Contract Administration (L1) Flashcards
NEC3 - How many clauses are there and what are they?
There are 9 core clauses:
- General
- The Contractor’s main responsibilities
- Time
- Testing and Defects
- Payment
- Compensation Events
- Title
- Risks and Insurance
- Termination
NEC3 - What are the different options and where would you use them?
- Option A: Priced Contract with Activity Schedule
- Option B: Priced Contract with Bill of Quantities
- Option C: Target Contract with Activity Schedule
- Option D: Target Contract with Bill of Quantities
- Option E: Cost Reimbursement Contract
- Option F: Management Contract
What is an early warning?
An early warning can be given by both the Contractor and Project Manager as soon as any matter becomes apparent which could:
-Increase the total of the prices
- Delay completion
- Delay meeting a key date
- Impair the performance of the works in use
What are the NEC3 Certificates?
- Completion Certificate (Completed works)
- Defects Certificate (No outstanding defects)
- Option X5: Sectional Completion (Secondary Option Clauses)
What are your thoughts on withholding retention?
- Withholding retention from a contractor puts the Project Manager in an advantageous position to request the contractor to correct any discovered defects during the defect period.
- I decided to withhold retention for 52 weeks for this scheme due to the new heating system (Check the systems operates correctly during winter and summer months), heating and cooling.
Retention - what are they trying to do nationally and why?
- A new bill is looking to abolish retention completely
- It is to avoid cashflow difficulties across whole supply chains
When would you not withhold retention?
- Depending on the nature and complexity of the scheme
- The value
- The level of risk
Talk me through the process of dealing with an early warning?
- The Project Manager enters the early warning matters in the Risk Register
- Either the Contractor or Project Manager can instruct the other to attend a risk reduction meeting
- The Contractor must give max 8 weeks’ notice of becoming aware of the event otherwise deemed to be no change in price (cost)
- If employer agrees to an Early Warning, they request the contractor to provide a quote within 1 week. (If no quote received the employer makes an assessment.)
- The Contractor provides a quote within one week and the employer must reply within 2-weeks either accepting or rejecting the quotation
- If rejected by employer, the contractor can resubmit a revised quote within 2 weeks
- If employer does not agree to the revised quote or receives no reply from the contractor, the employer will assess the compensation event and notify the contractor.
What is a compensation event and can you give me an example of where you used one on this project?
- A compensation event is when the Project Manager gives an instruction changing the works information. They are events which are usually not the fault of the contractor and change the cost of the work, or the time needed to complete it.
- On this project, I changed the product finish of the school playground from a standard pattern and colour finish to a rainbow pattern with multiple colour finishes. The was a cost increase for this change.
What are the procedures for quotations for Compensation Events?
- Notifying: The Contractor notifies the employer, if not notified within 8-weeks of the event occurring he is not entitled to charge for it. If the employer agrees with the Compensation Event, he instructs the Contractor to submit a quote
- Quoting: The Contractor submits a quote within 2-weeks
- Assessing: Price list can be used, other CE’s
Term Service Contract; what is it?
The NEC Term Service Contract is designed to engage a contractor for a set period of time, to manage and provide a service—this might include construction works, but can be used for the provision of other services.
What is the difference between partial and sectional completion?
Sectional Completion:
- Agreed up front and provided for in the contract
- Different completion dates for different sections of works
- Common on larger projects, allows clients to take
possession of the completed works whilst other areas are being worked on - Multiple completion dates, multiple defects dates.
- Very intensive for the Project Manager under the NEC3
Partial Completion:
- Requires are and agreement during the progress of the works. Contractor can refuse if he feels it will interrupt the progress of the works.
It an agreement to accept completion for part of the works
What is the procedure for an employer to assess a compensation event?
2 methods
- CEs with quantities shown in the price list are based on appropriate rates and multiplied accordingly.
- Other works not in price list. Assessed by
Labour (main contractor)
Plant
Materials
Sub contractors
Main contractors overheads and profit
Can you explain loss and expense?
Loss and expense is the term often used (most notably, in the JCT contracts) to describe the additional costs incurred by a contractor as a result of disturbance to the regular progress of the works caused by matters either within the employer’s control or by breaches of contract by the employer.
What is a pay less notice and when should it be served?
A pay less notice is the opportunity for a paying party to change their mind on what has already been agreed on payment, altering the payment due to the payee near to the end of the payment cycle.
If you are the payer and you want to reduce the sum certified already in the same payment period, you should serve a pay less notice.