CPD Q's Flashcards

CPD

1
Q
  1. CPD on Ariba and Icertis, online procurement software?
A

a. This allows population of tender documents by all parties, to the clients supply chain under their frameworks

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
2
Q
  1. Decarbonisation in the UK
A

a. Companies have incentives to reduce CO2 emissions, and there are targets in place for companies to

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
3
Q
  1. What is the knowledge and practice committee?
A

a. An RICS committee reporting to the board which develops the knowledge and working practice, highlighting areas of improvement

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
4
Q
  1. What happens at lease expiry?
A

a. A section 25 notice can be served by landlord to terminate existing lease.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
5
Q
  1. Whole life carbon in offsite construction?
A

a. Decarbonisation and use of sustainable materials in off site construction. Creating and designing materials to lookahead in the future how the end of life of those will work

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
6
Q
  1. You delivered workshop on drainage, how do you measure drainage?
A

a. Generally speaking for a drain run, I take the invert level and cover level of two manholes and calculate the average depth of both invert levels (the bottom), I then take the average depth and times it by the length. Manholes are Nr’s.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
7
Q
  1. What is a RICS surveyor?
A

a. Someone who is professional surveyor for RICS in the construction industry, providing services to clients

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
8
Q
  1. CPD on development funding, how are they funded?
A

a. Through joint ventures and banks. Risk is cashflow.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
9
Q
  1. What is the purpose of the memorandum of understanding?
A

a. The coming together of multiple organisations to drive diversity in the industry

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
10
Q
  1. What is immersion cooling technology?
A

a. Data centres have massive energy demands, for cooling which solar power cant do for air handling units. It is the process of pumping water through the servers to extract the heat output.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
11
Q
  1. What do you know about ISO 19650?
A

a. This relates to BIM, and offers guidance on how BIM is implemented in a business.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
12
Q
  1. Termination in JCT?
A

a. Contractors employment is terminated. It is difficult for employer to do and must have significant reason for doing so under common law.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
13
Q
  1. CESMM?
A

a. Class P is for piling works. Civil engineering standard method of measurement

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
14
Q
  1. What does the net to gross ratio of a building tell us?
A

a. If there is a lot of useable space. 75% ratio is the goal.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
15
Q
  1. If the drawings and specification clash, what takes precedence?
A

a. Generally in JCT anyway the drawings take precedence.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
16
Q

How is net present value assessed?

A

To do with cashflows at different times, to analyse the profitability of a project

17
Q

When is Nabers typically used on a prokect?

A

Soft landings

18
Q

What is force majeure and how do you assess?

A

Contractor has to demonstrate and show it was the event that caused the delay and nothing more, and how they looked to mitigate the delay

19
Q

What ratio of net to gross area should residential units aim for? And what is this?

A

75%. It is the ratio of useable area to unusable area

20
Q

What is the best way to reduce risk on a project?

A

Early design certainty.

21
Q

Why would you want to amend the contract to shift the risk of statutory requirements to the contractor?

A

As these can be a big risk to both programme and cost to the client, especially where there are unknowns. ground risk is biggest risk

22
Q

What is the lowest risk type of contract sum for the client?

A

Generally a lump sum is lowest risk, as the cost is known up front, and any other change will be by variation to this only.

23
Q

If there is an error between the spec and design docs, which takes precedence in JCT?

A

Generally the drawings take precedence

24
Q

What is the RICS ethics decision tree?

A

It sets out how to assess a possibly unethical situation, and how to act on it.

25
Q

What % of the lobal CO2 emissions does the construction industry contribute?

A

37%

26
Q

How does JCT define defects?

A

it doesn’t

27
Q

Is there any regulation when doing a PQQ that you are aware of?

A

PAS-91, offers a standardised approach

28
Q

Is there a clause in JCT that allows for material price changes?

A

Fluctuations provision, options A B C. based on different ways of estimating the change

29
Q

What takes precedence the ER’s or CPS’ and why?

A

The ER’s, although the contract does state the Employer has examined the CP’s, the contractor still must meet the ER’s

30
Q

Why is a CE different to a Variation?

A

CE deals with both time and money

31
Q

What pricing doc does NEC option B use?

A

BOQ

32
Q

What pricing doc does NEC option C use?

A

Target cost with Activity schedule

33
Q

What is the X29 clause?

A

(KPI’s) - Puts a requirement on the contractor to adhere to a performance indicator, such as CO2 emissions, materials used.

34
Q

What is the difference in force majeure between NEC and JCT?

A

In NEC contractor can claim time and money