Porter's Flashcards 2010
Bidding documents are considered contract documents.
- *Answer**: False
- *PRM Reference**: 5.1.2
Explanation: Procurement requirements are addressed to prospective bidders or proposers interested in the project. Although not necessarily part of a contract, the procurement requirements are usually bound with other written construction documents into a project manual.
Codes governing commercial construction and residential construction are different.
- *Answer**: True
- *PRM Reference**: N/A
- *Explanation**: Commercial building codes and residential codes are not the same.
The A/E usually hires a construction manager.
- *Answer**: False
- *PRM Reference**: 1.3
- *Explanation**: The owner usually engages the services of a construction manager, an entity that typically contracts with the owner to provide construction management services.
The owner, contractor, and A/E are parties to the construction agreements.
- *Answer**: False
- *PRM Reference**: 3.4.1.2, 5.3.1
Explanation: (3.4.1.2) Figure 3.2-A shows the tripartite relationship among the owner, contractor, and A/E. This relationship is created by obligations to third parties to the contract. For example, the owner-A/E agreement may require certain duties of the A/E acting on behalf of the owner. The contractor has a right to rely on the proper performance of these duties. The A/E, similarly, relies on the contractor to perform certain duties identified in the owner-contractor agreement, even though the A/E is not a party to that contract. The A/E relationship to the contractor in the owner-contractor agreement is a third-party relationship. These third-party relationships create the third side of the triangle in the construction process.
(5.3.1) A construction agreement might be executed with a contractor, a construction manager as a contractor, or a design-builder.
There are no differences between the AIA and EJCDC general conditions.
- *Answer**: False
- *PRM Reference**: 5.4.1.5
- *Explanation**: While similar, the AIA and EJCDC have some differences. For example, the AIA documents do not have a specific time frame for substitutions. The EJCDC documents permit substitutions within a limited time frame of executing the agreement. Each document deals with these concerns in a similar manner but with language determined to be in accord with the needs of each organization. In general, the DBIA general conditions provide fewer details and requirements than do the EJCDC and AIA documents because the designer and the builder are acting as a single entity.
The drawings take precedence over the specifications.
Answer: False
PRM Reference: 5.11.4.4, 7.8.1.1
Explanation: The drawings and specification are complementary documents in the AIA and EJCDC general conditions.
(5. 11.4.4) Precedence: Questions of precedence often arise among large scale drawings, small-scale drawings, and specifications. However, the use of statements in the project manual to establish the precedence of the various contract documents is not recommended because the documents are complementary. The general conditions of the contract should indicate only that in a case of conflict between drawings and specifications, the A/E will make a documented interpretation.
(7. 8.1.1) When the contract documents are being interpreted, the contents of the drawings and the specifications must be considered together. If an item is that it is not required for the project. not addressed in both the drawings and the specifications, it does not mean
The role of a subcontractor is the same as a material supplier.
- *Answer**: False
- *PRM Reference**: 1.3
- *Explanation**: A subcontractor generally provides labor at the site. A material supplier furnishes the materials for others to install.
- Subcontractor*: An entity that has a direct contract with the contractor to perform a portion of the work of the project at the site.
- Supplier*: Furnishes or supplies products or services for the project, but does not perform labor at the site.
The supplementary conditions should be coordinated with the owner/contractor agreement.
- *Answer**: True
- *PRM Reference**: 5.3
Explanation: The construction agreement is based on provisions of the conditions of the contract (general and supplementary), which becomes part of the contract. The agreement defines relationships and obligations between the signers and incorporates, by reference, all of the other documents that make up the contract documents: contracting forms; project forms; conditions of the contract (general and supplementary conditions); specifications; contract drawings; and revisions (addenda), clarifications, and modifications. The clauses and provisions of the general conditions for a construction contract are generally fixed and usually require only supplements to be adapted to a specific project. The agreement contains contractual elements that are subject to variation in each contract.
Preliminary Project Descriptions are legal and binding construction documents.
- *Answer**: False
- *PRM Reference**: N/A
- *Explanation**: Preliminary project descriptions and outline specifications are informational documents issued to the project team prior to construction documents.
The contractor and the A/E review submittals for the same reasons and from the same point of view point.
- *Answer**: False
- *PRM Reference**: 7.5.6
Explanation: The contractor reviews submittals for constructability and compliance to the contract documents. The A/E reviews submittals for compliance with design intent and to the contact documents. Each reviews submittals based on their agreements (A/E from the design point of view; contractor from the constructability point of view.)
Submittals are reviewed and approved by the contractor to ensure contract requirements have been met, to check dimensions, and to coordinate with subcontractors.
The A/E’s review is limited to determining whether the submittal is consistent with the design intent and the contract documents.
Division 01 sections expand and cross reference the conditions of the contract in all cases.
- *Answer**: True
- *PRM Reference**: 5.6
- *Explanation**: Division 01 sections expand on certain of the administrative and procedural provisions in the conditions of the contract and apply broadly to the execution of the work of all the other sections of the specifications.
Repetition of information on both drawings and specifications is a good way to emphasize its importance.
- *Answer**: False
- *PRM Reference**: 5.1.1
Explanation: Another important principle governing the production of construction documents is that each document, written or graphic, has a specific purpose and should be used for that purpose. Each requirement should be stated only once and in the correct location.
Performance bonds as part of construction submittals are part of the procurement requirements.
- *Answer**: False
- *PRM Reference**: 5.1.2
Explanation: Typically, procurement requirements include the following documents: solicitation; instructions for procurement; available information, including resource drawings; procurement forms and supplements; addenda (as applicable to procurement).
The invitation to bid is designed to attract qualified bidders.
- *Answer**: True
- *PRM Reference**: 5.2.3.1
Explanation: The invitation to bid is intended to attract qualified bidders and to help prospective bidders decide whether to obtain the procurement documents.
The volume containing the specifications, conditions of the contract, information to bidders, instructions to bidders, and the bid form is called:
(A) Spec book.
(B) Table leveler.
(C) Project manual.
(D) Door stop.
(E) None of the above.
(F) All of the above.
- *Answer**: C
- *PRM Reference**: Figures 5.1-A, 5.1.2
Explanation: See figure 5.1-A in PRM
The documents developed to attract and assist qualified bidders in properly submitting bids are called contract documents.
- *Answer**: False
- *PRM Reference**: 5.1.2
Explanation: Procurement requirements instruct the bidders or proposers about the established procedures or preparing and submitting their bids or proposals.
The Agreement:
(A) Defines the relationship of the owner, A/E, and contractor.
(B) Is the one instrument of the contract documents that binds the signing parties to the work.
(C) Constitutes the legal portion of the specifications.
(D) None of the above.
(E) All of the above.
- *Answer**: B
- *PRM Reference**: 3.3.4
- *Explanation**: The agreement is the written document signed by each party, and it is the legal instrument binding the parties to the contract.
An alternate:
(A) Is the same as an option in the specifications.
(B) Is used for the same purpose as unit prices.
(C) Should be described in Division 01 and specified in the appropriate specification sections.
(D) Should be described in detail on the bid form.
(E) None of the above.
- *Answer**: C
- *PRM Reference**: 4.6.4, 5.2.3.4, 5.6.3.1
Explanation: (4.6.4) Alternates should be carefully expressed in the pricing documents, including the criteria by which alternates will or will not be awarded. Alternates should be clearly delineated on the drawings as well as addressed appropriately in the specifications. If this is not done carefully, misunderstandings and misinterpretations can occur regarding the scope of an alternate.
(5.2.3.4) Alternates may be either additive or deductive to the base bid, the stipulated sum bid, or the total unit-price bid.
Appropriate blanks should be provided on the bid form. They must be clearly described in Division 01, Section 01 23 00-Alternates. The instructions to bidders should contain guidance for preparing alternate bids.
(5.6.3.1) Division 01 sections on allowances and alternates require particular coordination with the sections in other divisions that specify the affected products.
Contract Documents consist of:
(A) Agreement between owner and contractor, conditions of the contract, drawings, and specifications, addenda and modifications, other documents listed in the agreement.
(B) Agreement between owner and contractor, conditions of the contract, drawings and specifications, project manual, shop drawings.
(C) Agreement between owner and contractor, conditions of the contract, drawings and specifications, instructions to bidders, bid form, addenda, modifications, other documents listed in the agreement.
- *Answer**: A
- *PRM Reference**: 5.2.1
- *Explanation**: The contract documents include contracting forms, project forms, conditions of the contract, specifications, contract drawings, revisions, clarifications, and modifications and, excluding the drawings, are bound together into a volume called the project manual.
Contract documents include:
(A) Written portions of the contract only.
(B) Graphic portions of the contract only.
(C) Both written and graphic portions of the contract.
(D) Agreement and general and supplementary conditions.
- *Answer**: C
- *PRM Reference**: 5.1.4
- *Explanation**: Contract documents consist of both written and graphic elements and typically include the following: contracting requirements, specifications, contract drawings.
Addenda are used to:
(A) Modify the procurement documents before award of the contract.
(B) Modify the contract documents after award of the contract.
(C) Modify drawings and specifications only.
(D) Formalize verbal instruction given on the job.
- *Answer**: A
- *PRM Reference**: 5.1.4.3
Explanation: Addenda are written or graphic documents issued to clarify, revise, add to, or delete information in the original procurement documents or in previous addenda. Typically, an addendum is issued prior to the receipt of bids or proposals. Other revisions may include bid or proposal revisions when permitted.
The agreement is part of the:
(A) Bidding requirements.
(B) General conditions.
(C) Specifications.
(D) Contract forms.
- *Answer**: D
- *PRM Reference**: 6.9.1
- *Explanation**: The form of agreement to be used for a project is identified in the procurement documents. It is proper for procurement documents to contain the form of agreement for the prospective contractor’s reference.
Division 01 should be used to:
(A) Provide a location for general and supplementary conditions.
(B) Provide a means to modify standard sections of the specifications.
(C) Provide a logical arrangement for specifying administrative, procedural, and temporary facilities.
(D) Provide a location for specifying special construction and materials the bidders might overlook.
- *Answer**: C
- *PRM Reference**: 5.6
- *Explanation**: See PRM 5.6 for a complete discussion.
Division 01 sections relate to:
(A) Bidding requirements, the agreement, general and supplementary conditions, and specifications.
(B) Bidding requirements, the agreement, general and supplementary conditions, the specifications, and the drawings.
(C) The agreement, general and supplementary conditions, and specification only.
(D) The agreement, general conditions, specifications, and drawings.
- *Answer**: B
- *PRM Reference**: 5.6.2
- *Explanation**: See PRM 5.6.2 for a complete discussion.
Division 01 sections should coordinate with bidding requirements, the agreement, general and supplementary conditions, specifications, and drawings.
- *Answer**: True
- *PRM Reference**: 5.11.4.1, 5.6.2.5
Explanation: (5.11.4.1) Particular attention should be given to coordinating Division 01 sections with the conditions of the contract. The level of specification detail should complement the level of drawing detail. Early coordination with sufficient time devoted to the task will help achieve design intent and promote elimination of problems during the construction stage.
(5.6.2.5) Specification sections are subject to the administrative and procedural requirements of the conditions of the contract and of Division 01.
Administrative and procedural requirements and temporary facilities are specified in:
(A) General conditions.
(B) Supplementary conditions.
(C) Division 01.
(D) Bidding requirements.
- *Answer**: C
- *PRM Reference**: 5.6
- *Explanation**: The sections in Division 01, which are collectively referred to as the General requirements, specify administrative requirements, procedural requirements, temporary facilities and controls, performance requirements, and life cycle activities.
Division 01 administrative, procedural matters, and temporary facilities are cost items, the same as products and work in the technical specifications.
- *Answer**: True
- *PRM Reference**: 5.6.4.10
Explanation: Division 01 administrative and procedural requirements and temporary facilities and controls involve both direct and indirect costs. Over-specifying in Division 01 may increase construction costs unnecessarily and may create excessive obligations for the entity administering the construction contract.
All of the following are true about the use of standardized general conditions, such as the AIA A201 and EJCDC C-700, except:
(A) A/Es and contractors involved generally are familiar with the contents.
(B) Having been reviewed initially by legal counsel, an attorney need not be consulted for the project.
(C) The language has stood the test on time.
(D) They establish a baseline from which exception, modifications, and additions can be identified and evaluated. project.
- *Answer**: B
- *PRM Reference**: 5.3.3
Explanation: The agreement form and the respective conditions of the contract should be reviewed carefully by the owner’s legal counsel before modification to satisfy specific project requirements.
If a contractor recognizes or has knowledge of errors, inconsistencies, or omissions in the contract documents, the contractor is responsible for reporting those errors, omissions, or inconsistencies to the A/E and may be held liable if he does not.
- *Answer**: True
- *PRM Reference**: Figure 5.6-D, 7.8.1.1
- *Explanation**: Typically, the conditions of the contract require the contractor to report errors, inconsistencies, or omissions to the A/E.
Shop drawings, product data, and samples are considered part of the contract documents and are legal documents.
- *Answer**: False
- *PRM Reference**: 7.5
Explanation: During the construction of a project, the contractor is usually required by the contract documents to submit product data, shop drawings, and samples to the A/E for review. These submittals are typically not contract documents and are not to be used by the contractor or the A/E to modify the contract.