they were behind, and advised client on lack of expenditure.
A

a. Could be a risk to client, did deeper digging, but the contractor had just hit some things that slowed progress

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
13
Q
  1. Medical Physics - Variation control template was used, I advised contractor how to sue it and the whole process to be adhered to throughout construction.
A

a. To ensure communication, and avoid delays and disputes

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
14
Q
  1. Dental Hospital - issued financial statements and cashflows, advising on monthly changes and key risks. I made and presented a dashboard for the client which they used to present to board level.
A

a. Allowed board members to disseminate high level project information

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
15
Q
  1. Tyseley - produced order of cost estimates and formal cost plans from RIBA 1 to 4, using NRM 1 and 2
A

Throughout RIBA stages as design developed

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
16
Q
  1. Worcester Breast Unit - valued works using a BQ, and used this to value variations. Client wanted to change floor finish in reception from carpet to vinyl, which I negotiated and informed the CA of these costs
A

used Bill rates for Omission, and basis of new rate

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
17
Q
  1. Southport - produced a schedule of works template for contractor to use to price
A

So it offered comparison between tenders

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
18
Q
  1. Enabling Works - quantified and valued topsoil removal during valuations, and agreed final account
A

To ensure accurate valuation of works done to reduce financial risk to client

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
19
Q
  1. Advised colleague on use of NRM to produce a cost plan, NRM1 would be suited, while using COMP6 as basis.
A

to ensure right measurement principle was used

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
20
Q
  1. Data Centre - framework and tendered rates, I advised client that a specific template should be made and included in the tender which included the framework rates, with areas for vendors to input price increases.
A

a. Improved transparency, substantiation

21
Q
  1. Medical Physics - acted as EA, issued certificates, partial and sectional, released retention. I followed clients proformas, and stuck to interim valuation dates
A

To follow contract and ensure less risk to client

22
Q
  1. Windows Replacement - agreed on vesting of materials, and valued these
A

To reduce risk to client in event of contractor insolvency, and proper vesting of materials

23
Q
  1. Rugby Utilities - Acted as CA (MW contract), and valued works in line with milestone payments.
A

To ensure timely payment, and reduce risk. As per contract

24
Q
  1. Dental Hospital - chaired and facilitated risk workshops as QS, and assessed risks, advising on cost updates of risks
A

To enable clients contingency to be revisited

25
Q
  1. Date Centre - managed risk of lead In times of equipment using dates. Advised client of current risks in weekly catch ups.
A

To manage risk of equipment delivery on key project, highlighting escalations and where support is required

26
Q
  1. Havant - structural engineer warned roof structure was not strong enough to hold mechanical plant and suggested a structure would be required. I advised client that due to timescales and the time for the tenderer to price this mid/post tender item, to include a PSum in the contract.
A

Due to timescales a Psum was included in contract, with design just about completed to stage 4

27
Q
  1. Data Centre - EOT on tender, advised to meet deadline, and distributed queries to all vendors.
A

a. To ensure fair tendering strategies, as per RICS guidance on tendering, and general procurement regulations.

28
Q
  1. Data Centre - Advised on quantitative and qualitative scoring matrix to be separate.
A

a. Due to any unconscious bias that could come with scoring them holistically.

29
Q
  1. Advised colleague on receiving gifts.
A

a. Due to RICS policy and RLB policy on accepting gifts and risk of bribery.

30
Q
  1. IC7 - chaired VE workshop
A

Facilitated VE process

31
Q
  1. Cromwell - viability assessment then cost plan
A

through different design stages

32
Q
  1. Tyseley - initial cost plan to PTE, highlighting areas of increase cost (additional demo, forming openings, ramp)
A

through different design stages

33
Q
  1. Moreton - Abnormal’s cost plan, using rates in house data, RIBA stage 3
A

in house rates, for example cotswold stone façade

34
Q
  1. S278 - PTE, 2 adopting authorities, significant traffic management prelims.
A

a. Due to the different sections, logistics of works etc.

35
Q
  1. Southport - initial cost plan, then due to inflation and scope increase advised client costs had increased through reproducing a cost plan.
A

a. Due to scope and inflation increase.

36
Q
  1. Bankfield lane - analysed third party order of cost estimate, recommendations on excavation and disposal, suggesting further investigation is required. (possible to sell material on muck market), design wasn’t clear about quantities.)
A

a. Design didn’t have the detail.

37
Q
  1. S278 PTE - measured carriageway, drainage etc, different spec by authorities, found a clash between levels on drawings (matching up with the wider development), resulting in shortfall of excavation required.
A

advised designers to look into this as it seems its an error (two different designers designed different sections)

38
Q
  1. Measurement of SUDS and surface water systems.
A

Excavation using transects

39
Q
  1. Made assumptions in cost plans on build up of carriageways when information is lacking.
A

a. Due to limited design information.

40
Q
  1. Horsham - made assumption on CBR (3%), on similar greenfield sites, due to lack of GI, to inform build-up of carriageway. Also allowed for depths of drainage and utilities when not known
A

a. Due to lack of design information.

41
Q
  1. Cromwell - GI report highlighted poor ground, advised on cost of different foundation solutions.
A

a. Advised this because the GI report highlighted foundations may be required, and needed to include allowance in cost plan based on scenarios.

42
Q
  1. T&L centre - wrote prelims and contract docs
A

Using NBS Chorus, using contract amendments

43
Q
  1. IC7 - drafted contract with contract amendments (12 month rectification, 21 days payment terms)
A

And issued to client and contractor for signing

44
Q
  1. Havant - PC, drafted the final account statement and penultimate valuation.
A

Agreed and negotiated it, getting both parties to sign it

45
Q
  1. IC7 - advised use of PCG and Performance Bond, insurance option A.
A

a. As it was a new build and Employer wasn’t confident in insurance

46
Q
  1. S278 - advised on use of LAD’s regarding sections of works, as well as sectional sums.
A

a. As there was a wider development to consider/loss of profit

47
Q
  1. Medical Physics Bunker - advised contractor on valuation timescales, and managed change control procedure.
A

a. Due to amended contract dates.

48
Q
  1. Havant - recommended the use of the JCT ICD, due to retaining design control on completed architectural design and handing risk of uncompleted M&E design to contractor.
A

a. Because there was no time to wait for M&E design/risk allocation