Manage Risks Flashcards
You have been hired to manage a large project. During risk response planning, the team decided to postpone the solution design, hoping that a more cost-effective technology becomes available within the next two months. Which risk response strategy did the team adopt?
A. Exploit
B. Enhance
C. Contingent response
D. Mitigate
B. Enhance
The team took proactive measures to increase the probability and impact of the opportunity.
Serious errors were found in the product during a test cycle in a software development project. Management is worried because the project Cost Performance Index is 0.8 and the Schedule Performance Index is 0.75. Additionally, the project is struggling with a lack of resources. Which of the following is the MOST likely cause?
A. Poor scope definition
B. Inadequate quality management planning
C. Lack of a resource management plan
D. Unidentified risks
D. Unidentified risks
The project is facing problems across the schedule, costs, quality, and resource
management areas. Only poor risk management would explain why the project
is facing generalized performance problems. All other options are unable to
fully explain the project performance issues.
You have been asked to take over a troubled project. The project has a CPI of 0.7 and a SPI of 0.68. The product is plagued by errors and there is an history of constant scope changes and unstable resource allocation. What is the most likely cause of the project situation?
A. The scope statement was not defined with the relevant stakeholders
B. Poor risk management
C. The staffing management plan was not approved by functional managers
D. Team members did not participate in the estimating effort
B. Poor risk management
Widespread project issues are usually the result of inadequate or insufficient
risk management. The project is facing cost, schedule, quality, scope and
human resources issues. Therefore, poor risk management is the best answer.
You met with key stakeholders and subject matter experts and collected a large set of project risks. You now need to find the underlying causes which may lead to each risk event. Which of the following options can help you to improve the risk response effectiveness by identifying the risks causes?
A. Force-field diagram
B. Fishbone diagram
C. Pareto chart
D. Triggers
B. Fishbone diagram
A fishbone diagram is used to identify the risk causes.
After completing risk response planning, residual risks remain active. These risks should be managed through the _____________ process.
A. Identify risks
B. Workaround
C. Monitor risks
D. Plan risk responses
C. Monitor risks
Accepted risks should be managed through the monitor risks process.
A risk with a significant impact occurred. The risk was not previously identified so there is no risk response available. What should the project manager do FIRST?
A. Assess the risk probability and impact
B. Accept the risk
C. Implement a contingency plan
D. Establish a workaround
D. Establish a workaround
When the risk occurs and there is no planned response, the first priority should
not be to reevaluate the risk (answer A). The priority cannot be to implement a
contingency plan (answer C), because the risk has not been identified yet.
Accepting the risk (answer B) is not an option because the risk has already
occurred. The project manager’s main priority should be to solve the problem
through a workaround.
You have been hired by a consulting company to manage a large process improvement project. After identifying and assessing risks, you are now in the middle of risk response planning. Which of the following are valid strategies for responding to opportunities? (Choose three.)
A. Exploit
B. Share
C. Transfer
D. Ensure
E. Escalate
F. Improve
A. Exploit
B. Share
E. Escalate
Exploit, share and escalate are valid opportunity response stategies.
Fearing airline strikes, your company has decided to cancel all onsite meetings scheduled for the month of April. Web meetings have been scheduled instead. What type of risk response strategy has been used?
A. Accept
B. Mitigate
C. Transfer
D. Avoid
D. Avoid
The risk was avoided, because web meetings cannont be impacted by a potential airline strike.
You are managing a critical and complex off-shore Oil exploration project. A friend of yours recommended the adoption of risk thresholds. What is risk threshold?
A. Represent a boundary that signal that additional risk responses are required
B. A risk attitude where stakeholders are willing to accept high risk in exchange for high rewards
C. Definition of risk probability
D. A classification of the willingness to accept risks, in exchange of potential rewards
A. Represent a boundary that signal that additional risk responses are required
Risk thresholds establish a limit of how much risk stakeholders are willing to
take and Signal that additional responses are required.
A risk of high impact was identified during the project. What should you do FIRST?
A. Inform management about the risk
B. Evaluate the risk
C. Implement a workaround
D. Submit a change request
B. Evaluate the risk
An identified risk, that has not yet occured, should be analyzed.
You are managing a critical project that will redesign your company’s website. You want to ensure that the project risks are managed effectively. Which of the following are valid reasons to use risk management? (Choose three.)
A. Minimize project threats
B. Address expectations because senior management is always risk averse
C. Ensure that every issue is proactively addressed
D. Avoid chaos by implementing contingency plans if the risks do occur
E. Ensure that the project meets objectives
F. Protect project value
A. Minimize project threats
D. Avoid chaos by implementing contingency plans if the risks do occur
F. Protect project value
Senior management is not necessarily risk averse (answer B). It is not possible
to ensure that every issue is proactively addressed (answer C). It is not possible
to ensure that the project meets objectives (answer E). The remaining
statements are valid reasons to use risk management.
If there is 60% chance the procured servers are late with a consequent cost overrun of 1000. What is the expected monetary value of the risk?
A. 1000 loss
B. 600 loss
C. 400 loss
D. 400 savings
B. 600 loss
The risk expected monetary value is 60%x1000=600.
A project stakeholder consistently makes decisions to avoid high risk exposure. The stakeholder is known as:
A. Risk seeker
B. Avoiding risks
C. Risk averse
D. Managing risks
C. Risk averse
The stakeholder demonstrated evidences of being risk averse, i.e., his level of
satisfaction decreases with an increase of risk exposure.
A multi-year urban renewal project has been divided into three mid-size projects to manage solution complexity. Which risk response strategy has the team adopted?
A. Avoid
B. Transfer
C. Mitigate
D. Decompose
C. Mitigate
Risk mitigation refers to proactive measures to decrease the probability and/or
impact of the threat to an acceptable level (e.g., dividing a project into mid-size
projects to manage solution complexity).
You need to make a decision considering the probabilities and impacts of two alternative approaches. Which tool or technique should you use?
A. Decision tree analysis
B. Probability and impact scale
C. Probability and impact matrix
D. Expected monetaryvalue
A. Decision tree analysis
The decision tree is a treelike model of alternative and mutually decisions with
uncertain positive or negative outcomes.
During a risk workshop the team identified, assessed and recorded four individual risks. The team now needs to rank individual risks considering their probability and impact rates. Which of the following risks should be ranked higher?
- Risk 1 with a probability rate of 4 and an impact rate of 3
- Risk 2 with a probability rate of 3 and an impact rate of 4
- Risk 3 with a probability rate of 2 and an impact rate of 5
- Risk 4 with a probability rate of 3 and an impact rate of 5
A. Risk 1
B. Risk2
C. Risk 3
D. Risk4
D. Risk4
Risks may be ranked based on their individual risk scores. An individual risk
score may be assigned multiplied the probability rate by the impact rate. Risk 4
has the highest risk score (15).
As the project matures, the team updated the risk register with new risks that have emerged and retired risks which may no longer occur. Identifying new risks that have emerged throughout the project is performed as part of:
A. Risk reviews
B. Technical performance measurement
C. Risk audit
D. The identify risks process
A. Risk reviews
Risk reviews can include identifying, analyzing and responding to new risks
during the project.
A project stakeholder made an incorrect statement about risk reviews. Which one was it?
A. Risk reviews may require risk register updates
B. Risk reviews are part of risk monitoring
C. Risk reviews assess if risk management practices are effectively addressing project risk
D. Risk reviews should be frequently performed
C. Risk reviews assess if risk management practices are effectively addressing project risk
An assessment of the risk management practices to ensure that they are
effectively addressing project risk is known as a risk audit (answer C). The
remaining statements are correct.
During a risk workshop, the team identified a long list of project risks. You need to ensure that the team is focused on the most important risks. Risks are usually prioritized based on:
A. Overall project risk
B. Cause, event and impact
C. Category and impact
D. Probability and impact
D. Probability and impact
Risks are prioritized by assessing and combining their probability of occurrence
and impact.
You have just been assigned as project manager of a pharmaceutical research project. After identifying project risks, you need to perform a qualitative risk analysis. Which of the following may you perform as part of a qualitative risk analysis? (Choose three.)
A. Use hierarchical-type charts to rank risks
B. Determine which risks require immediate risk action
C. Perform a risk review
D. Understand risk appetite
E. Define probability and impact criteria
F. Assign scores to individual risks
A. Use hierarchical-type charts to rank risks
B. Determine which risks require immediate risk action
F. Assign scores to individual risks
You have just been assigned as project manager of a pharmaceutical research project. After identifying and assessing project risks, you need to plan risk responses. Risks that remain after risk response planning are:
A. Force majeure risks
B. Residual risks
C. Pure risks
D. Secondary risks
B. Residual risks
Residual risks are risks that remain after response planning.
What is the aggregated risk expected value if the project quantitative risk analysis identified 2 risks with the following probabilities and impacts?
* Risk A with a 10% probability of a 5,000 increase in materials costs
* Risk B with a 10% probability of a decrease of 2,000 in travel expenses
A. 700
B. 7,000
C. 300
D. 500
C. 300
The first risk has an expected monetary value (EMV) of 10%x5,000=500. The
second risk has an EMV of The overall EMV should be the sum of the individual EMV.
You are currently planning a project with a clear scope of work. You defined a cost provision to account for risk. All of the following statements regarding reserve analysis are correct, EXCEPT:
A. The project manager should prevent changes to the established reserve
B. Is monitored trough the monitor risk process
C. Can be applied to both the schedule and cost
D. Compares the amount of contingency reserves available to the amount of risk
A. The project manager should prevent changes to the established reserve
As the project moves forward the reserve may be consumed, reduced or
changed through the change control mechanism. Therefore, answer A is not
correct. All other statements are correct.
As a project manager you are assessing the quality of the data available for each risk and selecting risks for further analysis and response. What process are your performing?
A. Plan risk Management
B. Data quality
C. Perform qualitative risk analysis
D. Perform quantitative risk analysis
C. Perform qualitative risk analysis
Assessing the quality of the data available for each risk and selecting risks for
further analysis and response is part of the qualitative risk analysis.
Your organization’s project management office established that critical projects should adopt quantitative risk analysis techniques. You are completing a sensitivity analysis to determine which individual risks can have the most significant impact on the project objectives. The result of this assessment may be graphically displayed by a ________________.
A. Decision tree
B. Probabilistic distribution
C. Simulation
D. Tornado chart
D. Tornado chart
Sensitivity analysis is frequently represented graphically through a tornado chart.
During risk monitoring a new risk is identified. What should be done next?
A. Ignore the risk
B. Establish a workaround
C. Document the risk on the watch list
D. Perform qualitative analysis
D. Perform qualitative analysis
The risk was identified but we do not have information to assume that it
happened. Therefore we should analyze it.
You are currently planning a project with a clear scope of work. You estimated project costs and defined a cost provision to account for risk. A contingency reserve is _____________ .
A. An active risk acceptance response
B. Determined by a risk audit
C. A passive risk acceptance response
D. Not a risk response strategy
A. An active risk acceptance response
A contingency reserve is an active risk acceptance response.
James is a junior project manager Who has just been assigned to his first project. After defining the risk management plan, James identified the individual project risks and recorded them in the project risk register. What has he done wrong?
A. Team members should be engaged in risk identification
B. Key stakeholders should be engaged in risk identification
C. Individual risks should be recorded in the risk management plan
D. The risk management plan should be prepared after identifying risks
B. Key stakeholders should be engaged in risk identification
Risk identification should be a collective effort, involving the project manager,
team members, subject matter experts, customer representatives, risk management experts, suppliers and other relevant internal or external contributors (answer B). Team members should be engaged in risk identification, but so should other relevant stakeholders (answer A). Risks should not be recorded in the risk management plan (answer C). The risk management plan should be prepared before identifying risks (answer D).
You are currently planning a project with a clear scope of work. You estimated project costs and defined a cost provision to account for risk. How can the management reserve be used in risk management?
A. Manage unknown-unknowns
B. Manage risks identified by management
C. Manage known-unknowns
D. Account for profit
A. Manage unknown-unknowns
A management reserve is a provision of time or costs, held by management, to
compensate for unforeseen events. Management reserve is created to manage
unknown-unknowns.
You want to reduce the probability and the impact of a risk to a level where it can be accepted. You want to implement a ____________ risk response strategy.
A. Avoid
B. Mitigate
C. Contingent
D. Reduce
B. Mitigate
Risk mitigation reduces the risk to a level that is acceptable.
After preparing several management plans, the project manager is ready to move on into risk identification. Who should participate in the identify risk process?
A. The project manager
B. The project manager and the customer
C. The project manager, the team and the customer
D. The project manager, other project managers, team members, the customer, subject experts
D. The project manager, other project managers, team members, the customer, subject experts
Participants in risk identification activities can include the project manager,
other project managers, team members, the customer, subject experts, risk
management team, end users and other relevant stakeholders.
On a recently initiated telecommunications project, you are defining the actions required to address individual risks. Which of the following may you update next?
A. Risk register
B. Schedule and WBS
C. Procurement management plan
D. All of the above
D. All of the above
The adopted risk responses should be recorded in the risk register (answer A).
They may also require project management plan updates (answers B and C).
During a risk workshop, the team identified a long list of project risks. You need to ensure that the team is focused on the most important risks. Which of the following may be used to prioritize individual risks? (Choose three.)
A. Overall project risk
B. Cause
C. Urgency
D. Probability and impact
E. Event
F. Proximity
C. Urgency
D. Probability and impact
F. Proximity
Risks may be prioritized considering multiple factors including the risk urgency
(answer C), the risk probability and impact (answer D) and the risk proximity
(answer F).
You have just been assigned as project manager of a pharmaceutical research project. After identifying and assessing project risks, you need to plan risk responses. The outputs of risk response planning include: (Choose three.)
A. Retire risks
B. Update the project management plan and project documents
C. Accept residual risks and address secondary risks
D. Prepare contingency plans and fallback plans
E. Escalate risks and assess technical performance
B. Update the project management plan and project documents
C. Accept residual risks and address secondary risks
D. Prepare contingency plans and fallback plans
Retiring risks and assessing technical performance are part of monitoring risks
(answers A and F). The remaining options are part of risk response planning.
You are developing the communications management plan on a robotic system project. What should you do NEXT?
A. Identify project risks
B. Ensure that there is a common understanding of how to manage risks
C. Prepare the project WBS
D. Identify project stakeholders
B. Ensure that there is a common understanding of how to manage risks
If the project manager is planning communications management, the WBS
(answer C) and the stakeholder register (answer D) should have been defined
already. Risks should be identified (answer A) after defining the risk
management plan (answer B).
You have been hired by a consulting company to manage a large process improvement project. After identifying and assessing risks, you are now in the middle of risk response planning. Which of the following risk response strategies are applicable to both threats and opportunities? (Choose two.)
A. Contingency plan
B. Accept
C. Mitigate
D. Probability
E. Escalate
F. Share
B. Accept
E. Escalate
Paul identified 30 risks that may impact his back office system implementation project. Paul wants to categorize individual risks ensure that they are logically organized. Which of the following are potential benefits of assigning risk categories to individual risks? (Choose three.)
A. Establish how risks will be managed throughout the project.
B. Improve reporting
C. Organize risk-related historical information
D. Focus risk responses on concentrations of risks
E. Provide symptoms or warning signs that a risk is about to occur
F. Measure the severity of an individual risks
B. Improve reporting
C. Organize risk-related historical information
D. Focus risk responses on concentrations of risks
The risk management approach is established in the risks management plan
(answer A). Triggers provide symptoms or warning signs that a risk is about to
occur (answer E). Individual risk scores assess individual risks (answer F). The
remaining options express potential benefits of assigning risk categories to
individual risks.
After receiving the risk report a senior manager is worried because he does not understand the concept of secondary risk. You should explain that a secondary risk is a risk that:
A. Emerges from the adopted risk responses
B. Subsists after the adopted risk responses
C. Did not require proactive responses
D. Was identified during risk monitoring
A. Emerges from the adopted risk responses
Secondary risks are risks that emerge from the adopted risk responses.