Initiate and Plan - Prep Questions Flashcards
Exam Preparation (112 cards)
Team members presented the completed features to project stakeholders and ensured that everyone understood the progress toward the sprint goal. The product owner gathered suggestions from stakeholders and updated the product backlog. This agile practice is known as:
A. Product retrospective
B. Product backlog refinement
C. Release validation
D. Sprint review
D. Sprint review
A review is an opportunity to inspect and adapt the emerging product and to engage stakeholders. Team members present the completed functionality to the product owner and other stakeholders. The product owner accepts or rejects the completed items and gathers observations and suggestions from stakeholders.
You have just been assigned as project manager of a complex project adopting an agile approach.
Which of the following statements regarding business value are correct? (Choose three.)
A. You should report on realized value throughout the project
B. The team should promote opportunities for stakeholders to articulate their understanding of value
C. Product priorities should be clearly defined at the beginning of the project
D. Business value is created at the end of the project
E. The team may use surveys to determine if the business value is being delivered
A. You should report on realized value throughout the project
B. The team should promote opportunities for stakeholders to articulate their understanding of value
E. The team may use surveys to determine if the business value is being delivered
The project manager should report on realized value throughout the project (answer A). The business representative and the rest of the team should collect feedback and use that feedback to adjust the product backlog (answer B). The team may use surveys to determine if the business value is being delivered (answer E). Product priorities may be adjusted throughout the project (answer C). Partial products may be released to create business value at the end of one or more development cycles (answer D).
A global advertising company is using scrum to roll out a process-improvement initiative to other countries. The company assembled a team that will be timeboxing every scrum meeting. What is the meaning of timeboxing a meeting?
A. Meetings will always occur at the same time
B. Meetings cannot last more than the allocated amount of time
C. Meetings should not last more than the recommended amount of time
D. Meetings should last more than a certain amount of time
B. Meetings cannot last more than the allocated amount of time
Timeboxing events means that the team will stop work when the time limit is reached rather than continue until the goal is achieved.
An agile team is developing a machine learning solution using Kanban. During the early stages of the project, the team determined its workflow and established work in progress limits. Which of the
following is a good reason to limit the work in progress?
A. Because unfinished work does not add value
B. Because work must be completed within the timebox
C. Because work must be completed according to quality parameters
D. Because resources are limited
A. Because unfinished work does not add value
A work in progress limit constrains the amount of work in progress because unfinished items produce no business value.
You are managing an engine manufacturing project which is part of a larger program. The project management office requires that all projects should be authorized with a project charter. Which of
the following can approve the project charter? (Choose three.)
A. Senior management
B. Program manager
C. Project steering committee
D. Portfolio manager
E. Project manager
A. Senior management
B. Program manager
D. Portfolio manager
The project charter should be authorized by someone with enough authority to sponsor the project.
A financial institution is promoting the adoption of project management plans to improve their project management practices. Which of the following should you include in the project management plan? (Choose three.)
A. Adopted change management procedures
B. Required formal gate reviews
C. Adopted risk responses
D. Updated issue log
E. Adopted project approach
F. Updated business case
A. Adopted change management procedures
B. Required formal gate reviews
E. Adopted project approach
The risk register (answer C), issue log (answer D) and business case (answer F) are not part of the project management plan. The remaining options are part of the project management plan.
A project charter is a formal document that authorizes the beginning of the project and provides the project manager with the authority to apply resources to project activities. A project charter establishes:
A. Business need, assumptions, constraints, assigned project manager and scope statement
B. Business need, project success criteria, summary budget and summary schedule
C. Performance baselines
D. Cost-benefit analysis
B. Business need, project success criteria, summary budget and summary schedule
The business need, project success criteria, summary budget and summary schedule can be part of the project charter.
A scrum team is working on a highly anticipated product. Near the end of the second sprint, the team has completed most of the items in the sprint backlog. When is the sprint over?
A. When all the items included in the sprint backlog are completed according to their acceptance criteria
B. When all the tasks included in the sprint backlog are completed
C. When the timebox ends
D. When all the critical items are completed
C. When the timebox ends
The sprint is a fixed-duration period of time.
A friend of yours told you that her company is adopting the most popular agile framework. Which one is it?
A. Kanban
B. Scrum
C. Extreme Programming
D. Feature-Driven Development
B. Scrum
One of your friends received a call from her company’s vice president informing her that she will manage the new exhibit center construction project. She has also received a copy of the benefits management plan and business case. Which of the following should be prepared NEXT?
A. Project management plan
B. Project charter
C. Understanding of the expected project benefits
D. Statement of work
B. Project charter
A project charter should be developed to formally initiate the project (answer B). The project management plan (answer A) and statement of work (answer D) may be prepared after the project has been initiated. The project manager has already received a copy of the business case with an understanding of the expected project benefits (answer C).
Project managers are often involved in the early stages of the project, even before the project has been formally authorized. All of the following options may be performed by the project manager
during the project initiation, EXCEPT:
A. Acquire a working knowledge of the organization’s relevant processes, procedures and templates
B. Understand the project’s business need, justification and strategic alignment
C. Provide initial funding
D. Understand how benefits can be achieved
C. Provide initial funding
Provide initial funding is not one of the project manager’s responsibilities.
You are managing a critical project that Will redesign your company’s website. You are working closely with the project team to create the project management plan. All of the following options are part of the project management plan, EXCEPT:
A. Requirements documentation
B. Requirements management plan
C. Process improvement plan
D. Scope statement
A. Requirements documentation
Requirements documentation is the only available option that is not part of the project management plan. Options “B” and “C” are subsidiary plans and option “D” is part of the scope baseline.
You were hired by an insurance company that is new to agile. You are encouraging the adoption of daily standups. Which of the following expresses the reason to have a daily standup event?
A. Inspect and adapt the team’s progress towards the sprint goal
B. Report the sprint status
C. Enable the project manager to collect work performance information
D. Improve existing practices
A. Inspect and adapt the team’s progress towards the sprint goal
The ddaily standup is a short, daily event used to inspect and adapt the team’s progress.
A global advertising company is using scrum to roll out a process-improvement initiative to other countries. The company assembled an agile team that will be working in timeboxed sprints. How often will the team coordinate their progress?
A. Daily
B. Weekly
C. Once per sprint as part ofthe sprint review
D. A frequency aligned to the performance reporting cycle
A. Daily
The daily standup is a daily meeting to coordinate the team’s work.
You are working as project manager on a production system automation project. Barbara, a key project stakeholder, is requesting a critical scope change that is not aligned with the project charter.
Who should approve the change to the project charter?
A. The change control board because they should approve all scope changes
B. The sponsor who issued the project charter
C. The steering committee because the change is critical
D. Barbara because she is a key stakeholder
B. The sponsor who issued the project charter
The sponsor should approve changes to the project charter.
A global advertising company is using scrum to roll out a process-improvement initiative to other countries. The company assembled a team that will be working in timeboxed sprints. Which of the
following statements regarding timeboxing are correct? (Choose three.)
A. Timeboxing helps to build a sense of urgency
B. Timeboxing limits the work in progress to available capacity
C. An agile team working on a critical item should not stop working when the time limit is reached
D. The team must drop enough features to finish on time if the iteration is falling behind schedule
E. An agile team may timebox the daily standup meetings
A. Timeboxing helps to build a sense of urgency
D. The team must drop enough features to finish on time if the iteration is falling behind schedule
E. An agile team may timebox the daily standup meetings
The team must drop enough features to finish on time if the iteration is falling behind schedule (answer D). Fixing the schedule forces the team to build a sense of urgency and focus on the most important requirements (answer A).
Agile teams often timebox project events (answer E). Work in progress limits constrain the amount of work in progress on each process Step (answer B). An agile team should stop working when the time limit is reached (answer C).
You recently joined a global insurance company. The organization wants to adopt an agile approach that may suit projects with different sizes and criticality levels. Which of the following practices or approaches would you recommend?
A. Extreme Programming (XP)
B. Scrum of scrums
C. Plan-do-chek-act
D. Crystal Methods
D. Crystal Methods
Crystal is a family of agile methodologies with different levels of depth designed to suit projects with different sizes and criticality levels
You were asked to assist in creating an agile team that Will be working on a merger and acquisition project. After attending an agile training course, one stakeholder approaches you because he does
not understand the reason to adopt cross-functional teams. Which of the following reasons may you present? (Choose three.)
A. The team has all the expertise required to complete an increment
B. The team is able to complete the work within the timebox
C. The team shares the same values
D. Every team members has the knowledge required to complete a product backlog item
E. The team can avoid costly handovers across different functional areas
F. The team can assess problems from different viewpoints
A. The team has all the expertise required to complete an increment
E. The team can avoid costly handovers across different functional areas
F. The team can assess problems from different viewpoints
A cross-functional team has all the knowledge expertise required to complete an increment (answer A). Cross-functional teams break down functional silos and, therefore, avoid costly handovers across different functional areas (answer E). Cross-functional teams are better able to produce unique solutions and approaches because their team members assess problems from different viewpoints (answer F).
A financial institution is promoting the adoption of project management plans to improve their project management practices. Which of the following should you include in the project management plan?
A. Time-phased budget and approach used to identify, document and change configuration items
B. Scope statement, time-phased budget and record of project risks
C. Scope management plan, adopted formal gate reviews and change requests
D. Approved project schedule and records of configuration item status
A. Time-phased budget and approach used to identify, document and change configuration items
The project management plan includes the time-phased budget and the configuration management plan (answer A). The project management plan does not include the risk register (answer B), change requests (answer C) and configuration management records (answer D).
Your company is implementing an ecommerce solution. The sponsor has requested in the project charter that all products sold online should be delivered within 3 days. This request should be recorded as a(n):
A. Assumption
B. Expected outcome
C. Quality policy
D. Project constraint
B. Expected outcome
The maximum number of delivery days is a constraint limiting the project’s options. Answer A is not correct because the number of delivery days was not assumed by the project management team. It was imposed by the sponsor. The sponsor’s request is not an expected result (answer B) and it is not a quality policy (answer C).
You are managing a project that combines conventional and agile tracks. One agile team is holding a meeting to collectively plan the upcoming work. Team members are deciding which items they will
work on next and who will perform what tasks. At the end of the meeting, they will adjust the sprint backlog to reflect their improved understanding of how the sprint should progress. Which of the
following agile practices is the team adopting?
A. Sprint planning
B. Daily standup
C. Sprint review
D. Sprint retrospective
A. Sprint planning
The daily standup is a short, daily event used to inspect and adapt the team’s progress.
A pharmaceutical company is planning to develop an innovative product that it will predict the success rates of new drugs before Iaunching them into the market based on artificial technology. The
plan is to release a basic version of the product as soon as possible to seize the business opportunity.
Which of the following practices would you recommend? (Choose two.)
A. Increase the team size to complete every product backlog items as soon as possible
B. Determine the MVP
C. Prioritize the sprint backlog to focus on simpler tasks that can be completed faster
D. Delay non-critical product tests until the product is released
E. Prioritize the product backlog
F. Reduce the sprints’ duration to deliver value sooner
B. Determine the MVP
E. Prioritize the product backlog
The product owner should prioritize the product backlog and find the minimum viable product that can be released as early as possible (answers B and E).
Management wants to focus on quickly releasing a basic version of the product (answer A). Sprint backlog tasks are not prioritized (answer C). The team must complete all the necessary tests to complete the product according to the adopted standards (answer D). Reducing the sprints’ duration would enable shorter learning cycles but it would not help to release the product faster (answer F).
During the project early stages, the project manager is working closely with the project sponsor to prepare the project charter. Who should approve the project charter?
A. Customer
B. Sponsor
C. Functional manager
D. Team
B. Sponsor
The charter is usually approved by the sponsor.
Your customer service application project started 10 months ago and the team has finally completed every product backlog item according to adopted acceptance criteria. One team member informed
that two key stakeholders are unhappy claiming that the product is unfit for purpose. Which of the following is the best explanation for the situation?
A. The stakeholders did not review the Definition of Done
B. The stakeholders were not invited to the sprint reviews
C. The stakeholders did not approve the product vision
D. The stakeholders did not attend the sprint retrospectives
B. The stakeholders were not invited to the sprint reviews
The sprint review is an opportunityto inspect and adapt the product as well as engage stakeholders. The team presents the completed items and ensures that everyone understands the progress toward the goals. The product owner gathers the stakeholders’ observations and suggestions and may update the product backlog based on the collected feedback.