Design Economics & Cost Planning Flashcards
Design Economics &Cost Planning
1. Can you advise on what NRM1 is used for?
a. Order of Cost Estimating and Planning
- What is NRM2 and 3 used for?
a. 2 - Detailed Measurement of Building Works
b. 3 – Order of Cost Estimating and Planning for Building Maintenance Works
- When is a cost plan and order of cost estimate produced in relation to the RIBA stages?
a. Order of cost estimate – RIBA 0 – 1
b. Formal Cost Plan 1 – RIBA 2
c. Formal Cost Plan 2 – RIBA 3
d. Formal Cost Plan 3 – RIBA 4
e. PTE – RIBA 4
- What are the elements of NRM1?
- Facilitating works - Waste removal / Demo / Temporary supports / Specialist groundworks / Temporary diversions / Investigation works
- Substructure
- Superstructure
a. Frame
b. Upper floors
c. Roof
d. Stairs and ramps
e. External walls
f. Windows and external doors
g. Internal walls and partitions
h. Internal doors - Internal finishes
a. Wall finishes
b. Floor finishes
c. Ceiling finishes - Fittings furnishings and equipment
- Services - Sanitary Installations / Services equipment / Disposal installations / Water installations / Heat source / Heating and air conditioning / Ventilation systems / Electrical installations / Fuel installations / Lift and conveyor installations / Fire and lightning protection / Comms and security / Specialist installations / BWIC
- Prefabricated buildings
- Work to existing buildings - Minor demo and alterations / Repairs to existing services / Damp proof courses / Façade retention / Cleaning surfaces / Renovation works
- External works – site prep / roads paths paving’s / landscaping / fencing / external fixtures / external drainage / external services / minor building works
- Main Contractors Preliminaries
- Main Contractors overheads and profit
- Consultants + design team fees
- Other project costs – Insurances/planning/relocation costs/marketing
- Risk
a. Design development risk
b. Construction risk
c. Employer change risk
d. Employer other risk - Tender inflation
- Construction inflation
- VAT
- Are there any factors that you would apply to cost data?
a. Location factor
b. Time/date factor
- Tell me how you apply inflation to a cost plan?
a. I would use the BCIS indices to calculate the projected increase in costs from present day to mid-point of construction. Present minus future, divided by future
- What are you current views on inflation in the current construction market?
a. There is significant cost increases seen throughout the construction market. This is mainly down to significant global events such as Brexit, war in Palestine, war in Ukraine. This has squeezed supply of critical materials such as steel, copper and aluminium
- Why would you only take inflation to mid point of construction?
a. Most of the work packages have been let by mid point of construction
b. Halfway through payment milestones and therefore my point materials/subbies have been paid for
- What are the different RIBA stages?
a. SD Strategic Definition
b. PB Preparation and Briefing
c. CD Concept Design
d. SC Spatial Coordination
e. TED Technical Design
f. M&C Manufacturing & Construction
g. H Handover
h. U Use
- What do you understand by the term value engineering?
a. This is the process of reducing unwanted or unnecessary costs in a project, by changing the specification or type of sub elements an materials, while not having a detrimental effect on quality
- What is Value Management?
a. This is the overall process across a project from inception to completion, where value is added and provided to a project continually by the project team
- What was the outcome of the value engineering process on Innovation Centre 7? Were you able to reduce costs whilst delivering on the clients requirements?
a. I created a VE register for issue to the design team and client. ahead of VE workshops I requested the team put forward VE ideas for client acceptance. I also proposed ideas of focus where I knew the costs were high or unnecessary.
b. VE workshops were held In private with the DT and also with the contractor, to get input into the potential cost of the items, and offer advice on the buildability of them.
c. Overall, a cost reduction was achieved, although some items did increase in price, without affecting the overall quality of design. All accepted changes by the client and DT were integrated into the CSA, and where there wasn’t enough time to price them, as provisional sums. The VE register was also incorporated into the contract documents.
- How does a cost plan differ to an order of cost estimate?
a. A cost plan is based on more detailed design information, and I produced from RIBA stage 2 concept design onwards
- Can you advise how risk % may vary throughout the cost planning process?
a. The calculation of the risk should become more accurate with improved design information. At estimating stage risk should be calculated as a % addition to the bottom of the costs, whereas when cost planning, where design information is of suitable level, a risk register should be produced with associated cost of those risks.
- What are the stages of order of cost estimating?
a. Functional unit Method (rooms)
b. Floor Area Method (GIA)
c. Elemental Method (roof, frame, substructure)
- What does BCIS stand for, and what is it?
a. Building Cost Information Service
b. This is a database of cost data founded by RICS, aiding in providing cost advice for cost planning, benchmarking and estimating.
- What are the components of a cost plan?
a. Construction cost, prelims, OH&P, risk, inflation, assumptions, exclusions.
- What is usually excluded
a. When producing cost plans such as that on Cromwell lane, I excluded VAT, professional fees, S106 costs, asbestos removal