Contract Days by the Numbers Flashcards

1
Q

Architect issue addendum to all bidders for acceptable substitution

A

4 days

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
2
Q

Architect issues Certificate for Payment within _____ days after Contractor applies

A

7 days

The Architect will, within seven days after receipt of the Contractor’s Application for Payment, either (1) issue to the Owner a Certificate for Payment in the full amount of the Application for Payment, with a copy to the Contractor; or (2) issue to the Owner a Certificate for Payment for such amount as the Architect determines is properly due, and notify the Contractor and Owner of the Architect’s reasons for withholding certification in part as provided in Section 9.5.1; or (3) withhold certification of the entire Application for Payment, and notify the Contractor and Owner of the Architect’s reason for withholding certification in whole as provided in Section 9.5.1.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
3
Q

Owner pays Contractor within ___ days after the date established in the Contract Documents.

A

7 days

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
4
Q

Contractor pays subs and suppliers

A

7 days

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
5
Q

Contractor can stop the Work if Architect does not issue a Certificate for Payment within ___ days after receipt of the Contractor’s Application for Payment.

A

19.7 Failure of Payment

If the Architect does not issue a Certificate for Payment, through no fault of the Contractor, within seven days after receipt of the Contractor’s Application for Payment, or if the Owner does not pay the Contractor within seven days after the date established in the Contract Documents, the amount certified by the Architect or awarded by binding dispute resolution, then the Contractor may, upon seven additional days’ notice to the Owner and Architect, stop the Work until payment of the amount owing has been received.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
6
Q

The Contractor shall pay each Subcontractor, no later than ___ days after receipt of payment from the Owner.

A

9.6.2 The Contractor shall pay each Subcontractor, no later than seven days after receipt of payment from the Owner, the amount to which the Subcontractor is entitled, reflecting percentages actually retained from payments to the Contractor on account of the Subcontractor’s portion of the Work.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
7
Q

If requested, the Contractor has ___ days to furnish written evidence that he has properly paid Subcontractors and suppliers amounts paid by the Owner to the Contractor for subcontracted Work.

A

9.6.4 The Owner has the right to request written evidence from the Contractor that the Contractor has properly paid Subcontractors and suppliers amounts paid by the Owner to the Contractor for subcontracted Work. If the Contractor fails to furnish such evidence within seven days, the Owner shall have the right to contact Subcontractors and suppliers to ascertain whether they have been properly paid. Neither the Owner nor Architect shall have an obligation to pay, or to see to the payment of money to, a Subcontractor or supplier, except as may otherwise be required by law.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
8
Q

Contractor can ask Owner proof of Financial ability before & days of Final Bid Receipt

A

7 days

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
9
Q

Written Notice needed to terminate Contract bet Owner-Architect, Owner-Contractor, Architect- Consultant

A

7 days

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
10
Q

Owner can terminate contract with Architect or Contractor w/o cause within __ days of written notice

A

7 days

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
11
Q

Architect can terminate contract with CONSULT. w/o cause within __ days of written notice

A

7 days

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
12
Q

Owner has __ days to return Dwgs to Architect after termination of contract

A

7 days

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
13
Q

Architect has __ days to return Dwgs to Consultant after termination of Contract

A

7 days

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
14
Q

Substitution for a materials, system or product to architect before the bid deadline

A

10 days

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
15
Q

Contractor has __ days to correct work after Owner notifies

A

10 days

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
16
Q

Architect has time to review Claim

A

10 days

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
17
Q

To respond to initial decision makers’ request for additional supporting data

A

10 days

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
18
Q

Request Cert of Pay before Schedule of Value date of actual Payment

A

10 days

19
Q

Super name objection by Architect or Owner

A

14 days

20
Q

Owner to Request for architects certificates

A

14 days

21
Q

Owner has __ days to furnish all info to Contractor or Architect for filing Lien claim

A

15 days

22
Q

Notifying of concealed subsurface condition

A

14 days

23
Q

Damage discovered; notify Owner or Architect within __ days

A

21 days

24
Q

Damage to each other file claim within __ days of occurrence of problem

A

21 days

25
Q

Architect has __ days to take decision on a claim- if no decision Architect/ Contractor can go for Mediation

A

30 days

26
Q

Either party can demand in writing within __ days of initial decision to the other party to file for mediation within 60 days of initial decision

A

30 days

27
Q

Owner and Architect go for Arbitration with __ days of Mediation decision

A

30 days

28
Q

Notice given to Owner by Contractor or Architect by CONSULT. before actual insurance expires

A

30 days

29
Q

Contractor can terminate contract if No Fault/ Govt rule/ no Pay

A

30 days

30
Q

Architect / CONSULT. receives compensation after work is resumed for interruption, delay if work stopped more than __ days

A

30 days

31
Q

Final payment to the Contractor is due no later than __ days after the issuance of the Architects final certificate for payment

A

30 days

32
Q

File lien within __-__ days after the last work is performed or materials are installed

A

30-90 days

33
Q

__ days consecutive / ___ days/ 100% schedule time in One Year work is stopped – Contractor can terminate Contract

A

60 days consecutive / 120 days/ 100% schedule time in One Year work is stopped – Contractor can terminate Contract

34
Q

__ days Mediation stays pending after date of filing

A

60 days Mediation stays pending after date of filing

35
Q

Change of service for Architect and CONSULT. if Construction Admin Service goes beyond __ days

A

60 days

36
Q

Architect / CONSULT. can terminate Contract of work stopped __ consecutive days

A

90 consecutive days

37
Q

If Bidding is not progressed after CD documents is issued Project Budget subject to modification

A

90 days

38
Q

Architect to Return Submittals/ shops

A

Reasonable Promptness

39
Q

Respond to RFI

A

Reasonable Promptness

40
Q

CONSULT to seek arbitration within reasonable time after claim

A

Reasonable Promptness

41
Q

Time to claim warranty after Substantial Completion

A

1 Year

42
Q

Suit to enforce the bond must be brought within __ years from the date on which final payment under the contract is due

A

2 years

43
Q

Time limit on Claim after Substantial Completion

A

10 years