Keanu's Eye Yeah Eye Basic Review Flashcards
A201 covers what information?
General conditions of the contract for construction.
According to section 1.1.1 what are acceptable modifications to the contract issued after execution?
- A written amendment to the contract signed by both parties
- A change order
- A construction change directive
- A written order for a minor change in the Work issued by the architect.
What items do the contract documents not include?
Unless specifically enumerated in the Agreement, the Contract Documents do not include the advertisement or invitation to bid, Instructions to bidders, sample forms, other information furnished by the owner in anticipation of receiving bids or proposals, the contractor’s bid or proposal, or portions of addenda relating to bidding or proposal requirements.
(Updated for 2017)
The contract documents do not create a contractural relationship of any kind between what parties?
- The contractor and the architect or the architects consultants
- The owner and subcontractor or sub-subcontractor
- The owner and the architect or the architect’s consultants
- Between any persons or entities other than the owner and the contractor
What does the contract entitle the architect to under section 1.1.2
Performance and enforcement of obligations intended to facilitate the performance of the architects duties.
What does the term work mean under section 1.1.3?
The construction and services required by the contract documents whether completed or partially completed and includes all, labor, equipment, and services provided or to be provided by the contractor to fulfill the contractors obligations.
What is the project as outlined in section 1.1.4?
The project is the total construction of which the work performed under the contract documents may be the whole or a part and which may include work by the owner or separate contractors
What do the drawings show according to section 1.1.5?
Design, dimensions, and location of the work and generally include plans, elevations, sections, details, schedules, and diagrams.
What are the specifications according to section 1.1.6?
Written requirements for materials, equipment, systems, standards, and workmanship for the work and performance of related services.
What are the instruments of service outlined in section 1.1.7?
Representations in any medium of expression now know or later developed, of the tangible and intangible creative work performed by the architect and the architects consultants under their respective professional services agreements and may include without
Who is the initial decision maker?
The Initial Decision Maker is the person identified in the agreement to render initial decisions on Claims.
Are the contract documents considered complimentary?
Yes, what is required by one shall be as binding if it were required by all.
Is the contractor subcontractor, sub-subcontractor material or equipment supplier able to reproduce the instruments of service?
Yes, but solely and exclusively for the execution of the work. The instruments of service may not be used on other projects or for additions to this project outside the projects scope without written consent of the owner, architect, and architects consult
The term owner means the owner or?
The owner’s representative.
The owner has how many days after receipt of a written request for information necessary to enforce a mechanic’s lean on the property to provide this information?
15 days. The information shall include a correct statement of the record legal title to the property on which the project is located as well as the owner’s interest therein.
Prior to commencement of work the contractor may request in writing legal evidence that the owner has made financial arrangements necessary to fulfill the owner’s obligations under the contract. After commencement of work what circumstances must apply bef
1) The owner has failed to make payments to the contractor as the contract documents require.|2) A change in the work materially changes the contract sum.|3) The contractor identifies in writing a reasonable concern regarding the owner’s ability to make a
Under section 2.2.2 the owner must secure and pay for?
Necessary approvals, easements, assessments, and charges required for construction, use or occupancy of permanent structures, or for permanent change in existing facilities. The owner is not required to pay for permits and fees that are the responsibility
The owner must furnish what information as outlined in section 2.2.3?
Surveys describing physical characteristics, Legal limitations and utility locations for the site of the project, and a legal description of the site.
How many copies of the contract documents must the owner furnish to the contractor?
The owner must furnish one (1) copy to the contractor to make reproductions with.
Who is given the right to stop work and for what reasons?
The owner if the contractor fails to correct work that is not in conformance with the contract documents. A written order to stop work may be issued by the owner until the cause for the order has been eliminated.
The owner has the right to carry out the work if?
The contractor defaults or neglects to carry out the work in accordance with the contract documents and fails within 10 days of receiving a written notice to correct or remedy the issue.
The contractors obligations to perform the work in accordance with the contract documents are not relieved by?
The architect’s administration of the contract, tests, inspections, or approvals required or performed by persons or entities other than the contractor.
Execution of the contract by the contractor represents what?
That the contractor has visited the site, become generally familiar with the local conditions of which the work is to be performed, and correlated personal observations with the contract documents.
Before starting each portion of the work the contractor must?
Study and compare the contract documents relative to that portion of the work as well as information furnished by the owner, Shall take field measurements of of existing conditions, and observe any conditions at the site affecting the work to be completed
What obligation does the contractor have if he finds errors, omission, or inconsistencies in the contract documents?
These items must be submitted as a request for information to the architect in such form as the architect may require.
Is the contractor required to ascertain if the contract documents are in conformance with applicable laws statutes, ordinances, codes, rules, regulations, or lawful orders of public authorities?
No, but the contractor must notify the architect in a request for information if he becomes aware of any nonconformity.
If the contractor carries out his due diligence as set forth in sections 3.2.2 and 3.2.3 is he liable to the owner or architect for damages resulting from errors, inconsistencies, or omissions in the contract documents, differences between field measureme
No, if the contractor believes that additional cost or time has been involved because of clarifications or instructions from the architect the contractor may make claims as provided in article 15.
What does the contractor have sole control and responsibility for?
Construction means, methods, techniques, sequences, and procedures, and for coordinating all portions of work under the contract. If the contract documents give specific instructions over the items above then the contractor must evaluate the instructions
Is the contractor responsible for the acts of others performing portions of the work on the project?
The contractor is responsible for the acts and omissions of the contractors and subcontractors employees and agents as well as all other persons performing portions of the work performing portions of the work on behalf of the contractor or any of its subc
Who is responsible for inspections of portions of the work already performed to determine if they are in proper condition to receive subsequent work?
The contractor.
Under section 3.4 Labor and Materials what is the contractor responsible for?
The contractor shall provide and pay for labor, materials, equipment, tools, construction equipment and machinery, water, heat, utilities, transportation, and other facilities and services necessary for the proper execution and completion of the work whet
Is the contractor able to make substitutions?
Only with the consent of the owner after evaluation by the architect and in accordance with a construction change directive or change order.
Who is in charge of enforcing discipline and order among the persons performing the work?
The contractor. The employment of unfit persons or persons not properly skilled at the tasks assigned to them shall not be permitted by the contractor.