Contract Administration Flashcards
Contract Admin
1. How does the role of a CA differ to that of an EA?
a. The role of a CA differs to that of an EA as the CA simply administers the contract. The EA is responsible for all duties that the employer would usually perform.
b. The CA is impartial.
- Can you advise of a CA’s role at practical completion?
a. 50% retention is released (subject to the contract)
b. The 12 months defects period starts.
c. The ability to impose Liquidated Damages is ceased.
- Can you advise of a successful negotiation that you have undertaken and what you deem necessary for it to be successful?
a. On the Data centre procurement project, I negotiated the inclusion of items and the rates with the vendor, basing their costs on framework rates, and previous recent project submissions. I undertook critical analysis of the inclusion of items, ensuring substantiation and backup was received, as well as engineer approval where required.
b. I deem a negotiation successful when I can prove and substantiate to my client that there is value for money being achieved in the costs, and that they are in lie with current market rates. I also deem I t a success when successful clarification has been achieved between parties.
- What are the key differences between NEC and JCT?
a. PM in NEC
b. QS isn’t in NEC.
c. NEC collaborative
d. JCT has legal jargon, NEC is easier wording.
e. NEC more expensive to administer, more paperwork.
- What is a performance bond?
a. A performance bond is issued to one party of a contract as a guarantee against the failure of the other party to meet obligations in the contract.
- When may one be required?
a. Where the client needs to reduce the risk of non-performance of the contractor
b. Where the contractor doesn’t have a parent company.
c. If the contractor is new to working with this client.
d. If there is an ongoing economic crisis
- What types of performance bond are there?
a. On demand – payable immediately on beneficiary’s demand
b. Conditional – requires certain conditions to be met.
- If the client requested that you calculate and advise of the LD’s to be deducted, what would you suggest?
a. I would advise that this falls outside my area of expertise and knowledge, and I am not able to advise on this. I would suggest the client seek internal advice and legal help on this, to calculate what they would be owed. I would assist the client in noting any considerations that need to be made in relation to what costs may need to be sought after.
- How do partial possession and sectional completion differ?
a. Sectional completion is PC of a section of works, each section will have completion dates and rates of LAD’s, sectional completion is also in the contract, whereas partial possession is not pre agreed or stipulated in the contract.
- What would you do if a contractor could not provide a performance bond?
a. At the minute this is more common in the present market
b. I would firstly be concerned the contractor cannot provide this, as it could be proof that their financial situation is not good, I would therefore advise the client that entering into a contract with this contractor could be a large risk, which could be mitigated by diligent financial checks, such as Dunn and Bradstreet.
- What are the disadvantages of a performance bond?
- Insurers may attempt to deny payment.
- If they underestimate the cost of no performance, they will have to absorb any extra costs.
- Adds additional cost to contractor/client.
- What is the cost of a performance bond?
a. Usually, the value is 10% of the contract sum, and cost is 1%.
- What is time at large?
a. There is no current fixed date for completing works.
b. Usually this is down to the CA not doing his job properly.
- What is loss and expense?
a. Contractor can claim loss and expense due to Employers’ error.
- What are relevant matters?
a. They entitle the contractor to claim loss and expense.
- Give some Relevant Matters.
a. Variations
b. Instructions
c. Impediment by the Employer
- What is a Relevant Event?
a. Entitles the Contractor to an EoT
- What are some examples of Relevant Events?
a. Deferment of Possession
b. Variations
c. Impediment by the Employer
d. Exceptionally adverse weather conditions
e. In the new JCT suite – Covid-19/global pandemics
f. Force majeure
- What is force majeure?
a. Act of God.
- If there are concurrent delays, one fault of contractor and one the Employer, is there an entitlement?
a. There are no clear rules on this, each case has to be judged separately, and identify all causes and effects.
- How is the construction Act relevant?
a. Contains statutory provisions relating to all projects over 45 days
- What is the purpose of retention and what is it?
a. It is an amount deducted from payment to the contractor and retained until PC and EoMGD, it provides an incentive for the contractor to come and complete the works
- What is an alternative to retention
a. Retention bond, this is provided by the contractor for the same value, and is used to aid the contractors cashflow.
- What if the contract sum increases for a performance bond?
a. Then additional retention is deducted on that amount.
- What happens when PC is granted?
a. Half of retention is released
b. Rectification period beings
c. Employer now has to insure building
d. Liability for LAD’s ends
- What happens at end of rectification period?
a. Within 14 days a statement is issued for any defects that need rectifying, contractor has to make these within reasonable time.
b. Certificate of Making Good is issued, which triggers final valuation and release of retention.