Work performance information
Meaningful data that were processed by the project management team during the control activities.
Lessons learned register
Document used to record the knowledge gained from the lessons-learned exercise.
Corrective action
Activities required to address existing variances from the project management plan.
Project management information system
Manual and automated tools required to collect, record, process and distribute information across project stakeholders.
Cycle time
Flow-based agile metric that represents the total time required to complete an item from the moment the team started working on it.
Lead time
Flow-based agile metric that represents the total time required to deliver an item to the customer (e.g., user story) from the moment it was added to the Kanban board.
Response time
Flow-based agile metric that represents the time required to start working on an item from the moment it was added to the Kanban board.
Preventive action
Activities required to address anticipated variances from the project management plan.
Issue
Any existing problem, obstacle, disagreement, conflict or difference that requires management action.
Lessons learned
Learning exercises in which participants assess and document what went well, what can be improved and future recommendations.
Issue log
Tool used to record and track issues until their resolution.
Project artifact
Document required to manage a project.
Variance analysis
Compares actual performance with planned performance.
Work performance data
Raw data that were not processed by the project management team.
Actual performance
Performance that has actually occurred.