Contract Dates Flashcards

1
Q

Contractor to give Owner notice of cancellation or expiration of required insurance.

A

3 days

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
2
Q

Owner to give Contractor notice of cancellation or expiration of required insurance.

A

3 days

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
3
Q

Successful Bidder to deliver required bonds to Owner, after execution of Contract.

A

3 days

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
4
Q

Architect to issue addenda, before bid date.

A

4 days

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
5
Q

Contractor/Architect’s notice to Owner before disclosing confidential information.

A

7 days

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
6
Q

Architect to respond to Application for Payment.

A

7 days

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
7
Q

Contractor to pay subcontractor, after receiving payment from Owner.

A

7 days

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
8
Q

Contractor to provide proof of payment of subcontractors, at Owner’s request.

A

7 days

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
9
Q

Owner to pay Contractor, after date established in Contract Documents, if any.

A

7 days

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
10
Q

Contractor’s notice to Owner and Architect of stopping Work, after failure to receive payment.

A

7 days

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
11
Q

Contractor/Architect’s notice to Owner before terminating Contract for cause.

A

7 days

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
12
Q

Owner’s notice to Contractor before terminating for cause.

A

7 days

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
13
Q

Bidder’s deadline to submit RFIs, before bid date.

A

7 days

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
14
Q

Owner to furnish reasonable evidence of financial arrangements to Bidders, upon request.

A

7 days

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
15
Q

Architect to request lien rights from Owner, at Consultant’s request.

A

7 days

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
16
Q

Contractor to send Application for Payment to Architect, prior to scheduled progress payment date

A

10 days

17
Q

Bidder’s deadline to return Bid Documents to issuing office for refund of deposit, after bid date.

A

10 days

18
Q

Bidder’s deadline to propose substitutions, before bid date.

A

10 days

19
Q

Owner to furnish reasonable evidence of financial arrangements to Contractor, at Contractor’s request.

A

14 days

20
Q

Contractor to report concealed or unknown conditions, after discovery.

A

14 days

21
Q

Architect to report objections, whether by Architect or Owner, to proposed superintendent or subcontractors, or request additional time to consider.

A

14 days

22
Q

Owner to evaluate, give notice of, or enforce mechanic’s lien rights.

A

15 days

23
Q

Owner to furnish information necessary for Architect to evaluate, give notice of, or enforce lien rights, upon request.

A

15 days

24
Q

Injured party to give notice of injury or damage to other party, after discovery.

A

21 days

25
Q

Of stopped Work, at no fault of the Contractor, before Contractor may terminate the Contract.

A

30 days

26
Q

Days of stopped Work, due to Owner non conformance, before Contractor may terminate the Contract.

A

60 days

27
Q

Days after Substantial Completion, Construction Phase services to be compensated as Additional Services.

A

60 days

28
Q

Cumulative days of suspended Work before Architect can terminate.

A

90 days