Mock Interview (DeLever) - Case Study Flashcards

1
Q

Explain to me what had caused the failures?

A

There was lack on connections to the apex, extensive corrosion to the steel stole plate and what appeared to be numerous repairs to all the portal frame columns at the base. Mostly likely due to timber decay, as the glulam beams were partially exposed externally.

  • two decades worth of on-going repairs
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
2
Q

Was it purely the connections which was the cause of the defect?

A

The problem was the portal frame was partially exposed externally. The soleplate was also found to be slightly lower than ground level.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
3
Q

How old was the structure?

A

1970’s

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
4
Q

On the ridge line was it bowing slightly?

A

Yes.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
5
Q

Thinking about your options for construction, you considered modular; have you used modular construction before?

A

No.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
6
Q

Looking at modular construction, what do you think were the real key benefits to that option?

A
  • Majority of the manufacture was done off-site reducing the on-site construction programme and minimising any potential health and safety issues.
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
7
Q

Was the new building that exact same footprint of the existing?

A

Within the existing footprint but a smaller building.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
8
Q

Did the school need the hall?

A

The hall was privately funded and was being use at one point as a nursery building. However, circumstance’s changed and the building was used as teaching space for the early years children

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
9
Q

You have explained your role, what parts of the design were you responsible for?

A

I design the floorplan, external play area including the canopy and footpaths.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
10
Q

How did you connect the extension to the existing building?

A

I installed a vertical timber plate to the existing buildings and slot with the timber frame walls to allow for movement.

It was a connection that allowed for settlement and extension between the masonry and timber frame buildings.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
11
Q

You discounted the modular building because the lane was narrow and large trees. Could you have had the modular building delivered in smaller sections to site?

A

Yes the sections could have been smaller, however there was still the issue of the mature trees to the boundary. You would still need to close the road for a crane. However, there were overhead power cables which were also a concern.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
12
Q

How did you get the timber frame panels in?

A

Timber frame panels were delivery on a low-load vehicle. They were delivered in the same manner as roof trusses.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
13
Q

Did you need a crane on-site for the installation of the panels; what about the roof?

A

The panels came in sections of 1200 x 2600mm and were lifted in to place by two operatives. Small modules.

The roof trusses were lifted into place by a tele-handler.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
14
Q

The timber frame itself, when that was procured, were there any specific payment terms; did you have to pay for it up-front?

A

No.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
15
Q

How did you cost the three options?

A
  • The repairs were costed on time and materials
  • The modular was costed on previous rates from my colleagues accounting for location and inflation.
  • The timber frame was costs from the previous years rates accounting for location and inflation.
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
16
Q

What was the cost of the three options?

A
  • £100,000 for a full repair and refurbishment
  • Modular classroom was around £125,000
  • The new extension was around £250,000
17
Q

How did you provide this advice to the client?

A

I provided my advice to the client within a report with an options appraisal.

18
Q

Take me through the tender process for the timber frame?

A

I used a performance specification for the timber frame ensuring compliance with all aspects of the building regulations. I then procured the scheme on the NEC3 Short Contract.

19
Q

Why did you advise the client to use the NEC3 Contract?

A

I used this contract because it is standardised within our department primarily for consistency with regards to the terminology.

The JCT Minor Works contract would have also been a suitable option due to the size and nature of this scheme.

20
Q

You have a strange figure in for liquidate damages; how did you calculate that?

A

We have a system which we use to calculate liquidated damages to ensure consistency across our department.

It is not something that I do personally. I am aware there is a formula you can use.

21
Q

Could you have had the services contained within the panels off-site?

A

Its not something I considered.

I am aware that it is something that would be possible but not something which would have saved a significant amount of time for this scheme. Perhaps it would have been a better option for a larger scheme and something I will consider for next time.