Mondo Datapoints Flashcards

1
Q

Project Conception Phase

A
  • Owner’s needs and requirements are identified
  • Preliminary studies are performed
  • Site is selected
  • Preliminary budget and schedule are established
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
2
Q

Project Delivery Methods

A

Project Delivery Methods

  • Design-bid-build
  • Design-negotiate-build
  • Design-build
  • Construction management
  • Owner-build
  • Integrated project delivery
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
3
Q

Substantial Completion establishes responsibilities of Owner and
 Contractor for

A

Substantial Completion establishes responsibilities of Owner and
 Contractor for

  • Security
  • Maintenance
  • Heat
  • Utilities
  • Damage to Work
  • Insurance
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
4
Q

Mobilization

A

Mobilization

The setting up of temporary facilities that the contractor will need to perform the work. Occurs after notice to proceed. Elements include:

  • Use of Site
  • Site Security
  • Temporary Facilities
  • Temporary Utilities
  • Temporary Controls
  • Equipment
  • Environmental Protection Requirements
  • Project Site Safety
  • Utility Locations
  • Survey/Layout/Datum
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
5
Q

Preconstruction meetings include

A

Preconstruction meetings include

  • Procedural Meeting
  • Site Mobilization Meeting
  • Utility Coordination Meeting
  • Meetings with AHJs
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
6
Q

Contractor’s Liability Insurance

A

Contractor’s Liability Insurance

Contractor purchases and maintains insurance to protect himself from 
claims resulting from operations under Contract at limits specified or 
required

  • Worker’s compensation
  • Bodily injury or death of Contractor’s employees
  • Bodily injury or death of other than Contractor’s employees
  • Personal injury liability
  • Damages because of injury or destruction of tangible property
  • Use of motor vehicles
  • Damage arising out of completed operations
  • Contractual liability
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
7
Q

SectionFormat - PART 1

A

Part 1 - General

  • Summary
  • Price and Payment Procedures
  • References
  • Administrative Requirements
  • Submittals
  • Quality Assurance
  • Delivery, Storage, and Handling
  • Field Conditions
  • Warranty

Note locations of QA and QC. With each Part of the Specification QA = Part I.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
8
Q

SectionFormat - PART 2

A

Part 2 - Products

  • Owner-Furnished Products
  • Materials/Products/Equipment
  • Manufacturers
  • Description
  • Performance/Design Criteria
  • Operation
  • Materials
  • Fabrication
  • Mixes
  • Finishes
  • Accessories
  • Source Quality Control
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
9
Q

SectionFormat - PART 3

A

Part 3 - Execution

  • Installers
  • Examination
  • Preparation
  • Erection/lnstallation/Application
  • Repair/Restoration
  • Reinstallation
  • Field Quality Control
  • System Start-up
  • Adjusting
  • Cleaning
  • Closeout Activities
  • Protection
  • Maintenance
  • Attachments

End of Section

  • Schedules
  • Tables
  • Illustrations
  • Forms
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
10
Q

Division 00 - Procurement and Contracting Requirements

A
  • Bid solicitation
  • Instructions to bidders
  • Information available to bidders
  • Bid forms and attachments
  • Bid security form
  • Bonds
  • Certificates
  • The agreement (contract)
  • General conditions of the contract
  • Supplementary conditions
  • Addenda
  • Modifications
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
11
Q

Revision, Clarifications, Modifications

A

Before receipt of bids

  • Addenda
  • Substitution requests

Between receipt of bids and contract execution

  • Post-bid addenda
  • Negotiations
  • Substitution requests

After contract execution

  • Change orders
  • Substitution requests
  • Requests for interpretation
  • Supplemental Instructions
  • Written amendments
  • Construction change
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
12
Q

Division 01 - General Requirements

A
  • Summary of the work
  • How pricing ♦ payment will be handled
  • Alternates
  • Value analysis
  • Contract modification procedures
  • Unit prices
  • Construction progress documentation
  • Submittal procedures (shop drawings, etc.)
  • Quality control
  • Temporary facilities
  • Product substitution procedures
  • Owner-furnished items
  • Special execution requirements
  • Final cleaning ♦ inspection
  • Sustainability
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
13
Q

Procurement Requirements

A

Procurement Requirements

  • Solicitation
  • Instructions for procurement
  • Available information
  • Procurement forms and supplements
  • Addenda
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
14
Q

Contract Requirements

A

Contract Requirements

  • Contract forms
  • Project forms

  • Conditions of the Contract
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
15
Q

Contracting Requirements

A

Contracting Requirements.

Contracting requirements define the processes, rights, responsibilities, and relationships of the parties to the contract and include the following:

  • Contracting forms
  • Project forms
  • Conditions of the contract
  • Revisions
  • Clarification
  • Modifications
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
16
Q

Project Manual

A

Project Manual

  • Procurement Requirements
  • Contract Forms
  • Project forms
  • Conditions of the contract
  • Specifications
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
17
Q

Procurement Documents

A

Procurement Documents

  • Procurement Requirements
  • Contracting Forms
  • Contract Forms
  • Conditions of the Contract
  • Specifications
  • Drawings
  • Addenda
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
18
Q

Construction Documents

A

Construction Documents

  • Procurement Requirements
  • Contracting Forms
  • Contract Forms
  • Conditions of the Contract
  • Specifications
  • Drawings
  • Addenda
  • Contract Modifications
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
19
Q
  • Contracting Forms
  • Contract Forms
  • Conditions of the Contract
  • Modifications
A

Contracting Forms

  • The Agreement

Contract Forms

  • Performance bond
  • Payment Bond
  • Certifications

Conditions of the Contract

  • General information
  • Supplementary Conditions

Modifications

  • Written amendment
  • Change order
  • Construction change directive
  • Written order for a minor change
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
20
Q

8 typical elements of contract documents

A

8 typical elements of contract documents

  • Contracting forms
  • Contract forms
  • Conditions of the Contract
  • Revisions
  • Clarifications
  • Modifications
  • Specifications
  • Contract drawings
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
21
Q

AIA A201: Long History of Success

A

AIA A201: Long History of Success

  • First issued in 1888
  • Well known and understood by A/Es, Contractors, and Insurers
  • Basis for many Owner developed General Conditions
  • Tested in the Courts
  • 1915 to 1963, Architect had “general supervision and direction of the Work”.
  • 1963, Architect makes “periodic site visits”
  • 1965, Major reorganization, Project Manual emerges
  • 1970, Architect no longer responsible to “stop the Work”
  • AGC “endorsed” A201 until 2007
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
22
Q

Solicitation

A

Solicitation

PROJECT IDENTIFICATION. Clearly identify the owner and the architect/engineer issuing the documents, including full name, address,
 and telephone number. Show the name or title of the project in a conspicuous manner and the project number. Include the date of issue of
the procurement documents.

DESCRIPTION OF WORK. Briefly describe the project type and size and major characteristics of construction to give an idea whether the 
project is within the bidder’s work capacity and financial ability. This
 description should not be elaborate or detailed. It is intended only to
 help the bidder determine whether it is worthwhile to obtain procurement documents. Estimated costs of the project should not be 
mentioned unless it is a legal requirement. Costs are a matter for the 
bidder to determine.

TYPE OF BID. Indicates briefly the type of bid required, that is, whether stipulated sum, cost-plus fee, or unit price bids are required, and
 whether there are alternates or bidder proposed substitutions. If separate bids are allowed, indicate acceptable combinations. Give details
 on the type of bid in the instructions to bidders.

TIME OF COMPLETION. If established, states the number of days 
allowed for constructing the project or the date by which substantial 
completion or final completion is desired. State whether the time of completion is stipulated or to be filled in on the bid form by the bidder.

PREBID MEETING. States date, time, and location. Advise bidders if
 attendance at this meeting is mandatory or voluntary.

BID OPENING. States who will receive bids, when and where bids will
 be opened, and whether the opening will be public or private. For
 private bid openings, state who can attend. Sometimes bidders are
 permitted to attend private openings that are closed to subbidders
 and trade publication representatives.

DOCUMENT AVAILABILITY. Lists the locations and addresses where
 procurement documents may be examined. State where documents 
can be obtained and give information regarding charges, deposits,
 and refunds. Coordination between the solicitation and the instructions to bidders is necessary to prevent repetition or discrepancies.


BIDDER QUALIFICATIONS. If required, and qualifications required of 
the bidder/contractor should be mentioned.

BID SECURITY. States whether a bid security is required and whether 
it is a percentage of the bid or a fixed amount. Give details concerning 
the security in the instructions to bidders.

OWNER RIGHT TO REJECT BIDS. States that the owner reserves the 
right to waive irregularities and to reject bids.

LAWS AND REGULATIONS. Includes specific laws and regulations, such
 as those covering nondiscrimination in employment and wage rates.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
23
Q

00 21 13 Instructions to Bidders

A

00 21 13 Instructions to Bidders

The instructions to bidders will not be as brief as the solicitation because they 
contain specific information not included in the other procurement requirements;
 the instructions are the information a bidder needs to properly prepare and submit a 
bid. The instructions also describe conditions affecting the award of the contract.

DOCUMENTS. State whether documents will be issued to other than 
prime bidders. Include information
 about the availability of documents to supplement information in the bid
 solicitation. Issuance of partial sets of documents should be avoided.
 Explain conditions and requirements governing return of documents
 by bidders, including time for their return and refund of deposits. 
Some architect/engineers prefer to include this information in the 
invitation to bid, rather than in the instructions, to eliminate repetition;
 however, the invitation is often limited in size through circumstances 
beyond the preparer’s control. Minimum information should still appear 
in the invitation, but complete details should be given in the instructions.


EXAMINATION OF DOCUMENTS, SITE, AND LOCAL CONDITIONS.
 Explain that the bidder is responsible for examining the documents, 
the site, and the local conditions that will affect the work. Give limitations on time of examination and describe arrangements necessary
 for the examination, and, when applicable, give a name and telephone
 number of the person to contact.

INTERPRETATIONS DURING BIDDING. Describe how discrepancies and 
ambiguities in the documents will be resolved during the bidding period
 and give instructions for obtaining the information.

  • Name and address of the entity to which inquiries and requests for clarification should be directed.
  • Manner in which such requests are to be made, including 
time limits.
  • Replies should be issued as addenda. State how and when
 addenda will be issued and to whom they will be sent. Include 
time limits.

SUBSTITUTION OF PRODUCTS. The practice of listing more than one
 product or manufacturer for a given material description is preferred
 (and may also be required in some public work) by many architect/
engineers to stimulate competition among suppliers. Some circumstances allow for substitution of products other than those specified. 
The architect/engineer should state the requirements and procedures 
under which proposed substitutions of materials and methods will be
 considered. If such consideration is during the bidding period, include 
a date prior to bid opening after which requests for substitutions will
 no longer be considered. Refer the bidders to Division 01, Specification Section 01 25 10, Substitution Procedures, for specific requirements and procedures for requesting substitutions.

TYPE OF BID. Describe the type of bid required. There are several
 possibilities, and the instructions to bidders should clearly state the
 requirements and conditions for the bid type. The instructions to 
bidders should also include guidance for preparing items on the bid
 form, such as combined bids, allowances, alternates, and unit prices.


PREPARATION OF BID. Inform bidders how bids are to be prepared,
 including instructions for forms to be used and the number of copies 
required. Give explicit instructions regarding the signatures required.
 Describe any additional information to be submitted with the bid.

BID SECURITY INFORMATION. Inform bidders if a bid security will be 
required, and what amount and form.

PERFORMANCE BOND AND PAYMENT BOND. Indicate if bonds will 
be required. Performance and payment bonds, each equal to 100 percent of the contract sum, are usually required for public work and are 
recommended for private work. If bonds are required, stipulate the
 time period in which they must be furnished. Coordinate this requirement with the conditions of the contract.

SUBCONTRACTOR LISTING. Where applicable, explain conditions and 
requirements relating to listing and acceptance of proposed subcontractors. Instruct the bidders to submit the information as a listing 
on the bid form or as a supplement to the bid form, or to note that it
 will be furnished within a specified time after the bid opening. Where 
appropriate, give information about the significance of such a list in
 evaluating the bids and how binding the list may be.

IDENTIFICATION AND SUBMITTAL OF BID. Indicate how to identify 
the bid, the project name, number, contract number, owner, bid date
 and time, and name of bidder. Give instructions regarding submittal
 of the completed bid and whether a sealed envelope is required.


MODIFICATION OR WITHDRAWAL OF BID. Indicate whether bids may
be modified between submittal and opening. Explain the circumstances under which a bidder may not withdraw the bid. Include a list of conditions 
under which bids may be withdrawn without forfeiture of bid security
 and describe the procedures to be followed when doing so. State the length
 of time the owner may hold bids before any withdrawal is permitted.

DISQUALIFICATION OF BIDDERS. List conditions or irregularities under which a bidder may be disqualified.

SPECIAL APPLICABLE LAWS. List applicable federal, state, and local
 laws and regulations. Avoid an exhaustive list and avoid implying that 
the list is complete. The listed items may include:

Licensing of contractors for special requirements,

Requirements for special construction permits,

Exemption from sales tax, if applicable,

Wage rates and employment requirements when required by 
law or by the owner,

Local labor agreements, and

Nondiscriminatory hiring practices.

PREBID MEETING. Refer the bidder to the solicitation and provide any 
supplemental information not included in the solicitation.


LIQUIDATED DAMAGES. Provide information about provisions relating to liquidated damages.

OPENING OF BIDS. Refer the bidder to the solicitation for information 
about date, time, and place for opening of bids.

EVALUATION AND CONSIDERATION OF BIDS. Describe the basis under which the owner will award the contract, including considerations
 of alternates and unit prices. If applicable, the order in which alternates are to be accepted should be stated, if there is one. Reserve for 
the owner the right to waive irregularities in a bid or to reject all bids.


EXECUTION OF AGREEMENT. List requirements and conditions for execution of the agreement, including the preparation and examination.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
24
Q

Available Information

A

Available Information

There are various types of information that should be made available to bidders, proposers, and contractors during procurement and execution of the work. This information is
 not contract documents.

00 31 13 Preliminary Schedules - Preliminary schedule information, when provided, is normally included as advisory data to be used by the bidders and proposers in preparing their bids and proposals. This information is not part of the contract documents unless specifically incorporated in the agreement.

00 31 16 Project Budget Information - There are occasions when it is necessary for the owner to make bidders, proposers, and contractors aware of the owner’s budget.

00 31 19 Existing Condition Information - For projects that involve renovations or additions to existing facilities, it is common 
to provide bidders, proposers, and contractors with information about the existing 
conditions that might also include the construction documents of existing structures.

00 31 21 Survey Information - Virtually every project requires the owner to disclose essential information about
 the project site, such as the location of property lines and boundaries, descriptions of site conditions and existing facilities, topography, and underground utility 
locations that are known.

00 31 24 Environmental Assessment Information - Environmental assessments studies are sometimes required to be disclosed. 
Examples include soil contamination reports, environmental impact study report,
 or environmental impact mitigation report.

00 31 25 Existing Material Information - For projects involving renovations or additions, there may be existing materials 
that should be disclosed.

00 31 26 Existing Hazardous Material Information - It is good professional practice to make bidders, proposers, and contractors 
aware of hazardous materials that might be present in existing facilities that are 
to undergo renovations or additions, such as the presence of asbestos, lead, poly
chlorinated biphenyl, mold, or hazardous waste.

00 31 31 Geophysical Data - Some building sites may require more sophisticated investigations to discover 
and document seismic, magnetic, electromagnetic, electrical resistivity phenomenon, and like geotechnical data needs to be disclosed to the bidders, proposers,
 and contractors.

00 31 32 Geotechnical Data - It is common to make bidders, proposers, and contractors aware of the findings 
discovered by a geotechnical investigation prior to solicitation, such as soil boring 
data, subsurface drilling and sampling information, soil and rock strata formations present.

00 31 43 Permit Application - Bidders or proposers may need to be made aware of a building code or regulatory requirement that would not ordinarily be discovered during the procurement 
process that may affect the bid, proposal, or execution of the work. An example might be a permit that is required for a project close to an airport, a major
 highway, a facility being built over a railway, or within a particular governmental jurisdiction.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
25
Q

What are the four C’s for effective communication?

A

What are the four C’s for effective communication?

  • Clear. Use proper grammar and simple sentence construction to avoid ambiguity.
  • Concise. Eliminate unnecessary words, but not at the expense of clarity, correctness, or completeness.
  • Correct. Present information accurately and precisely. Carefully select words that convey exact meanings.
  • Complete. Do not leave out important information.
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
26
Q

What elements are typically included in Procurement Requirements?

A

What elements are typically included in Procurement Requirements?

  • Solicitation
  • Instructions for procurement
  • Available information
  • Procurement forms and supplements
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
27
Q

Contractors

A

Contractors

Contractor solely responsible for, and have control over, the following 
construction activities:

  • Means
  • Methods
  • Techniques
  • Sequences
  • Procedures
  • Coordination

Contractors are now responsible for performing their own due diligence regarding the safety of
 construction means and methods dictated in the Contract Documents.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
28
Q

Labor and Materials

A

Labor and Materials

Contractor provides and pays for following for proper
 execution and completion of the Work

  • Labor
  • Materials
  • Equipment
  • Tools
  • Construction equipment
  • Water
  • Heat
  • Utilities
  • Transportation
  • Other facilities and services
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
29
Q

Contractor shall secure and pay

A

Contractor shall secure and pay

  • Building permit
  • Other permits
  • Fees
  • Licenses
  • Inspections by government agencies
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
30
Q

Contractor 
assumes responsibility and bears cost for correction

A

If Contractor performs Work contrary to following, Contractor 
assumes responsibility and bears cost for correction

  • Laws
  • Statutes
  • Ordinances
  • Codes
  • Rules and regulations
  • Lawful orders of public authorities
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
31
Q

Costs included in Allowance

A

Costs included in Allowance

  • Cost of material and equipment delivered to site
  • Taxes, less trade discounts
32
Q

Costs included in Contract Sum

A

Costs included in Contract Sum

  • Unloading and handling at site
  • Labor
  • Installation
  • Overhead
  • Profit
  • Other expenses
33
Q

Changes accomplished after Contract execution that does not 
invalidate Contract

A
  • Change order - Based on agreement among Owner, Contractor and
 Architect
  • Construction Change Directive - Requires agreement by Owner and
 Architect and may or may not be agreed to by Contractor
  • Minor change in the Work - Issued by Architect alone
34
Q

Change Order

A

Change Order

Written instrument,
 prepared by Architect
 and signed by Owner
 and Contractor, agreeing
 to

  • Change in the Work
  • Amount of adjustment in
 Contract Sum
  • Amount of adjustment in
 Contract Time
35
Q

Methods for adjustment of
 Contract Sum

A

Methods for adjustment of
 Contract Sum

  • Itemized lump sum
  • Unit price
  • In a manner mutually agreed
36
Q

Minor changes in the 
Work

A

Architect has authority to
 order minor changes in the 
Work not involving

  • Adjustment in Contract Sum
  • Adjustment in Contract Time
  • Not inconsistent with Contract 
Documents
37
Q

Delays and Extensions of Time

A

Delays and Extensions of Time

If Contract Time is delayed by any of the following then extend the Change Order:

  • Act or neglect by Owner or Architect
  • Changes in the Work
  • Labor disputes
  • Fire
  • Unusual delay in deliveries
  • Unavoidable casualties
  • Mediation or arbitration
  • Other causes justified by Architect
  • Adverse weather conditions
  • Other causes beyond the Contractor’s control
38
Q

List the 3 typical contract forms:

A

List the 3 typical contract forms:

  • Notice of award
  • Agreement
  • Attachments to the agreement
39
Q

List several reasons construction warranties are usually required.

A

List several reasons construction warranties are usually required.

  1. To protect against faults, defects or failures
  2. To provide a remedy for non-conformance after completion and acceptance
  3. To give recourse against additional parties
  4. To extend the manufacturer’s responsibility beyond the end of the correction period
  5. To allow a remedy beyond the normal statute of limitations
40
Q

What six separate limits of liability are covered in general liability policies?

A

What six separate limits of liability are covered in general liability policies?

  • General aggregate limit
  • Products/completed operations aggregate
  • Personal and advertising injury limit
  • Each occurrence limit
  • Fire damage limit
  • Medical expense limit
41
Q

In the CSI CDT program, construction document production is defined to be

A

In the CSI CDT program, construction document production is defined to be

A separately-defined activity and phase that commences once design decisions have been made, a component of the input into, and reporting out of, a BIM model; an ongoing effort by many entities reflecting the collaboration and fast track delivery typical of modern construction projects

42
Q

The nationally-recognized California AIA “Integrated Project Delivery Guide” redefines the stages of a project to include

A

The nationally-recognized California AIA “Integrated Project Delivery Guide” redefines the stages of a project to include

  • Conceptualization
  • Criteria Design
  • Detailed Design
  • Implementation Document
43
Q

According to the BEES model, life cycle analysis (LCA) is characterized by

A

According to the BEES model, life cycle analysis (LCA) is characterized by

Questions regarding the materials and impacts related to the six stages of the product life cycle, estimates of the cumulative environmental impacts resulting from all stages of a product life cycle over a 50- year period, and support for selection of products with the lowest total environmental impact

44
Q

Experienced owners may require project teams to utilize integrated project delivery based upon

A

Experienced owners may require project teams to utilize integrated project delivery based upon

  • Previous negative experience with adversarial project team relationships
  • Desire for reduction in project claims and disputes
  • Desire to utilize collaboratively-produced BIM as a facilities management asset
  • Expectation of benefit from innovation stemming from collaborative effort
45
Q

What are the 4 project teams?

A

What are the 4 project teams?

  • Owner
  • Design
  • Contractor
  • Supplier
46
Q

Describe the role of the Owner.

A

Describe the role of the Owner.

Establishes the design requirements, budget, and time constraints for the project. As the ultimate purchaser of installed products, the owner may have significant input on equipment and finish selections and may require information on product operation, maintenance, and warranties.

  • Assumes risk
  • Provides funding
  • Controls and manages design and construction process
  • Approves design/construction
47
Q

What is accomplished during the Project Conception Phase?

A

What is accomplished during the Project Conception Phase?

  • Owner’s needs and requirements are identified
  • Preliminary studies are performed
  • Site is selected
  • Preliminary budget and schedule are established
48
Q

List the 6 Project Delivery Methods.

A

List the 6 Project Delivery Methods.

  • Design-bid-build
  • Design-negotiate-build
  • Design-build
  • Construction management
  • Owner-build
  • Integrated project delivery
49
Q

Describe what happens during the Procurement Phase.

A

Describe what happens during the Procurement Phase.

Bidding/Negotiating/Purchasing (Procurement). Stage in the facility life cycle that allows the prospective contractor to examine bidding documents, visit the site, request clarifications and interpretations, propose substitutions, and finally, prepare a bid or price for executing the work. Acceptance of the contractor’s bid or negotiated sum and other conditions will result in award of contract and commencement of work.

50
Q

Describe what occurs during the Schematic Design Phase.

A

Describe what occurs during the Schematic Design Phase.

Site plan and area relationships may be defined, the general size, shape, and massing of building elements are determined, elevations and exterior finishes established, and conceptual design criteria for structural, mechanical, and electrical systems identified. Written documents usually consist of preliminary project descriptions and preliminary cost projections.

  • Schematic drawings
  • Preliminary project description
  • Preliminary estimates
  • Preliminary schedules
51
Q

Describe the Design Development phase.

A

Describe the Design Development phase.

Design development documents fix and describe the size and character of the entire project, including architectural, structural, mechanical, and electrical systems. Documentation includes more precise and specific drawings, physical or electronic models, and outline specifications.

  • technical info
  • outline specifications
  • updated estimates
  • updated schedules
52
Q

UniFormat

A

UniFormat

A uniform classification system for organizing preliminary construction information into a standard order or sequence on the basis of elements and systems. Derived from OmniClass Table 21: Elements.

1 A Substructure

2 A10 Foundations

3 A1010 Standard Foundations

4 A1010.10 Wall Foundations

5 A1010.10CF Continuous Foundations

53
Q

page format (3 objectives)

A

page format (3 objectives)

Standardized way of presenting information on the page.

Three objectives:

  • Present text clearly for easy reading
  • Provide acceptable standard
  • Provide flexible format compatible with most software
54
Q

Characteristics of specifications

A

Characteristics of specifications

• Defines qualitative requirements for

  • Product, materials, equipment
  • Physical properties of products
  • Performance requirements
  • Standards of workmanship

• Describes administrative procedures

55
Q

Comprehensive services

A

Comprehensive services

The architect’s basic services expanded to include:

  • Any additional Services
  • Programming
  • Land use studies
  • Models
  • Renderings
  • Presentations to DRC
56
Q

Project manual

A

Project manual

The manual prepared by the architect for the project

  • Technical Specifications
  • Bidding instructions and forms
  • General conditions / supplementary conditions
57
Q

Construction Docs must show sufficient detail to ensure the design adheres to code

A

Construction Docs must show sufficient detail to ensure the design adheres to code

  • Standard plans/elevations/sections/details
  • Site plan that shows location and finished grades
  • Drawings must show all portions of the means of egress, number of occupants on each floor and in all rooms/spaces
  • Exterior wall envelope must be described
  • Fire protection shop drawings may be required
  • Structural calculations may be required

Potentially:

  • info regarding all designers involved
  • legal description of property
  • square footage
  • building type + occupancy type
  • occ load calc
  • valuation of new construction
58
Q

information in specs vs drawings

A

information in specs vs drawings

specifications:

  • quality of materials
  • workmanship
  • execution of work
  • standards

drawings:

  • general configuration
  • size
  • shape
  • dimensions
59
Q

Schematic Drawings

A

Schematic Drawings

The extent of schematic design drawings depends on the complexity of the project and terms of the owner-A/E agreement. Schematic design drawings give a more organized form to the approved design concept and begin to describe the following about the project design:

  • Aesthetics
  • Size
  • Shape
  • Volume
  • Special relationships
  • Functional characteristics
  • Code and life-safety requirements
  • Materials
  • Major building systems

Drawings are not technical in nature and may include any of the following: site plan, floor plans, elevations, building sections, perspective and renderings, digital modeling (building information modeling), and scaled models.

60
Q

Estimate of Probable Construction Costs - Schematic Design

A

Estimate of Probable Construction Costs - Schematic Design

Uses the unit of measure technique for the estimate of probable construction costs which are consistent with other schematic design documents. Because the design is broadly defined, the estimate will be similarly broad with a substantial contingency category to account for unknown factors.

61
Q

Estimate of Probable Construction Costs - Design Development

A

Estimate of Probable Construction Costs - Design Development

Design development activities include selecting products, systems, and equipment, which require more detailed cost information than the previous stages. The assemblies/systems or unit price method may be used for estimating cost.

62
Q

Estimating Techniques

A

Estimating Techniques

Estimating methods used by the A/E during design include:

  • Order of magnitude
  • Unit-of-measure
  • Assemblies or systems
  • Unit price
63
Q

Life Cycle Costs

A

Life cycle costs are the estimated expenses for a project, or a specific material, equipment, or system, including:

  • Design
  • Construction
  • Operation
  • Maintenance
  • Resale, demolition, or salvage

Life cycle costs are based on the total costs of ownership rather than just the initial cost.

64
Q

Value Analysis Process

A

Value Analysis Process

Properly implemented, value analysis is composed of a series of phases, including the following phases:

  • Data gathering
  • Investigation
  • Analytical/development
  • Reporting
  • Implementation
  • Evaluation
65
Q

Data-Gathering Phase

A

Data-Gathering Phase

First phase of the value analysis process that compiles valuable information regarding the project including:

Project program to understand the owner’s goals and requirements

  • Code analysis
  • Geothermal information
  • Energy analysis
  • Design documents
  • Construction documents
66
Q

Analytical/Development Phase

A

Analytical/Development Phase

Short-listed concepts are evaluated in detail including:

  • Cost analysis
  • Impact on other work
  • Schedule impacts
  • System performance
  • Plan of implementation
  • Recommendations
67
Q

Assessing Product Sustainability

A

Assessing Product Sustainability

Determining whether a product or facility is sustainable, requires a life cycle assessment by a qualified project participant. According to the BEES model, the life cycle of a product is a 50 year period, the stages of which are as follows:

  • Raw materials acquisition
  • Product manufacturer
  • Transportation
  • Installation
  • Operation
  • Maintenance
68
Q

Sustainability Life Cycle Analysis

A

Sustainability Life Cycle Analysis

Under the BEES model evaluates six impacts a product make on the environment during each of the aforementioned stages including:

  • Global warming potential
  • Acidification
  • Nitrification potential
  • Natural resource depletion
  • Solid waste produced
  • Indoor air-quality
69
Q

Product Selection

A

Product selection is required to:

  • Establish performance requirements for the products, assemblies, equipment, as well as the facility itself
  • Identify types of products with attributes that comply with the performance requirements that are established for the project
  • Obtain product information from product representatives
  • Select specific products based on their history of performance in like applications, their compatibility with other selected products, and their life cycle value
  • Consider alternatives, present product selections to the owner
  • Document selections
70
Q

Types of Products

A

Types of Products

The term “product” can be used to identify the following:

  • Manufactured units
  • Materials
  • Assemblies/fabrications
  • Equipment
71
Q

Evaluation and Selection Process

A

Evaluation and Selection Process

The process should be disciplined and thorough, and should conclude with products that are suitable for the project design and its location. The process includes:

  • Initial product identification
  • Establishing project criteria
  • Determining applicable criteria for evaluation
  • Attribute categories for evaluation
72
Q

Attribute Categories for Evaluation

A

Attribute Categories for Evaluation

Attribute categories include:

  • General considerations
  • Physical properties
  • Performance
  • Sustainability
  • Safety and protection
  • Manufacturers
  • Installers
  • Cost
  • Maintenance
73
Q

What are Project Stages?

A

What are Project Stages?

o Conceptual Design

o Schematic Design

o Design Development

74
Q

What activities are involved in Project Conception stage?

A

What activities are involved in Project Conception stage?

  • Feasibility Study (O)
  • Programming (O)
  • Site Analysis (A/E)
  • Site Selection (O)
75
Q

What documents are involved in Project Conception stage?

A

What documents are involved in Project Conception stage?

  • Program (O)
  • Budget Schedule (O)
  • Analysis Reports (A/E)
  • Recommendations (A/E)
76
Q

What documents are involved in Design stage ?

A

What documents are involved in Design stage?

  • Schematic Design
    • Survey geotech data (O)
    • Schematic drawings (A/E)
    • Conceptual drawings (A/E)
    • Preliminary Project Description (PPD) (A/E)
    • Cost Projection (A/E)
  • Design Development
    • Developed drawings (A/E)
    • Engineering design criteria (A/E)
    • Equipment layouts (A/E)
    • Outline specs (A/E)
    • Revised cost projection (A/E)
77
Q

Facility Life Cycle

A

Know the individual components of this chart and components of each phase. The PDPG is broken down into chapters following this process.

Project Conception

  • Owner identifies need for a facility
  • Identifies a site
  • Completes planning activities to verify feasibility
  • Develops a budget and secures financial resources
  • Develops a facility space program
  • Selects project delivery method

Design

  • Schematic Design - Site plan and area relationships may be defined, the general size, shape, and massing of building elements are determined, elevations and exterior finishes established, and conceptual design criteria for structural, mechanical, and electrical systems identified. Written documents usually consist of preliminary project descriptions and preliminary cost projections.
  • Design Development - The design development phase follows the owner’s approval of the schematic design and any necessary program or budget adjustments. The emphasis shifts from overall relationships and functions to more technical issues of constructability and integration of systems and components. Aesthetic concerns move from massing and arrangement to materials, surfaces, and details. Design development phase documents fix and describe the size and character of the entire project, including architectural, structural, mechanical, and electrical systems.

Construction Documents

The construction documents stage (referred to as the final design phase in engineering projects) is based on the owner-approved design development documents and any further adjustments in the scope of the project or the project budget. During this stage the A/E prepares documents that will be used to file for permits and approvals from AHJs and to obtain prices upon which a bid or a negotiated contract can be based.

  • Detailed Drawings
    • Plans, elevations, sections, details, schedules

  • Specifications
    • MasterFormat®
    • Bidding requirements or
 procurement documents
  • Revised cost projections

Procurement (Bidding/Negotiating/Purchasing)

Stage in the facility life cycle that allows the prospective contractor to examine bidding documents, visit the site, request clarifications and interpretations, propose substitutions, and finally, prepare a bid or price for executing the work. Acceptance of the contractor’s bid or negotiated sum and other conditions will result in award of contract and commencement of work.

  • Project cost is updated
  • Project is bid or negotiated
    • Bid process depends on project delivery method selected
  • Construction Contract is awarded

Construction

Stage in the facility life cycle where owner’s project is constructed. Involves cost estimating, procurement, coordination of construction activities, and the physical construction.

  • Mobilization & Pre-Construction Activity
  • Construction
    • Project is constructed according to:
      • Contract Documents
      • Regulatory requirements
  • Construction Contract Administration, by the Architect
  • Project Closeout

Facility Management

The longest stage in the facility life cycle when the facility is accepted and put into use by the owner for its intended purpose

  • Longest stage in facility life cycle
  • Commences with Substantial Completion
  • Facility placed in service
  • Facility Manager maintains and evaluates performance of project components
  • Operations and maintenance procedures