Manage Scope - Prep Questions Flashcards

Exam preparation questions

1
Q

During scope validation you notice that a critical deliverable does not meet its requirement. The customer did not notice it and is about to validate the deliverable. You are worried because the correction can compromise the project schedule. What should you do NEXT?

A. Complete scope validation without correcting the defect. Correct the defect later at a more appropriate time.
B. Correct the deliverable and review the project schedule
C. Discuss the issue with the customer
D. Issue a change request

A

C. Discuss the issue with the customer

The deliverable should be corrected because it does not meet its specification.
However, correcting the deliverable would lead to a schedule delay. There is therefore a conflict between schedule and scope objectives. The project manager should inform the customer and discuss options. Completing scope validation without correcting the defect (answer A) would not be an ethical option. Correcting the deliverable (answer B) would lead to a schedule delay. Issuing a change request (answer D) would not be the first step.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
2
Q

To collect project requirements, the project manager has sent questionnaires to a number of stakeholders. Once the ideas have been collected and processed, they will be sent back to stakeholders to obtain more feedback. The process will be repeated until a meaningful consensus is obtained. The technique used by the project manager is known as:

A. Focus group
B. Nominal group technique
C. Delphi
D. Iteration technique

A

C. Delphi

Delphi reaches consensus by repeatedly consulting experts, usually through an anonymous process.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
3
Q

The project manager has completed the scope statement and will now prepare the project work breakdown structure (WBS). Which of the following best describes a WBS?

A. A graphical tree-like hierarchical decomposition of the project’s product to facilitate a common understanding and support tracking and control.
B. Deliverable-oriented tree-like representation of all the work required to achieve the project objectives
C. Diagram that identifies the deliverables, work packages, dependencies and their start and finish dates for each activity
D. Hierarchical diagram that displays the relationship between work packages and resources

A

B.

A WBS is a deliverable-oriented tree-like representation of all the work required to achieve the project objectives

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
4
Q

During the design phase of a solar energy project, a deliverable was satisfactorily completed without one of its planned work packages. How should the project manager proceed?

A. Ensure that the missing work package is completed
B. Update the project WBS
C. Submit a change request for approval
D. Update the requirements documentation

A

B. Update the project WBS

You need to update the work breakdown structure to ensure that it records the work that was actually required to accomplish the project objectives (answer B).
The deliverable was completed so there is no need to complete the missing work package (answer A), submit a change request (answer C) or update the requirements documentation (answer D).

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
5
Q

You have been hired to manage a strategic project. In the middle of the third iteration, the team is performing a backlog refinement session. Which of the following activities may be performed as part
of the session? (Choose three.)

A. Ensure that the backlog is ready for the upcoming iterations
B. Reprioritize existing items
C. Add the tasks required to complete the following sprint
D. Ensure that the product backlog only includes items aligned to the sprint goal
E. Disaggregate epics into user stories
F. Ensure that every product backlog item is clearly described

A

A. Ensure that the backlog is ready for the upcoming iterations
B. Reprioritize existing items
E. Disaggregate epics into user stories

Product backlog refinement ensures that the backlog is ready for the upcoming iterations (answer A) by removing, adding, disaggregating (answer E), estimating or updating (answer B) items. Backlog refinement does not plan the work required to complete the sprint (answers C and D). Items that will not be developed within the following iterations may not be clearly described (answer

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
6
Q

You were assigned to an agile project that is developing navigational software. Team members are concerned because the time spent testing product backlog items has increased significantly
throughout the project. Which of the following practice would you recommend?

A. Improve product backlog refinement
B. Increase the sprint duration to ensure that there is sufficient time for testing
C. Adopt sprints specifically dedicated to testing and stabilizing the product
D. Ensure that the product backlog items acceptance criteria are fully defined upfront

A

A. Improve product backlog refinement

Product backlog refinement may help to disaggregate large, broadly defined requirements into small, clearly defined user stories.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
7
Q

You are leading a project to build a gas platform that is well over budget. The change control board has approved a number of significant scope changes. Which of the following statements about the project performance is correct?

A. Scope changes are inevitable because the scope is progressively detailed
B. An approved scope change does not justify a cost overrun
C. The scope baseline cannot be changed once it is established
D. Scope changes must be approved by the change control board

A

B. An approved scope change does not justify a cost overrun

An approved scope change, with an impact on the project budget, should have changed the cost baseline. An approved scope change does not, therefore, justify a cost overrun (answer B). The remaining statements are incorrect.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
8
Q

You were assigned to an agile project that is developing a process automation system. After completing five sprints, the team made a significant effort to refine the product backlog. Which of the
following is the most likely outcome of the product backlog refinement?

A. The number of impediments will increase
B. The number of product backlog items will increase
C. The number of defects will increase
D. The number of items completed per sprint will increase

A

B. The number of product backlog items will increase

Product backlog refinement may help to disaggregate large, broadly defined requirements into small, clearly defined user stories.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
9
Q

You are a in a global organization trying to adopt agile. Team members, being new to the agile, are still unsure about their responsibilities. Who will be responsible for preparing and refining the product backlog?

A. The product owner and the team
B. The scrum master
C. The project team
D. The product owner with input from the project team

A

D. The product owner with input from the project team

The product owner is ultimately responsible for the product backlog but should work in close collaboration with the project team.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
10
Q

The team is using post-its to record brief statements of the product features written from the user perspective. What is the team documenting?

A. User story
B. User epics
C. Mind maps
D. Product backlog

A

A. User story

A user story is a concise and intuitive description of a feature, often written from the user perspective.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
11
Q

An agile team has a total of Six members, three members who work full time and three members who work part time. At the beginning of the second sprint, team members are defining the tasks required
to complete a user story. Which of the following statements regarding user stories are correct? (Choose three.)

A. They should add value
B. They are defined during sprint planning
C. They are recorded in the product backlog
D. They are assigned to individual team members
E. They are the actions required to complete product backlog items
F. They are a concise and intuitive description of a feature

A

A. They should add value
C. They are recorded in the product backlog
F. They are a concise and intuitive description of a feature

A user story is a concise and intuitive description of a valuable feature (answers A and F) recorded in the product backlog (answer C). A task represents a small action required to create a product backlog item (answer E). User stories are not defined as part of sprint planning (answer B) and should not be assigned to individual team members (answer D).

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
12
Q

You are managing a project to build an office center. To collect requirements, you sent out a questionnaire to key stakeholders and requested anonymous answers. You expect to find a consensus by recirculating a summary of responses and requesting further comment. Which technique did you use?

A. Delphi
B. Brain writing
C. Brainstorming
D. Interviewing

A

A. Delphi

The Delphi technique reaches a consensus by repeatedly consulting experts, usually through an anonymous process.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
13
Q

The project manager should manage the project and the product scope. Which of the following statements regarding the product scope is correct?

A. Is progressively elaborated throughout the project
B. Defines the complete scope of work
C. Is defined in the project WBS
D. Defines the project business need

A

A. Is progressively elaborated throughout the project

The product scope can be progressively elaborated as more and better information becomes available. The project scope (not the product scope) is defined in the WBS. Therefore answers B and C are incorrect. The project business need is established as part of project initiation before planning the product scope. Therefore answer D is incorrect.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
14
Q

The project manager should manage the project and the product scope. Which of the following BEST describes project scope?

A. All of the agreed upon project deliverables
B. AI ofthe agreed upon product functionalities
C. Work required to complete the project objectives
D. Work required to complete the product

A

C. Work required to complete the project objectives

Project scope includes all the work required to achieve project objectives, including completing the project’s product.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
14
Q

A project has been authorized to develop a new mobile phone. The team is considering using brainstorming sessions to collect requirements. How can brainstorming support the requirements
collection process?

A. Collect new requirements and consolidate those requirements into a cohesive whole
B. Enable requirements-related discussions and prioritize requirements
C. Prioritize requirements and generate consensus
D. Develop a sense of team and enable an unrestrained collection of potential requirements

A

D. Develop a sense of team and enable an unrestrained collection of potential requirements

Brainstorming is an information gathering technique based on an
unconstrained and informal exchange of ideas.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
14
Q

The team is decomposing deliverables into work packages. What is the best advice you can offer?

A. Define work packages that can be clearly allocated to individuals, teams or organizational units
B. Decompose deliverables until the team can clearly identify logical relationships
C. Detail the WBS as much as possible to improve the accuracy of estimates
D. Decompose deliverables until the team can clearly identify product requirements

A

A. Define work packages that can be clearly allocated to individuals, teams or organizational units

Work packages should be clearly allocated to individuals, teams or
organizational units (answer A). Logical relationships are defined in the network diagram (answer B). Detailing the WBS Will not necessarily increase the accuracy of estimates (answer C). The WBS decomposes project work (answer D).

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
15
Q

A project stakeholder made an incorrect statement about the work breakdown structure. Which one was it?

A. It should record resource-related information
B. Work that is not represented in the WBS is beyond the scope of the project
C. It establishes the total scope of the project
D. It is deliverable-oriented

A

A. It should record resource-related information

The WBS does not record resource-related information. The remaining statements are correct.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
16
Q

The brainstorming exercise has generated a large number of requirements. Your now need to organize requirements into groups according to their similarities. Which technique would best
accomplish this?

A. Mind mapping
B. Focus group
C. Multicriteria decision analysis
D. Affinity diagram

A

D. Affinity diagram

The affinity diagram organizes existing ideas into groups according to their similarities.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
17
Q

You have been hired to manage a strategic project. In the middle of the third iteration, the team is performing a backlog refinement session. When should the backlog be refined?

A. When the scrum master decides that the session is required
B. As required by the product owner when more information emerges
C. Atthe end of each sprint
D. As required to ensure that every item is properly disaggregated and includes the required acceptance criteria.

A

B. As required by the product owner when more information emerges

The product owner owns the product backlog (answer A) and may refine it as the project evolves (answers B and C). The backlog session ensures that the product backlog is ready to deliver the following iterations (answer D).

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
18
Q

A WBS is a deliverable-oriented, treelike depiction of all the work required to accomplish the project objectives. Which of the following options is used to accelerate the WBS development?

A. Chart of accounts
B. Templates
C. Control accounts
D. WBS dictionary

A

B. Templates

WBS templates can accelerate WBS development

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
19
Q

You are taking over an urban development project from a project manager who is retiring. The scope management plan and scope statement are already complete. Which of the following should be done NEXT?

A. Develop the project WBS
B. Define schedule activities
C. Ensure that the scope statement reflects the stakeholders’ understanding of the project and product scope
D. Submit the scope statement for approval

A

C. Ensure that the scope statement reflects the stakeholders’ understanding of the project and product scope

You should ensure that the scope statement establishes a common
understanding of what is included and excluded from the project and product scope (answer C). The remaining options may be performed later.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
20
Q

A team member is struggling to distinguish scope validation from quality control. You should explain to him that:

A. Scope validation is performed by team members and control quality is usually performed by the customer
B. Quality control may inspect any project deliverable and scope validation can only inspect project management deliverables
C. Scope validation is usually performed before quality control
D. None of the above

A

D. None of the above

Scope validation Will usually involve the customer and quality control will usually involve team members (answer A). Scope validation is not exclusively used to validate project management deliverables (answer B). Scope validation will usually be performed after quality control (answer C).

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
21
Q

A project has been authorized to develop a new mobile phone. The customer is insisting on using focus groups to collect requirements. How can focus groups support the requirements collection
process?

A. Organize requirements into groups
B. Uncover requirements that the team might have overlooked or deepen the knowledge of previously identified requirements
C. Collect requirements based on an unrestrained exchange of ideas
D. Present a model to key stakeholders to obtain feedback

A

B. Uncover requirements that the team might have overlooked or deepen the knowledge of previously identified requirements

In a focus group, subject matter experts meet to express their expectations towards the product. Open discussions should help to uncover requirements that the team might have overlooked or to deepen the knowledge of previously identified requirements

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
22
Q

You are managing a project that will expand the IT infrastructure. The team is not certain how to verify, change and trace requirements. You should direct the team members to the:

A. Scope statement
B. Requirements management plan
C. Requirement documentation
D. Requirements traceability matrix

A

B. Requirements management plan

The requirements management plan is an element of the project management plan that sets the rules regarding how to analyze, prioritize, document, approve, develop, verify, change and trace requirements.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
23
Q

A team member needs information regarding estimates, assumptions, acceptance criteria, and resources required for a particular work package. You should direct the team member to the:

A. Work breakdown structure dictionary
B. Project management plan
C. Scope statement
D. Work breakdown structure

A

A. Work breakdown structure dictionary

The WBS dictionary stores additional information regarding each work package.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
24
Q

A footwear manufacturer authorized an agile project to design a new pair of sneakers. During a sprint review meeting, the product owner identified a low-priority requirement. How should the product
owner proceed?

A. Record an epic in the product backlog
B. Use the meeting to disaggregate the epic into small, clearly defined user stories
C. Organize an urgent refinement meeting to decompose the epic into user stories and record them in the product backlog
D. Ignore the requirement because it is not a priority

A

A. Record an epic in the product backlog

The product owner can record the epic in the product backlog and later disaggregate into user stories, if there is a realistic probability that they will be completed.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
25
Q

You are working with key business representatives to create a common understanding of the project’s boundaries. You are defining what is and what is not included in the product scope, as well as defining the verifiable items that must be produced to complete the project and the items explicitly excluded from the project scope. Which document are you preparing?

A. Product breakdown structure
B. Scope statement
C. Work breakdown structure dictionary
D. Work breakdown structure

A

B. Scope statement

The scope statement establishes a common understanding among project stakeholders regarding the project and product scope. A typical scope statement may provide a detailed description of the product requirements, project deliverables and acceptance criteria.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
26
Q

You are reviewing a key project deliverable with the customer to ensure that it meets acceptance criteria and obtain a formal sign-off of the deliverable. The customer, however, claims that the
deliverable does not address the business need. Which of the following can help to redefine the deliverable?

A. Collect requirements
B. Define scope
C. Validate scope
D. Control scope

A

A. Collect requirements

If the deliverable does not address the business need, it indicates that there might have been a gap or misunderstanding in the initial requirements gathering. Collecting requirements involves defining and documenting stakeholders’ needs to meet the project objectives. Revisiting this process can help to redefine the deliverable to ensure it aligns with the business needs.
Control scope process would follow as it involves monitoring the status of the project and product scope and managing changes to the scope baseline. It is about managing changes to the scope, not redefining the deliverables based on business needs.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
27
Q

You need to quickly define cross-functional requirements as well as ensure consistency across multiple areas. Which requirement collection technique should be used?

A. Facilitated workshops
B. Brainstorming
C. Mind Map
D. Delphi

A

A. Facilitated workshops

Facilitated workshops can bring together stakeholders from multiple areas to discuss ideas and generate consensus, allowing for a swift collection of information. The interactive nature of workshops enables consensus and issues resolution.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
28
Q

The team met with key stakeholders and subject matter experts and collected a large set of requirements. A junior project manager, however, is unsure of the purpose of collecting requirements. Which of the following statements regarding collecting requirements is correct?

A. The collect requirements process defines high-level requirements that are later decomposed and recorded in the project WBS
B. The requirements documentation should provide an understanding of stakeholders’ needs
C. The team should collect business, stakeholder, solution and resource requirements during the collect requirements process
D. All collected requirements Will be part of the scope baseline

A

B. The requirements documentation should provide an understanding of stakeholders’ needs

The requirements documentation should provide an understanding of stakeholders’ needs (answer B). Requirements are detailed as part of the collect requirements process (answer A). The collect requirements process does not collect resource requirements (answer C). Some requirements may not be included in the scope baseline (answer D).

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
29
Q

An agile team has systematically met the previous sprints’ goals. During a sprint review, one key stakeholder requested a critical new product feature to respond to recent market changes. How should the new requirement be handled?

A. The product owner should decide whether to include the feature in the product backlog
B. The product owner should decide whether to include the feature in the following sprint
C. The sprint should be extended to accommodate the critical feature
D. The team should record the new feature in the product backlog

A

A. The product owner should decide whether to include the feature in the product backlog

The product owner owns the product backlog.

30
Q

Your company is planning to expand its business into a new market. A new project was authorized to develop a new electronical device for consumers and the team will now need to collect product
requirements. Which of the following techniques would you recommend considering that the company does not have previous experience in similar products?

A. Brainstorming
B. Affinity diagram
C. Product breakdown structure
D. Prototypes

A

D. Prototypes

Prototypes enable the team to demonstrate a model or early version of a future product to collect feedback from stakeholders and adjust accordingly.

31
Q

An agile team has been working on a system integration for several iterations. The team is now focused on completing several user stories that will enable credit card payments. Who owns user
stories?

A. Team
B. Project manager
C. Users
D. Product owner

A

D. Product owner

The product owner owns the product backlog.

32
Q

You have been given the approved project charter and are now collecting requirements. Which of the following sets of activities is part of requirements collection?

A. Collecting resource requirements and documenting them in the requirements documentation
B. Preparing the requirements management plan and the requirements traceability matrix
C. Establishing an agreement on the final set of requirements
D. Decomposing high-level requirements into detailed level and prioritizing requirements

A

D. Decomposing high-level requirements into detailed level and prioritizing requirements

Decomposing high-level requirements into detailed level and prioritizing requirements are part of the collect requirements process (answer D). Resource requirements are estimated as part of the resource management effort (answer A). The requirements management plan is prepared as part of the plan scope
management process (answer B). An agreement on the final set of
requirements is only established in the define scope process (answer C).

33
Q

You have just been assigned as project manager of the company’s helpdesk implementation project. The customer has provided you a list of requirements to be included in the project scope. Which of
the following requirements is an invalid requirement?

A. The project should hire 30 helpdesk professionals
B. The project should procure a specific list of equipment
C. The project should implement a state-of-the-art software
D. The project should processes aligned with the company’s policies

A

C. The project should implement a state-of-the-art software

Requirements need to be specific, measurable, and clear to ensure that they can be effectively implemented and verified. The requirement to implement “state-of-the-art software” is too vague and subjective, making it an invalid requirement.

34
Q

Your company initiated a project to build an amusement park. After preparing the project scope statement, you are now creating the project WBS. Which of the following can be used as an input into
creating the WBS?

A. Project management plan
B. WBS templates
C. Scope baseline
D. All of the above

A

B. WBS templates

Organizational process assets, such as WBS templates, may be used as an input while creating the project WBS.

35
Q

During the development of a transportation drone, you realized that the team delivered features beyond the agreed scope of work. What should be done NEXT?

A. Adjust the change management plan to avoid scope creep
B. Investigate how the features were added to the product scope
C. Submit a change request for approval to ensure that the scope of work adequately reflects the drone’s features
D. Assess the work performed to develop these features

A

D. Assess the work performed to develop these features

You should first understand the issue (the team delivered features beyond the agreed scope of work) before you can address it. You may need to submit a change request (answer C) to address the issue but that should be done after you understood it. Adjusting the change management plan (answer A) and investigate how the features were added (answer B) can help to prevent further
scope creep but that should not be your first priority.

36
Q

You are currently conducting a product analysis in your logistics information system implementation project. Which of the following BEST describes the purpose of the product analysis technique?

A. Translating product requirements into deliverables
B. Defining the products that will be procured from an external vendor
C. Establishing the scope management approach
D. Breaking down project deliverables into work packages

A

A. Translating product requirements into deliverables

Product analysis translates product descriptions into specific and verifiable deliverables (answer A). The procurement statement of work defines the products that will be procured from an external vendor (answer B). The scope management plan establishes the scope management approach (answer C).
The decomposition technique breaks down project deliverables into work packages (answer D).

37
Q

With a production system automation project underway, a team member submitted a deliverable for approval that was not what you expected. What is the BEST thing to do?

A. Meet with the team member to explain your concern
B. Fix the deliverable to ensure that it meets requirements
C. Ask the team member to implement the necessary corrective action
D. Follow the scope validation process

A

D. Follow the scope validation process

The project manager should first inspect the deliverable, according to the agreed-upon approach, to determine if it meets requirements and acceptance criteria (answer D) instead of assuming that the deliverable was not completed according to acceptance criteria (answers B and C). Meeting with the team member to discuss the problem may not be enough to ensure that the deliverable meets acceptance criteria (answer A).

38
Q

You are asked to explain the purpose of a work breakdown structure (WBS). Which of the following statements explains it best?

A. A document that describes the products or services that will be procured within the project
B. A technique used to decompose high-level deliverables into detailed deliverables
C. A deliverable-oriented tree-like depiction of all the work required to accomplish the project objectives
D. A document that defines a common understanding among project stakeholders regarding product characteristics, deliverables, exclusions and acceptance criteria

A

C. A deliverable-oriented tree-like depiction of all the work required to accomplish the project objectives

A work breakdown structure is a deliverable-oriented, treelike depiction of all the work required to complete project deliverables (answer C). The procurement statement of work describes the products or services that will be procured within the project (answer A). The product analysis technique decomposes high-level deliverables into detailed deliverables (answer B). The scope statement defines a common regarding product characteristics,
deliverables, exclusions and acceptance criteria (answer D).

39
Q

You are managing a large agile project that is redefining the organization’s processes. The product owner is updating the product backlog by removing, adding, disaggregating and updating items. What activity is the product owner performing?

A. Sprint planning
B. Product backlog preparation
C. Backlog adjustment
D. Product backlog refinement

A

D. Product backlog refinement

Product backlog refinement, also known as product backlog grooming, refers to the process of regularly updating the backlog by removing, adding, disaggregating or updating items.

40
Q

You are working with the business representative to analyze and refine product requirements. You are, however, struggling to recall why those requirements were defined. Which of the following would
help you the MOST?

A. Context diagram
B. Requirement traceability matrix
C. Requirements documentation
D. Requirements log

A

B. Requirement traceability matrix

The requirements traceability matrix establishes a clear link between business requirements, stakeholder requirements and solution requirements (answer B). The context diagram (answer A), requirements documentation (answer C) and requirements log (answer D) could help to analyze and record requirements but
would not help to explain why they were defined.

41
Q

You want to ensure that the project deliverables meet acceptance criteria. All the following tools or techniques may be used to validate scope, EXCEPT:

A. Inspection
B. Prototypes
C. Walkthroughs
D. Reviews

A

B. Prototypes

A prototype is a technique used to collect requirements. All other options are used for scope validation.

42
Q

An agile team is conducting a refinement session in the middle of an iteration to ensure that three new epics are properly estimated and prioritized. Which of the following statements is correct?

A. Epics should be disaggregated into stories before they can be recorded in the product backlog
B. Epics can be found towards the bottom of the product backlog
C. The most important undeveloped product backlog items can be found at the bottom of the product backlog
D. Epics should be recorded in the sprint backlog

A

B. Epics can be found towards the bottom of the product backlog

Broadly defined requirements that can span multiple iterations, known as epics, are typically found towards the bottom of the product backlog (answer B). Epics should be recorded in the product backlog (answer A and D). The most important undeveloped product backlog items can be found at the top of the product backlog (answer C).

43
Q

The team is working with a number of stakeholders to establish a clear understanding of the project’s needs. They are defining what should and should not be included in the project scope, as well as
establishing a clear set of deliverables. Which of the following statements regarding the project scope statement is correct?

A. Is developed by the customer and used as an input during scope definition
B. Describes the buyers needs to potential suppliers
C. Is prepared with the input of relevant stakeholders and is used as an input during the development of the WBS
D. Establishes the contract scope

A

C. Is prepared with the input of relevant stakeholders and is used as an input during the development of the WBS

The scope statement is prepared by the project management team during scope definition and is used as an input during WBS development. A scope statement is not a statement of work (answer A), a procurement document (answer B) or a contract statement of work (answer D).

44
Q

The team established a common understanding regarding the project and product scope and is now preparing the WBS. All of the following are advantages of using a WBS, EXCEPT:

A. Establishes project objectives
B. Avoids scope creep
C. Increases team members’ buy-in
D. Improves internal and external communication

A

A. Establishes project objectives

The WBS represents the work required to accomplish project objectives. It does not establish those objectives. The remaining answers represent advantages of using a WBS.

45
Q

You are managing a project that will expand the IT infrastructure. A team member is unsure of how the project deliverables should be formally accepted. You should tell the team member to check the:

A. Scope statement
B. Scope management plan
C. Work package description in the WBS dictionary
D. Product backlog

A

B. Scope management plan

The scope management plan specifies the scope management procedures, tools, techniques, roles and responsibilities.

46
Q

You are managing a project to build an office center. The team will use the Delphi technique to collect requirements. Which of the following best describes the outcome of using the Delphi technique?

A. List new requirements and consolidate those requirements into a cohesive whole
B. Enable unrestrained discussions and prioritize requirements
C. Generate consensus
D. Develop a sense ofteam and enable an informal exchange of ideas

A

C. Generate consensus

Delphi is a group decision-making-technique that seeks a consensus by repeatedly consulting a panel of experts Who usually participate anonymously.

47
Q

An agile team has systematically met the previous sprints’ goals. Most of the original product backlog items have now be successfully completed according to their acceptance criteria. Which of the following statements regarding product backlog items are correct? (Choose two.)

A. Are defined as part of an analysis phase
B. Should add value to the user or customer
C. Are defined during the daily standup event
D. High-priority product backlog items should be small enough to be fully completed within a single sprint
E. Represent the tasks required to complete a sprint

A

B. Should add value to the user or customer
D. High-priority product backlog items should be small enough to be fully completed within a single sprint

Product backlog items should add value (answer B). High-priority product backlog items, which may be completed in the following sprints, should be small enough to be fully completed within a single sprint (answer D).

48
Q

You are overseeing an IT project with a history of scope management issues. Which of the following recommendations could have avoided the situation?

A. Project scope should be clearly defined at the beginning of the project
B. The team should define all the work required to meet project objectives and prevent project changes
C. The team should ensure that the project performs all the work required and only the work required
D. All of the above

A

C. The team should ensure that the project performs all the work required and only the work required

Scope management should ensure that the project performs all the work required and only the work required (answer C). The scope may be defined on an iteration basis when using an adaptive approach (answer A). Scope management should manage potential changes instead of avoiding them (answer B).

49
Q

You are currently conducting a product analysis in your logistics information system implementation project. What is the role of product analysis in scope management?

A. Decomposes project deliverables into work packages
B. Analyzes the product of the project to create the scope statement
C. Obtains a product description from the customer
D. Collects project requirements

A

B. Analyzes the product of the project to create the scope statement

Product analysis translates high level product descriptions into tangibles deliverables.

50
Q

The project management office requires that each project should establish performance baselines.
These baselines are references against which the project performance will be measured. Which of the following options is not part of the scope baseline?

A. WBS
B. Scope statement
C. Statement of work
D. WBS dictionary

A

C. Statement of work

The statement of work (SOW) is a document that describes the products or services to be delivered by the project. While it is important, it is not part of the scope baseline.

51
Q

During the early planning stages, you are working with your customer to define a clear scope definition. Which of the following should you be determining?

A. Deliverables and work packages
B. Deliverables, acceptance criteria and exclusions
C. Deliverables, list of prioritized requirements and scope management approach
D. Deliverables, assumptions and change requests

A

B. Deliverables, acceptance criteria and exclusions

A clear scope definition should include the deliverables (what the project will produce), acceptance criteria (the conditions that must be met for the deliverables to be accepted), and exclusions (what is not included in the project scope). These elements help set clear boundaries and expectations for the project. These elements ensure that all stakeholders have a shared understanding of what the project will and will not include, which helps in managing expectations and project boundaries.

52
Q

An agile team has been working on a system integration for several iterations. The team is now focused on completing several user stories that Will enable credit card payments. Which of the following statements regarding user stories are correct?

A. User stories should have value
B. User stories should be disaggregated into epics
C. User stories may be found towards the bottom of the product backlog
D. User stories may spawn several iterations

A

A. User stories should have value

The user story should add value to the business (answer A). Epics can be disaggregated into user stories (answer B). User stories may be found towards the top of the product backlog (answer C). User stories should be small to fit a single iteration (answer D)

53
Q

The project manager is working with a number of stakeholders to establish a clear understanding of the project’s needs. They are currently defining the deliverables acceptance criteria and the elements explicitly excluded from the project scope, as well as establishing a clear set of deliverables. In which document will the project manager record these elements?

A. WBS
B. Project charter
C. WBS dictionary
D. Scope statement

A

D. Scope statement

The team is defining the scope with stakeholders. Thus, the result should be a scope statement. Answers A and C are not correct because the WBS and the WBS dictionary should be prepared by the team after defining the scope statement. Answer B is not correct because the project charter should already have been prepared.

54
Q

The project manager is struggling to measure the accomplished work. Which of the following is the LEAST likely cause of the problem?

A. Poor scope definition
B. Deliverables were not decomposed into work packages
C. Poor integrated change control
D. Lack of a WBS numbering system

A

D. Lack of a WBS numbering system

A WBS code of accounts may be used to report performance but not to assess it. All other options may lead to performance assessment problems.

55
Q

A project deliverable is often developed by multiple organizational units. Which WBS element can be used to assign responsibilities to specific organizational units?

A. Control account
B. Organizational breakdown structure
C. Responsibility assignment matrix
D. Work package

A

D. Work package

Work packages can be used to assign work responsibilities to individuals or organizational units.

56
Q

Halfway through a digital transformation project, the team informed you that the development work was underestimated and that it Will not be possible to complete the project on schedule without adjusting scope requirements. What is the BEST course of action?

A. Inform the sponsor and discuss alternatives
B. Adjust the project schedule, inform the customer that the project will be late and ensure that the team addresses the issue in the next lessons learned meeting
C. Remove enough scope requirements to complete the project on schedule
D. Request additional resources and funds to complete the project on schedule

A

A. Inform the sponsor and discuss alternatives

The project manager should inform the sponsor and discuss alternatives (answer A). The project manager cannot unilaterally decide to adjust the project schedule (answer B), remove requirements (answer C) or compromise the budget (answer D).

57
Q

Your wave energy plant development project is in the planning stage. You have collected requirements and are about to define the verifiable items that must be produced to complete the project and the conditions that these items must satisfy to be accepted. What are you documenting?

A. Deliverables and product requirements
B. Work packages and product requirements
C. Deliverables and acceptance criteria
D. Project milestones and acceptance criteria

A

C. Deliverables and acceptance criteria

A deliverable is a verifiable item, whether tangible or intangible, which must be produced to complete the project. Acceptance criteria represent conditions that the deliverables must satisfy to be accepted.

58
Q

A team manager requires detailed information about a specific work package, including work descriptions, assigned roles and responsibilities, target dates, instructions and performance
assessment criteria. Which of the following should the team manager check?

A. Scope statement
B. Activity attributes
C. Work breakdown structure
D. WBS dictionary

A

D. WBS dictionary

The WBS dictionary records detailed information about the project’s work package.

59
Q

You were asked to help an agile team to adopt agile practices. You want to introduce the practice of ordering the product backlog. How should the product backlog be ordered?

A. Less complex items should be ranked higher
B. Items that were requested first should be ranked higher
C. Items that contribute more to the expected benefits should be ranked higher
D. The tasks required to create the product backlog items should be ranked higher

A

C. Items that contribute more to the expected benefits should be ranked higher

Value is the key product backlog ordering factor.

60
Q

The project started Six months ago and is now 70% complete. You are currently performing the control scope process. The control scope process can include all of the following activities, EXCEPT:

A. Validating deliverables
B. Determining actions required to correct scope variances
C. Preventing the team from completing work that is not within the project scope
D. Comparing actual scope performance with the baseline

A

A. Validating deliverables

Validating deliverables is part of the validate scope process. All other options are part of the control scope process.

61
Q

Your wave energy plant development project is in the planning stage. The team is progressively decomposing deliverables into smaller and more manageable elements. Which of the following statements regarding the work breakdown structure (WBS) and the product backlog is correct?

A. Both artifacts may be used to prioritize requirements
B. The WBS should be complete and the product backlog should evolve
C. Both artifacts represent the work that must be completed
D. Both artifacts represent the product scope

A

B. The WBS should be complete and the product backlog should evolve

The WBS captures all the project work and the product backlog should evolve to reflect the most recent understanding of the product (answer B). The WBS is not used to prioritize requirements (answer A). The product backlog does not represent the work that must be completed (answer C). The WBS does not represent the product scope (answer D).

62
Q

You are managing a project to build an office center. You are considering whether to use the nominal group technique (NGT). In which circumstances would you use a nominal group technique (NGT)?

A. When you need to present a model to key stakeholders and obtain feedback
B. When you need to gather information from large populations
C. When you need to reach a consensus through an anonymous process
D. When you need to make a decision quickly, by vote, but want everyone’s opinions taken into account

A

D. When you need to make a decision quickly, by vote, but want everyone’s opinions taken into account

NGT quickly reaches a decision through vote. Each member ranks each opinion and the highest ranked opinion is selected.

63
Q

The customer informed you that a key functionality should be added to the project’s scope. What should you do NEXT?

A. Notify management
B. Include the functionally in the project’ scope. The plan can be progressively elaborated
C. Obtain an approval for the change request
D. Analyze the change’s impact

A

D. Analyze the change’s impact

Changes should go through a change control process in which the change is analyzed. Options A and B are not managing the change, Option C would always be performed after option D.

64
Q

A global organization is expanding into an emerging market. The company wants to analyze other companies to identify best practices and generate improvement ideas. Which of the following practice would you recommend?

A. Process improvement
B. Benchmarking
C. Brainstorming
D. Expert judgment

A

B. Benchmarking

Benchmarking analyzes other projects to establish references, generate improvement ideas and create a basis for comparison.

65
Q

The team met with key stakeholders and subject matter experts and collected a large set of requirements. The team is now ranking requirements based on weighting multiple criteria. Which technique is the team using?

A. Affinity diagram
B. Idea map
C. Nominal group technique
D. Multicriteria decision analysis

A

D. Multicriteria decision analysis

The multicriteria decision analysis may be used to prioritize requirements based on previously defined weighted criteria.

66
Q

A WBS is a deliverable-oriented, treelike depiction of all the work required to accomplish the project objectives. Which of the following statements regarding work packages is CORRECT?

A. A change in a work package represents a scope baseline change
B. The WBS should include all internal and external project deliverables, including project management
C. Work packages cannot be used to assign work to organizational units
D. Work packages are found at the highest level of the WBS

A

B. The WBS should include all internal and external project deliverables, including project management

The WBS captures all the project scope (answer B). A change in a work package is not necessarily a change to the scope baseline (answer A). Work packages are frequently used to assign work to organizational units and may be found at the lowest level of the WBS (answers C and D).

67
Q

A WBS is a deliverable-oriented, treelike depiction of all the work required to accomplish the project objectives. What is the element at the lowest level of the WBS?

A. Activity
B. Work package
C. Deliverable
D. Activity attributes

A

B. Work package

The work packages are the lowest level of the WBS.

68
Q

Thomas is a customer’s project manager of a medium-sized project. Thomas is planning to rely on the decomposition technique to manage the scope of the project. The decomposition technique is used to: (Choose two.)

A. Decompose customer needs into product requirements
B. Decompose the product into deliverables
C. Decompose the deliverables into work packages
D. Decompose work packages into activities

A

C. Decompose the deliverables into work packages
D. Decompose work packages into activities

Decomposition involves breaking down project deliverables into smaller, more manageable components called work packages. This helps in organizing and defining the total scope of the project.
After breaking down deliverables into work packages, the next step is to decompose these work packages into individual activities that can be scheduled, executed, and monitored.

69
Q

The customer is complaining that a critical deliverable was not included in the approved scope statement. How should the project manager proceed?

A. Include the deliverable in the scope statement and WBS and use the project contingency reserve to accommodate the additional work
B. Analyze the impact of the change
C. Tell the customer that the deliverable is out of scope and cannot be completed
D. The scope statement does not require an update because the project objectives have not changed

A

B. Analyze the impact of the change

There is a potential scope change that should be managed through the change control process. Therefore answers A and D are incorrect. The change should not be ignored. Therefore answer C is incorrect.

70
Q

Your project is having a poor schedule and cost performance from the beginning. You believe that the root cause of the problem is the number of scope changes that were not formally controlled. The project is ___________.

A. Performing rolling wave planning
B. Planning iteratively
C. Managing stakeholders expectation correctly
D. Experiencing scope creep

A

D. Experiencing scope creep

Scope creep refers to uncontrolled additions to project and product scope.

71
Q

You want to ensure that the project deliverables meet acceptance criteria. When should scope validation be performed?

A. Immediately after defining the project scope
B. Continuously to ensure that deliverables are developed according to requirements
C. Periodically, upon completing project deliverables
D. When all the project deliverables are completed

A

C. Periodically, upon completing project deliverables

When a deliverable is completed, scope validation assesses if it was completed according to the acceptance criteria to obtain a formal sign-off. It is not, therefore, performed continuously (answer B), nor performed necessarily when all the project deliverables are completed (answer D). Scope validation is not exclusively used to validate the scope statement (answer A).

72
Q

Your team has collected requirements from stakeholders and is about to prepare requirements documentation. Which of the following should not be part of requirements documentation?

A. Functional requirements
B. Requirements management approach
C. Requirements priority
D. Business requirements

A

B. Requirements management approach

The requirements management approach is defined in the requirements management plan. All other options can be part of requirements documentation.

73
Q

An internet service provider is using scrum to develop a new product. The product owner met with key stakeholders and collected a large set of product requirements. These requirements were then
refined and prioritized. Where should the product owner record these prioritized requirements?

A. Sprint burndown
B. Sprint backlog
C. Product roadmap
D. Product backlog

A

D. Product backlog

The product backlog is a prioritized list of the features, requirements,
enhancements and product defects that might be addressed in the future.

74
Q

The team has just detected an inconsistency on the scope statement. The team believes that correcting the inconsistency is critical to project success but will probably lead to failing to meet the
project deadline. How should the project manager proceed?

A. Ignore the inconsistency because the team’s effort should be focused on the agreed-upon project scope
B. Discuss the situation with the customer
C. Correct the scope statement and try to minimize schedule delays by increasing the number of resources
D. Finish the project with the current scope statement and correct the scope after meeting the project deadline

A

B. Discuss the situation with the customer

The project manager does not have enough authority to establish a priority between scope, time and cost. The project manager should discuss the issue with the customer.