Initiate and Plan - Prep Questions Flashcards
Exam Preparation
Team members presented the completed features to project stakeholders and ensured that everyone understood the progress toward the sprint goal. The product owner gathered suggestions from stakeholders and updated the product backlog. This agile practice is known as:
A. Product retrospective
B. Product backlog refinement
C. Release validation
D. Sprint review
D. Sprint review
A review is an opportunity to inspect and adapt the emerging product and to engage stakeholders. Team members present the completed functionality to the product owner and other stakeholders. The product owner accepts or rejects the completed items and gathers observations and suggestions from stakeholders.
You have just been assigned as project manager of a complex project adopting an agile approach.
Which of the following statements regarding business value are correct? (Choose three.)
A. You should report on realized value throughout the project
B. The team should promote opportunities for stakeholders to articulate their understanding of value
C. Product priorities should be clearly defined at the beginning of the project
D. Business value is created at the end of the project
E. The team may use surveys to determine if the business value is being delivered
A. You should report on realized value throughout the project
B. The team should promote opportunities for stakeholders to articulate their understanding of value
E. The team may use surveys to determine if the business value is being delivered
The project manager should report on realized value throughout the project (answer A). The business representative and the rest of the team should collect feedback and use that feedback to adjust the product backlog (answer B). The team may use surveys to determine if the business value is being delivered (answer E). Product priorities may be adjusted throughout the project (answer C). Partial products may be released to create business value at the end of one or more development cycles (answer D).
A global advertising company is using scrum to roll out a process-improvement initiative to other countries. The company assembled a team that will be timeboxing every scrum meeting. What is the meaning of timeboxing a meeting?
A. Meetings will always occur at the same time
B. Meetings cannot last more than the allocated amount of time
C. Meetings should not last more than the recommended amount of time
D. Meetings should last more than a certain amount of time
B. Meetings cannot last more than the allocated amount of time
Timeboxing events means that the team will stop work when the time limit is reached rather than continue until the goal is achieved.
An agile team is developing a machine learning solution using Kanban. During the early stages of the project, the team determined its workflow and established work in progress limits. Which of the
following is a good reason to limit the work in progress?
A. Because unfinished work does not add value
B. Because work must be completed within the timebox
C. Because work must be completed according to quality parameters
D. Because resources are limited
A. Because unfinished work does not add value
A work in progress limit constrains the amount of work in progress because unfinished items produce no business value.
You are managing an engine manufacturing project which is part of a larger program. The project management office requires that all projects should be authorized with a project charter. Which of
the following can approve the project charter? (Choose three.)
A. Senior management
B. Program manager
C. Project steering committee
D. Portfolio manager
E. Project manager
A. Senior management
B. Program manager
D. Portfolio manager
The project charter should be authorized by someone with enough authority to sponsor the project.
A financial institution is promoting the adoption of project management plans to improve their project management practices. Which of the following should you include in the project management plan? (Choose three.)
A. Adopted change management procedures
B. Required formal gate reviews
C. Adopted risk responses
D. Updated issue log
E. Adopted project approach
F. Updated business case
A. Adopted change management procedures
B. Required formal gate reviews
E. Adopted project approach
The risk register (answer C), issue log (answer D) and business case (answer F) are not part of the project management plan. The remaining options are part of the project management plan.
A project charter is a formal document that authorizes the beginning of the project and provides the project manager with the authority to apply resources to project activities. A project charter establishes:
A. Business need, assumptions, constraints, assigned project manager and scope statement
B. Business need, project success criteria, summary budget and summary schedule
C. Performance baselines
D. Cost-benefit analysis
B. Business need, project success criteria, summary budget and summary schedule
The business need, project success criteria, summary budget and summary schedule can be part of the project charter.
A scrum team is working on a highly anticipated product. Near the end of the second sprint, the team has completed most of the items in the sprint backlog. When is the sprint over?
A. When all the items included in the sprint backlog are completed according to their acceptance criteria
B. When all the tasks included in the sprint backlog are completed
C. When the timebox ends
D. When all the critical items are completed
C. When the timebox ends
The sprint is a fixed-duration period of time.
A friend of yours told you that her company is adopting the most popular agile framework. Which one is it?
A. Kanban
B. Scrum
C. Extreme Programming
D. Feature-Driven Development
B. Scrum
One of your friends received a call from her company’s vice president informing her that she will manage the new exhibit center construction project. She has also received a copy of the benefits management plan and business case. Which of the following should be prepared NEXT?
A. Project management plan
B. Project charter
C. Understanding of the expected project benefits
D. Statement of work
B. Project charter
A project charter should be developed to formally initiate the project (answer B). The project management plan (answer A) and statement of work (answer D) may be prepared after the project has been initiated. The project manager has already received a copy of the business case with an understanding of the expected project benefits (answer C).
Project managers are often involved in the early stages of the project, even before the project has been formally authorized. All of the following options may be performed by the project manager
during the project initiation, EXCEPT:
A. Acquire a working knowledge of the organization’s relevant processes, procedures and templates
B. Understand the project’s business need, justification and strategic alignment
C. Provide initial funding
D. Understand how benefits can be achieved
C. Provide initial funding
Provide initial funding is not one of the project manager’s responsibilities.
You are managing a critical project that Will redesign your company’s website. You are working closely with the project team to create the project management plan. All of the following options are part of the project management plan, EXCEPT:
A. Requirements documentation
B. Requirements management plan
C. Process improvement plan
D. Scope statement
A. Requirements documentation
Requirements documentation is the only available option that is not part of the project management plan. Options “B” and “C” are subsidiary plans and option “D” is part of the scope baseline.
You were hired by an insurance company that is new to agile. You are encouraging the adoption of daily standups. Which of the following expresses the reason to have a daily standup event?
A. Inspect and adapt the team’s progress towards the sprint goal
B. Report the sprint status
C. Enable the project manager to collect work performance information
D. Improve existing practices
A. Inspect and adapt the team’s progress towards the sprint goal
The ddaily standup is a short, daily event used to inspect and adapt the team’s progress.
A global advertising company is using scrum to roll out a process-improvement initiative to other countries. The company assembled an agile team that will be working in timeboxed sprints. How often will the team coordinate their progress?
A. Daily
B. Weekly
C. Once per sprint as part ofthe sprint review
D. A frequency aligned to the performance reporting cycle
A. Daily
The daily standup is a daily meeting to coordinate the team’s work.
You are working as project manager on a production system automation project. Barbara, a key project stakeholder, is requesting a critical scope change that is not aligned with the project charter.
Who should approve the change to the project charter?
A. The change control board because they should approve all scope changes
B. The sponsor who issued the project charter
C. The steering committee because the change is critical
D. Barbara because she is a key stakeholder
B. The sponsor who issued the project charter
The sponsor should approve changes to the project charter.
A global advertising company is using scrum to roll out a process-improvement initiative to other countries. The company assembled a team that will be working in timeboxed sprints. Which of the
following statements regarding timeboxing are correct? (Choose three.)
A. Timeboxing helps to build a sense of urgency
B. Timeboxing limits the work in progress to available capacity
C. An agile team working on a critical item should not stop working when the time limit is reached
D. The team must drop enough features to finish on time if the iteration is falling behind schedule
E. An agile team may timebox the daily standup meetings
A. Timeboxing helps to build a sense of urgency
D. The team must drop enough features to finish on time if the iteration is falling behind schedule
E. An agile team may timebox the daily standup meetings
The team must drop enough features to finish on time if the iteration is falling behind schedule (answer D). Fixing the schedule forces the team to build a sense of urgency and focus on the most important requirements (answer A).
Agile teams often timebox project events (answer E). Work in progress limits constrain the amount of work in progress on each process Step (answer B). An agile team should stop working when the time limit is reached (answer C).
You recently joined a global insurance company. The organization wants to adopt an agile approach that may suit projects with different sizes and criticality levels. Which of the following practices or approaches would you recommend?
A. Extreme Programming (XP)
B. Scrum of scrums
C. Plan-do-chek-act
D. Crystal Methods
D. Crystal Methods
Crystal is a family of agile methodologies with different levels of depth designed to suit projects with different sizes and criticality levels
You were asked to assist in creating an agile team that Will be working on a merger and acquisition project. After attending an agile training course, one stakeholder approaches you because he does
not understand the reason to adopt cross-functional teams. Which of the following reasons may you present? (Choose three.)
A. The team has all the expertise required to complete an increment
B. The team is able to complete the work within the timebox
C. The team shares the same values
D. Every team members has the knowledge required to complete a product backlog item
E. The team can avoid costly handovers across different functional areas
F. The team can assess problems from different viewpoints
A. The team has all the expertise required to complete an increment
E. The team can avoid costly handovers across different functional areas
F. The team can assess problems from different viewpoints
A cross-functional team has all the knowledge expertise required to complete an increment (answer A). Cross-functional teams break down functional silos and, therefore, avoid costly handovers across different functional areas (answer E). Cross-functional teams are better able to produce unique solutions and approaches because their team members assess problems from different viewpoints (answer F).
A financial institution is promoting the adoption of project management plans to improve their project management practices. Which of the following should you include in the project management plan?
A. Time-phased budget and approach used to identify, document and change configuration items
B. Scope statement, time-phased budget and record of project risks
C. Scope management plan, adopted formal gate reviews and change requests
D. Approved project schedule and records of configuration item status
A. Time-phased budget and approach used to identify, document and change configuration items
The project management plan includes the time-phased budget and the configuration management plan (answer A). The project management plan does not include the risk register (answer B), change requests (answer C) and configuration management records (answer D).
Your company is implementing an ecommerce solution. The sponsor has requested in the project charter that all products sold online should be delivered within 3 days. This request should be recorded as a(n):
A. Assumption
B. Expected outcome
C. Quality policy
D. Project constraint
B. Expected outcome
The maximum number of delivery days is a constraint limiting the project’s options. Answer A is not correct because the number of delivery days was not assumed by the project management team. It was imposed by the sponsor. The sponsor’s request is not an expected result (answer B) and it is not a quality policy (answer C).
You are managing a project that combines conventional and agile tracks. One agile team is holding a meeting to collectively plan the upcoming work. Team members are deciding which items they will
work on next and who will perform what tasks. At the end of the meeting, they will adjust the sprint backlog to reflect their improved understanding of how the sprint should progress. Which of the
following agile practices is the team adopting?
A. Sprint planning
B. Daily standup
C. Sprint review
D. Sprint retrospective
A. Sprint planning
The daily standup is a short, daily event used to inspect and adapt the team’s progress.
A pharmaceutical company is planning to develop an innovative product that it will predict the success rates of new drugs before Iaunching them into the market based on artificial technology. The
plan is to release a basic version of the product as soon as possible to seize the business opportunity.
Which of the following practices would you recommend? (Choose two.)
A. Increase the team size to complete every product backlog items as soon as possible
B. Determine the MVP
C. Prioritize the sprint backlog to focus on simpler tasks that can be completed faster
D. Delay non-critical product tests until the product is released
E. Prioritize the product backlog
F. Reduce the sprints’ duration to deliver value sooner
B. Determine the MVP
E. Prioritize the product backlog
The product owner should prioritize the product backlog and find the minimum viable product that can be released as early as possible (answers B and E).
Management wants to focus on quickly releasing a basic version of the product (answer A). Sprint backlog tasks are not prioritized (answer C). The team must complete all the necessary tests to complete the product according to the adopted standards (answer D). Reducing the sprints’ duration would enable shorter learning cycles but it would not help to release the product faster (answer F).
During the project early stages, the project manager is working closely with the project sponsor to prepare the project charter. Who should approve the project charter?
A. Customer
B. Sponsor
C. Functional manager
D. Team
B. Sponsor
The charter is usually approved by the sponsor.
Your customer service application project started 10 months ago and the team has finally completed every product backlog item according to adopted acceptance criteria. One team member informed
that two key stakeholders are unhappy claiming that the product is unfit for purpose. Which of the following is the best explanation for the situation?
A. The stakeholders did not review the Definition of Done
B. The stakeholders were not invited to the sprint reviews
C. The stakeholders did not approve the product vision
D. The stakeholders did not attend the sprint retrospectives
B. The stakeholders were not invited to the sprint reviews
The sprint review is an opportunityto inspect and adapt the product as well as engage stakeholders. The team presents the completed items and ensures that everyone understands the progress toward the goals. The product owner gathers the stakeholders’ observations and suggestions and may update the product backlog based on the collected feedback.
You are working as an agile coach for an organization that has just begun to embrace agile principles.
There are currently several agile teams working on different products. Senior management is concerned because each team is implementing agile principles differently. What would you recommend?
A. You should recommend a standardized approach to implement agile practices
B. You should organize cross-team retrospectives to share practices
C. You should explain that agile principles may be implemented differently according to the context
D. You should recommend agile training to ensure that agile principles are implemented properly
C. You should explain that agile principles may be implemented differently according to the context
Agile emphasizes the use of empirical processes that will be adjusted with the acquired experience and knowledge.
You were asked to support an agile team that is developing a vaccine. The team is using a Kanban board to visualize its process flow. The Kanban board can be used: (Choose three.)
A. As a repository of work information
B. To constrain the amount of work in progress on each process step
C. To agree on what can be done in the iteration
D. To ensure that the team is focused on quickly completing the current work
E. To visualize the prioritized requirements that may be addressed in future iterations
A. As a repository of work information
B. To constrain the amount of work in progress on each process step
D. To ensure that the team is focused on quickly completing the current work
A Kanban board is a repository of work information (answer A) and is used to constrain the amount of work in progress on each process Step (answer B) and ensure that the team is focused on quickly completing the current work (answer D). The iteration backlog is used to agree on what can be done in the iteration (answer C). The product backlog is used to visualize the prioritized requirements that may be addressed in future iterations (answer E).
Baselines provide a benchmark for comparison. Which of the following statements concerning baselines is incorrect?
A. Performance baselines are used to assess project performance
B. Baselines may be changed through formal change control
C. They are the project objectives that were established when the project management plan was first approved
D. Product baselines may be defined by the configuration management system
C. They are the project objectives that were established when the project management plan was first approved
A performance baseline is a formally approved version of project objectives. The initial baselines are established when the project management plan is approved but may be changed throughout the project (answer C). The remaining statements are correct.
During the project early stages, the project manager is working closely with the project sponsor to complete the project initiation activities. All of the following can be inputs to project initiation
EXCEPT.
A. The project charter
B. Enterprise environmental factors
C. Benefits management plan
D. Business case
A. The project charter
The project charter is the document used to formally initiate the project. It is therefore an output of project initiation. All other options can be inputs to initiating a project.
A junior project manager is overseeing a service development project with three separate teams working on different modules of the same product. The project has adopted Scrum of Scrums events
to synchronize and integrate the work of the different teams. Which of the following criteria should be used to decide who should attend the Scrum of Scrums events?
A. Representatives of each team with strong communication skills
B. Representatives of each team who are able to understand the work across the different teams
C. Representatives of each team with deep knowledge in their area of expertise
D. The product owner, scrum masters and every team member
B. Representatives of each team who are able to understand the work across the different teams
Scrum of Scrums is a scaled agile technique used to synchronize and integrate the work of several teams working on the same product. Representatives who attend should understand the work across the different teams.
A junior project manager wants to know what should be included in the performance measurement baseline. You should reply that the performance measurement baseline should include:
A. Scope statement, WBS, WBS dictionary, project schedule and time-phased budget
B. Management plans
C. Quality metrics
D. All of the above
A. Scope statement, WBS, WBS dictionary, project schedule and time-phased budget
Collectively, the scope baseline (scope statement, WBS and WBD dictionary), schedule baseline (project schedule) and cost baseline (time-phased budget) may be referred to as the performance measurement baseline.
A government agency has recently started to adopt agile practices. Which of the following statements express the agile principles? (Choose three.)
A. Projects are built around excellent processes
B. Agile may be implemented differently depending on the environment
C. Documents should create value to the customer
D. Agile teams rely on close collaboration to overcome challenges
E. Project performance is the primary measure of project success
B. Agile may be implemented differently depending on the environment
C. Documents should create value to the customer
D. Agile teams rely on close collaboration to overcome challenges
Statements B, C and D reflect the agile manifesto. Agile projects are built around motivated individuals (answer A). Realized value should be the primary measure of project success in agile projects (answer E).
One team member is insisting that team members are accountable to themselves for their assignments, actions and behaviors and for ensuring that others keep their commitments. What concept is the team member referring to?
A. Collaboration
B. Self-discipline
C. T-shaped people
D. Disciplined agile
B. Self-discipline
The concept of self-discipline means that team members are accountable to themselves for their assignments, actions and behaviors and for ensuring that others keep their commitments.
You are supporting an agile team that has been working together for several sprints. The team is focused on releasing valuable features to the customer early and frequently. Which of the following is a good reason to release features frequently?
A. Minimize changes
B. Collect regular feedback
C. Meet performance targets
D. Shorten the sprint length
B. Collect regular feedback
Agile emphasizes the importance of producing usable product versions that can release value and obtain regular feedback from users and other stakeholders.
You were hired by an insurance company that is new to agile. You are encouraging the adoption of retrospectives. Common topics addressed in the retrospective include:
A. Team morale
B. Ability to detect and address impediments
C. Actual and forecasted velocity
D. All of the above
D. All of the above
The retrospective is an opportunity to reflect on the team’s practices. The team may discuss how team morale, ability to detect and address impediments and velocity impact its effectiveness.
A junior project manager in your company asked for your help because she does not understand the purpose of a project charter. You should explain her that the project charter ___________.
A. Creates a common project vision and is authorized bythe sponsor
B. Establishes the project manager’s authority and is authorized by the functional managers
C. Establishes the management approach and is authorized by senior management
D. Establishes project constraints and is authorized by the customer and the team
A. Creates a common project vision and is authorized bythe sponsor
The project charter is authorized by the project sponsor and establishes a common vision.
You have just joined an existing team that has been working together for several month. The team is using a Kanban board to visualize work information. Who should update the Kanban board?
A. Project manager
B. Scrum master
C. Team members doing the work
D. Team leader
C. Team members doing the work
Agile teams track their own progress.
You are working with the project sponsor, capturing early assumptions and constraints, understanding previous agreements, specifying high-level requirements and ensuring that the project
is formally approved. Which of the following are you performing?
A. Developing the project management plan
B. Conducting a project kick-off meeting
C. Developing the project charter
D. Preparing a business case
C. Developing the project charter
The project charter formally initiates the project
Your company has asked you to assist in creating an agile team that will develop navigational software. Management is considering different staffing alternatives. Which of the following would
you recommend?
A. Collocated team members who are fully available for the project
B. Geographically distributed team members who are fully available for the project
C. Collocated team members who are partially available for the project
D. Geographically distributed team members who are partially available for the project
A. Collocated team members who are fully available for the project
Collocated and fully available teams are more effective.
Your team is adopting Scrum to manage a system upgrade project. The Scrum team will rely on an empirical approach to make project decisions. The Scrum empirical approach is based on:
A. Iterative and incremental development
B. Inspection, adaptation and transparency
C. Empiricism and timeboxing
D. Events and artifacts
B. Inspection, adaptation and transparency
Scrum pillars are inspection, adaptation, and transparency.
You met with key stakeholders to record a high-level understanding of the project scope before the project is formally authorized. After the meeting, a Subject Matter Expert (SME) expressed her concern that it may not be technically possible to develop one of the project deliverables. What should be done NEXT?
A. Identify the deliverable development risks and update the risk register
B. Ensure that there is enough contingency reserve to account for product development uncertainty
C. Voice your concerns and record the issue in the issue log
D. Conduct a feasibility analysis
D. Conduct a feasibility analysis
A feasibility analysis would allow the project manager to determine if it is technically possible to develop the deliverable.
The project manager is working with senior management collecting relevant historical records, defining high-level objectives, understanding the overall project risk and obtaining a project mandate. What should be done NEXT?
A. Prepare the project business case
B. Negotiate contracts with suppliers
C. Complete the project deliverables
D. Establish the project management approach
D. Establish the project management approach
The project was initiated. The project manager should now establish the project management approach (answer D). Preparing the project business case (answer A) should have been done before project initiation. Negotiating contracts with suppliers (answer B) and completing deliverables (answer C) are part of project execution.
An agile coach is encouraging the adoption of retrospectives. Which of the following activities can be part of a retrospective meeting? (Choose three.)
A. Identify impediments that are impacting performance
B. Coordinate the team’s work
C. Determine the work and effort required to complete the selected product backlog items
D. Suggest changes to improve the team’s effectiveness
E. Review the team’s common understanding of the meaning of completing a deliverable
A. Identify impediments that are impacting performance
D. Suggest changes to improve the team’s effectiveness
E. Review the team’s common understanding of the meaning of completing a deliverable
The retrospective is an opportunity for the team to determine what went well and what could be improved in the future (answer A), identify actionable items that can improve performance and remove impediments (answer D) and review their Definition of Done (answer E). The daily stand-up is an opportunity to coordinate the team’s work (answer B). Sprint planning is an opportunity to determine the work and effort required to complete the selected product backlog items (answer C).
An insurance company is planning to develop a new customer self-service application. An agile team was assigned to the project and the agile coach is encouraging the adoption of daily standups. Which
of the following questions are typically asked in a daily standup? (Choose three.)
A. How can the team improve?
B. What was done yesterday?
C. What Will be done today?
D. What are the existing impediments?
E. How can the team fix the existing product defects?
F. What Will the team do in the upcoming sprints?
B. What was done yesterday?
C. What will be done today?
D. What are the existing impediments?
A common daily standup approach is to ask team members to answer three simple questions: “what was done yesterday?”, “what Will be done today?” and “is there any impediment?” (answers B, C and D). The purpose ofthe retrospective is to improve the team’s practices (answer A). The daily standup should not be used to repair defects (answer E). The sprint review may be used to discuss what item Will be done in the following sprints (answer F).
An agile team is working in 4-week sprints to design a new laptop. During a sprint retrospective, team members are discussing the meaning of project success. Which of the following is the key measure of project success for an agile team?
A. Story points
B. Velocity
C. Performance targets
D. Working product
D. Working product
“Working software over comprehensive documentation” is an agile manifesto value.