Case Study Key Issue 1 Flashcards

KI 1

1
Q

18. How would you go about re tendering.

A

a. I would first create a shortlist of contractors by issuing out expressions of interest and getting feedback, with the hopes of having between 3-4 tenderers. I would then issue the tender information, in this case as soon as possible, ensuring that they all had the same times, and sufficient time, in which to price the works.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
2
Q
  1. Why was a negotiated procurement route selected? What were the advantages and disadvantages?
A

a. A negotiated procurement route was chosen because the clients priority was speed to start construction, it was also with a trusted contractor that the client preferred, this allowed earlier onboarding of the contractor to the project.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
3
Q
  1. How was the contractor chosen?
A

a. Previous satisfactory work carried out by contractor and myself, locality to the region, experience delivering similar schemes

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
4
Q
  1. Why was an Intermediate Building Contract selected over say a JCT D&B?
A

a. As the client wanted to retain control over the architectural design elements, but also wanted a standard contract for medium and regular sized construction projects, that are straightforward in nature, it contained all of the relevant clauses.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
5
Q
  1. You mention the risk was handled through effective partnership, but what were the underlying risks and what methods were put in place to combat these?
A

a. There was a risk that the contractor could take advantage of being the only tendering contractor and price this into the tender return. Therefore, this was mitigated by the contractor providing 3 quotes on all major packages. quotes were also interrogated in detail, and large measured items cross checked and remeasured where there was dispute.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
6
Q
  1. At what RIBA Stage was the contractor brought in to assist and advise on design of the M&E?
A

a. For the M&E design it was stage 3, for the rest it was stage 4.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
7
Q
  1. You mention that the costs returned were 28% higher than the cost limit - where were the biggest variances seen?
A

a. The MEP works constituted most of this, as additional AHU’s were added into the scheme, this further led to the addition of the plant deck (originally priced as an upper floor by the contractor), which added further price.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
8
Q
  1. What is a plant deck, and how is it constructed?
A

a. It is a timber structure built and resting on timber stilts which sits and spans across multiple or a single room, above the ceiling. It is used to bear the weight of mechanical and electrical plant when it is unable to be hung from the higher roof structure due to it not being structurally sound enough.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
9
Q
  1. You mention that selecting a single contractor reduces cost certainty, but what could you have done to combat this and ensure that costs were fair and reasonable?
A

a. I requested the contractor provide 3 quotations for the main works packages, such as MEP, joinery/carpentry, finishes, and FF&E

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
10
Q
  1. What is VFM?
A

a. Can mean multiple things, best out of budget, best value per pound for the client

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
11
Q
  1. You mention general inflation in the period being a cause for an increase in cost limit - should you not have included for inflation in the period within your estimate?
A

a. There was a 2 month allowance in the original cost plan for inflation, based on an assumed tender and construction period.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
12
Q
  1. How did you calculate inflation?
A

a. I utilized the BCIS building cost indices, using the present day and future date as two points in time, dividing the future by the present minus the future, to give me a percentage to apply to the bottom line.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
13
Q
  1. What were the VE items that reduced the costs and were any of the options proposed by you?
A

a. I made some minor proposals to the design team for consideration so they could then put forward and advise on. For example from experience on other schemes similar in nature with this client, I was aware that the data cabling could perhaps be substituted from CAT6A to CAT6. I noted that the contractor had proposed £13k for a banksman to be on site during construction, and proposed the question to the client and design team if there was ana alternative, to make use of the new recently erected fencing.
b. Large VE items included the change from an upper floor solution, to a simple plant deck solution to carry the weight of the mechanical plant.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
14
Q
  1. What is the risk of VE?
A

a. Lose sight of purpose, and start omitting important design aspects
b. Could have an impact on whole life cycle costs

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
15
Q
  1. Did your cost plan originally not contain tender inflation and risk allowances?
A

a. At the time it was unknown when the project would be tendered, therefore 2 months of inflationary uplift was included and any addition was noted as excluded.
b. I included total contingency in the form of NRM risk allowanced at a total of 10%, as even at that time the design was at stage 3 with no more foreseeable changes.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
16
Q
  1. When you went out to tender a year later, did you advise the Client that a cost plan would need to be updated since so much time had lapsed?
A

a. I advised the client I should create a pre-tender estimate based on the updated design, prior to getting tender returns back.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
17
Q
  1. Option 2: Reducing scope? Is this omitting in its entirety or would these works need to be carried out at a later stage?
A

a. These are omitting the works altogether from the project, for example omitting cork wall boarding which was purely aesthetical, which could then be added back in future months as a client direct expense, not falling under the main project budget

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
18
Q
  1. Did you advise on design elements
A

a. I didn’t advise on the design of the project, and I know to not do this as this doesn’t fall under my scope of services, and my companies PI cover does not cover liability for construction design.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
19
Q
  1. What is the difference between CAT6 and CAT6A?
A

a. The difference is the data speed that the cable can carry, this produced a saving but both cables still serve the same purpose of data transmission. it is cheaper material.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
20
Q
  1. How much was the saving for the value engineering.
A

a. Total saving made was £153k inc scope reduction and negotiated items. (all part of same register)

21
Q
  1. Did you advise the design changes?
A

a. I didn’t advise on the design changes, however I made proposals, and areas of focus as I knew where the main costs were in the design and tender return. I then negotiated costs of these changes with the contractor, and advised on suitable allowances for any provisional sums.

22
Q
  1. How did you assess the contractors submission?
A

a. I requested 3 quotations from the contractor on the packages of works to ensure commercial value. I also used rates from other recently tendered similar projects, and projects the contractor has worked on.

23
Q
  1. How do you successfully negotiate?
A

a. Prepare in advance and highlight areas which perhaps seem erroneous or unreasonable, then hold a meeting where items are ran through, and substantiation is either requested or costs are asked to be lowered or altered, where I would back these up with my own data collection.

24
Q
  1. You had a 3-week tender period, and knew the costs would come back higher, why didn’t you produce another cost plan, or a PTE during the tender period?
A

a. Clients internal sign off procedures were monthly, so if I produced a cost plan, it would not have resulted in a change due to the timing of reporting.
b. The cost plan was based on the assumption of a competitive tender, but it was eventually negotiated due to timescales, it was widely accepted by the business this would incur increased costs.

25
Q
  1. Was it in your scope of services to produce a PTE?
A

a. No, it wasn’t agreed to produce a PTE on this project originally, and as before when I advised the client to produce one, they opted not to. Maybe on a larger project this would have served well, but this was a fast paced environment.

26
Q
  1. Ok but you did one for Southport fit out?
A

a. Yes, there was more time to produce the cost plan on this project, and the budget was able to be revised and revisited due to separate funding pots (north compared to south). This was timed it to take advantage of client approvals in the month, to achieve additional funding.

27
Q
  1. Why weren’t you proactive in doing the VE prior to tender submission if you knew there were issues?
A

a. Prior to tendering one of the key cost drivers was the storage of mechanical plant, as the specification had changed substantially. I advised the client that a structural engineer should be approached, to deduce if the previous assumption of hanging the plant from the roof is still feasible. The structural engineer was appointed and carried out a survey and produced a drawing for a plant deck option. This was then communicated the contractor post tender (the drawing was only produced at the end of the tender period)
b. I had requested the architect and MEP engineer produce a log of all design changes that have elapsed in the months prior, to deduce if they were all required.
c. It was also only known where the main cost differences between the cost plan and tender return where, when the tender was actually returned.

28
Q
  1. It seems you have been a passenger throughout the tender process and have not demonstrated client care.
A

a. I advised the client throughout the project of the risks involved with expediting a project.
b. I advised the client to go down a competitive tender route to achieve cost certainty.
c. I advised the client I should produce a PTE and review the projects cost limit in line with design changes and inflation.
d. Advised the client to carry out a VE and scope reduction exercise in which I led the workshops and facilitated the discussion, achieving a significant cost reduction of the project, eventually achieving the project under budget.
e. Due to my advice around acceleration of works, the project was achieved to the tight timescales, and the practice was able to move in prior to Christmas.

29
Q
  1. If programme was a key driver, surely option 2 to re tender wasn’t an option?
A

a. Although the practice had to move in early January, the question was asked if this could be pushed back some weeks.
b. Programme was not the only key driver, however, when the project came back over budget this became a key driver. There was little time to re tender.

30
Q
  1. What are unknown risks?
A

a. Ones where works aren’t yet known to be able to estimate cost, such as potential for asbestos in a building, or underground services.

31
Q

The tenders were received over budget, was this purely due to inflation? Did you allow for any inflation on your PTE

A

In my PTE i allowed for inflation to mid point of construction as it was previously assumed, this was only for a couple of months however, as the delay was not known at the time.

32
Q

How many tenders were received? Did you do any engagement with contractors prior to the tender process?

A

Due to the tight timescales only one contractor was entered into negotiations with. An EOI was sent out to 3 contractors initially who fitted the requirements, however only one promised delivery of the scheme at such tight timescales, and were able to immediately tender the scheme

33
Q

Can you talk me through the process of ensuring the return was value for money and market rate?

A

I ensured VFM by comparing rates to previously submitted tenders as well as in house cost data, in addition to comparing to rates from this contractor specifically. For large items where they changed from the cost plan, i did do some re measurement to ensure the quantities were accurate.

34
Q

Can you talk me through how you achieved the negotiated savings on the OH&P and M&E works?

A

Planning, friendly, collaborative, making them aware we look to reduce cost of scheme.

35
Q

What was the inflation in 2022?

A

Around 7% for that period, impacted by global events (Ukraine Russia war)

36
Q

Why would implementing VE increase programme, is there an example?

A

For example changing specification of materials could warrant longer lead in times

37
Q

What changed with the shaft wall linings?

A

It was designed previously as an insulated double walled partition essentially, instead battens were nailed to the wall and plasterboard affixed to this, with insulation in between, and with a cheaper supplier. The architect reviewed the proposal and deemed it acceptable

38
Q

Option 4 was to enter negotiation, is this not standard practice?

A

It can be seen to be standard in a sense, however this was a more direct approach to negotiation, and could have impacted on contractor relationships, or added time to the programme as the contractor would need sign off on items. Everything had to be weighed up.

39
Q

What were the key issues using a different decoration subcontractor? Why didn’t the contractor use them initially if they were better value?

A

I requested 3 sub-contractor quotations from each main package of works. The contractor used a decorator he knew and had experience with, but wasn’t local to the area, so charged much more. the alternative was a similar service but local.

40
Q

How much contingency and inflation did you include in our cost plan?

A

It was envisaged the tender would happen soon so 1% was included for inflation, along with 10% for contingency

41
Q

How did you decide on the procurement route, and come to the conclusion there was no time for a competitive tender?

A

I undertook an analysis of the programme with the project manager and assessed the critical path.

42
Q

What is VE?

A

Analysis of materials and specs used to potentially provide cost savings while keeping or improving the quality of design.

43
Q

Is practical completion the correct term?

A

No, it should be date of completion

44
Q

Does the contractor have to comply with acceleration or instructions?

A

No, as this is the result of the clients imposition so can have reasonable objection. Client can then get someone else to do these works and charge this to the contractor

45
Q

What is loss and expense?

A

Direct loss and consequential loss by the contractor for delaying works, it is a relevant matter, and can be a relevant event if its a delay. (where he can prove it)

46
Q

What is a variation?

A

Alteration of the design, quality, or quantity of works.

47
Q

How do you value a variation?

A

Use rates in pricing schedule
Fair rates and prices
Approximate quants, use the rate
dayworks

48
Q

Do you have to use the rates in the contract?

A

If the extent of works is of similar character and nature yes. if not then a fair allowance based on the contract rate should be made.

49
Q

You say you managed risk through partnership, but did you employ risk management techniques?

A

Meetings, risk register, contractual design risk allocation, completing the design prior to contract execution, clear transparent comms with contractor