Construction Technology (L3) Leconfield Primary School Flashcards

1
Q

What did your outline designs include?

A
  • I included for a timber-frame classroom extension including of teaching space, cloakroom and storage.
  • Externally, a wet pour play area with a canopy
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
2
Q

How did you produce your outline design?

A

I initially used AutoCAD to produce a floor plan showing the layout and space requirements. I then imported the floorplan into revit to provide a 3D model to make it easier for the school to interpret the design.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
3
Q

How did you produce your budget estimate and did you make any adjustments?

A

I used an elemental rate from the previous year on a similar project adjusting for labour and material price increases and time and quality.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
4
Q

What was the reason for the closure of the school hall?

A

Major structural defects to the glulam portal frame due to a lack of force resisting connections.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
5
Q

What impact did the clients request have on your construction choices?

A

I had 3 construction choices:

  • Traditional build: This option required a longer on-site programme and could not be completed before the start of the new term.
  • Modular classroom: This option could be completed before the start of the new school term, but I had to omit this option due to restricted site access
  • Timber-frame: This option was a shorter on-site programme and could be completed to the client’s request. I recommended this option as a form of construction.
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
6
Q

Why did you specify timber-frame?

A
  • I could achieve the requested timescales made by the client
  • I considered timber-frame as are more sustainable form of construction with excellent thermal performance, minimal waste, and flexibility on design.
  • I considered traditional cavity walls, however, the clients requested timescales could not be achieved. The benefits of the timber frame also outweighed the benefits of the traditional construction
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
7
Q

What were the main benefits of timber-frame?

A
  • Shorter on-site programme
  • Flexible design
  • Excellent thermal properties whilst remaining a narrow wall construction
  • Lightweight, not requiring extensive foundations
  • Excellent tolerances can be achieved due to being manufactured in a controlled environment
  • Minimises potential health and safety issues due to manufacturing off-site
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
8
Q

What was the build-up of the wall construction?

A
  • 15mm plasterboard and skim
  • 25mm vertical batten for service void
  • Vapour Control Layer
  • 140mm timber frame structure at 600mm centres
  • 120mm PIR insulation between studs
  • 9mm OSB3 board
  • Breathable membrane
  • 38 x 47mm vertically fixed timber batten
  • 25 x 50mm horizontally fixed counter batten
  • 21mm Thermowood timber cladding
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
9
Q

What were the benefits of the timber walls being narrow?

A
  • Lightweight
  • Did not require extensive foundations
  • Maximised internal floorspace
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
10
Q

What was the u-value and why was this important?

A
  • 0.17 W/m2K
  • Excellent thermal performance and air tightness resulting in reduced energy costs for the school
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
11
Q

What legislation did you refer to for the u-value?

A

Approved Document L Volume 2

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
12
Q

Were there any implications on time and quality?

A
  • Yes, the client had requested that the works were completed before the start of the new school term. For that reason, I specified timber-frame which could achieve the timescales.
  • I used 90% price 10% quality on the programme and ESP including method statement.
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
13
Q

What was the floor build-up?

A
  • Reinforced concrete raft foundation with 150mm upstands
  • 1200- gauge damp-proof membrane lapped with DPC and taped joints
  • 75mm Kingspan Kooltherm K103 PIR Insulation
  • Separation layer
  • 75mm quick drying sand/cement screed
  • 140mm timber soleplate is mechanically fixed through the DPC and into the 150mm concrete upstand. Holes created through DPC are beaded with silicone to prevent moisture transmission into the timber
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
14
Q

Was the raft foundation reinforced; what was the reinforcement detail?

A
  • To prevent cracking and provide flexibility
  • Strength the up-stand for the timber-frame wall
  • Consulted with a structural engineer for the design
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
15
Q

What were the existing ground conditions?

A
  • There were no issues with the existing ground
  • Trial holes had been dug as part of my initial investigation
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
16
Q

Did you design the foundations?

A

I consulted with a structural engineer to ensure the raft foundation was designed accordingly forming a 150mm up- stand for timber-frame walls to be mechanically mounted.

17
Q

What was the connection detail for the raft foundation up-stand and the timber walls?

A

A 140 x 38mm timber soleplate was mechanically fixed into the 150mm concrete up-stand using threaded rods fixed with a resin compound. Any penetration to the DPC was sealed with a sealant.

18
Q

Why did the raft foundation minimise time and cost?

A

Less excavation was required resulting in less earth disposal.

19
Q

How did the timber-frame building connect to the existing building; did you account for thermal movement and settlement?

A

A DPC was laid vertically beneath a timber soleplate which was fixed directly into the existing walls using mechanical fixings. A slot was created to allow the timber-frame to move independently from the existing building.

20
Q

What was the outcome of the completed works?

A

The scheme was completed within budget, to programme and a completion certificate was issued by Building Control for compliance.