Manage Procurement Flashcards

1
Q

A buyer sent a formal invitation to potential vendors. The buyer wishes to receive offers similar in scope and make a selection based on price. Which of the following should he prepare?

A. Request for proposal
B. Invitation for bid
C. Statement of work
D. Request for quotation

A

B. Invitation for bid

In an invitation for bid, the buyer specifies the product and the solution and
requests a price from the potential supplier.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
2
Q

You are starting a new waste management project that seeks to reduce industrial, household and municipal waste. You need to decide whether a deliverable Will be delivered internally or procured from an external vendor. In a “make or buy” decision, which of the following are good reasons to do the work yourself? (Choose three.)

A. The information is confidential
B. You have resources available
C. Your team does not have the required knowledge
D. You want to transfer the risk
E. Your organization wants to retain knowledge

A

A. The information is confidential
B. You have resources available
E. Your organization wants to retain knowledge

Not having the required knowledge (answer C) and transferring the risk (answer
D) can be reasons to procure. The remaining option can be good reasons to do
the work yourself.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
3
Q

You recently joined a project that Will build a sports arena. After awarding a services contract to a local vendor, the procurement manager expressed his concern that every contract should be properly complete. In which of the following options is your contract complete?

A. All deliverables have been completed as contracted but the customer is not happy
B. AI deliverables have been completed as contracted but there are still open claims
C. Some contracted project management deliverables have not been completed
D. There was a breach in the contract

A

A. All deliverables have been completed as contracted but the customer is not happy

If all deliverables have been completed as contracted, the contract is completed.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
4
Q

Senior management requested a procurement management plan. Which of the following statements regarding the procurement management plan is correct?

A. Specifies the procured items
B. Is used to request responses from potential vendors
C. Establishes how contracts should be managed within the organization
D. Is a subsidiary management plan ofthe project management plan

A

D. Is a subsidiary management plan ofthe project management plan

The procurement management plan is a subsidiary management plan and,
therefore, a part of the project management plan (answer D). The procured
items are specified in the procurement statement of work (answer A). Bid
documents are used to request responses (e.g., proposal) from potential
vendors (answer B). The procurement management plan is not an
organizational contract management policy (answer C).

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
5
Q

The team collected the sellers’ proposals and is struggling to select the best alternative. Which of the following would be LEAST helpful?

A. Check the procurement statement of work
B. Exclude potential vendors that do not meet mandatory source selection criteria
C. Review and bargain the different contract elements with potential vendors
D. Organize a vendor conference

A

D. Organize a vendor conference

Vendor conferences should be organized before receiving the sellers’ proposals
to provide an opportunity to answer questions, identify inconsistencies and
gather improvement recommendations (answer D). The remaining answers
could help to select the best alternative.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
6
Q

John is managing a CRM software implementation across the Middle East that Will be largely based on consulting services provided by third parties. To support the procurement process, John wants to organize a bidder conference. What is the purpose of a bidder conference?

A. They are used to prepare the procurement statement of work
B. They provide potential suppliers an understanding of the technical and contractual requirements of the procurement documents.
C. They are used to collect suppliers’ proposals.
D. They are used to assess the bidders proposals and prepare a short list of potential suppliers.

A

B. They provide potential suppliers an understanding of the technical and contractual requirements of the procurement documents.

Bidder conferences are meetings organized by the buyer to help potential
suppliers understand the bid documents.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
7
Q

Your construction company has been awarded a fixed price incentive fee contract to build a bridge over a river gorge. The main reason to adopt contract incentive mechanisms is to:

A. Provide a contractual assurance that the products or services Will be supplied according to requirements
B. Synchronize the contracting parties’ objectives
C. Minimize the buyer’s cost risk provisions
D. Reduce the final price

A

B. Synchronize the contracting parties’ objectives

Contract incentives mechanisms are used to synchronize the contracting
parties’ objectives.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
8
Q

Your company needs to urgently contract the service of an interior design company to design and furnish the new office building. With no time to complete a detail scope analysis, the company should rely on:

A. A fixed-price contract
B. A time & material contract
C. Cost-reimbursable contract with incentives
D. The supplier’s experience

A

C. Cost-reimbursable contract with incentives

The new contract will include scope (design and furnish). Therefore, a time &
material contract should not be used (answer B). The scope of that contract will
not be well defined. Therefore, a fixed price contract should not be used
(answer A). Supplier’s experience would not be enough to establish a
sustainable contract. Your company should use a cost-reimbursable contract
with contract incentives to synchronize objectives with the supplier.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
9
Q

You are managing an oil-refinery expansion project that needs to procure engineering services from a global provider. You are trying to make sure that potential suppliers have a clear and common understanding of the procurement need. Which of the following is your BEST option?

A. Meet with each potential supplier separately before preparing the statement of work
B. Engage the potential suppliers in the effort to develop the procurement management plan
C. Organize a bidder conference
D. Ensure that potential suppliers receive a copy ofthe request for proposal

A

C. Organize a bidder conference

Bidder conferences are meetings organized by the buyer to help potential
suppliers to understand the bid documents.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
10
Q

A consulting company has recently started to decentralize its procurement management practices. Which of the following is a valid reason to decentralize the procurement process?

A. Improving control over the organization’s purchasing activities
B. Adopting a more standardized, professional and efficient procurement process
C. Adapting the contract to the project’s needs
D. Benefiting from better pricing

A

C. Adapting the contract to the project’s needs

Organizations that decentralize the procurement process benefit from a more
flexible procurement management process that will be better able to deliver the
procured products or services in line with the project’s specific requirements
and timings.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
11
Q

You have completed the procurement management plan and issued a request for proposal. You will now need to do perform the conduct procurement process. All of the following options are part of the conduct procurements process, EXCEPT:

A. Search the internet for potential suppliers
B. Issue a letter of intent
C. Report on contract performance
D. Receive proposals, bids or quotations

A

C. Report on contract performance

Reporting on contract performance is part of the control procurement process.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
12
Q

A team member does not know what the supplier should deliver under a contract. To which document should you direct the team member?

A. Proposal
B. Contract special terms
C. Contract statement of work
D. The project WBS

A

C. Contract statement of work

The procurement statement of work is a narrative description of the products
and services that Will be acquired under contract.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
13
Q

You decided to outsource a complex deliver of your off-shore Oil exploration project. You have prepared a formal document describing the products and services that should be provided under the contract. Which of the following have you prepared?

A. Proposal
B. WBS
C. Contract Statement of work
D. Scope statement

A

C. Contract Statement of work

A contract statement of work describes the products and services that should
be provided under the contract.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
14
Q

You are the project manager for a military project that needs to procure a highly specialized service. Your project’s procurement management plan established that the project Will adopt a firm-fixed-price (FFP) contract for its procurement process. Which of the following will be your MAIN concern?

A. Establish contract incentives to synchronize the contracting parties’ interests
B. Determine a clear statement of work
C. Oversee performance to prevent a cost overrun
D. Administer the supplier’s expenditures closely to ensure that you are only invoiced for valid expenditures

A

B. Determine a clear statement of work

The fixed price contract should be used when the scope can be clearly defined
up front (answer B). The firm-fixed-price contract does not have incentive
mechanisms (answer A). With a fixed price contract, the buyer shifts the cost
risk to the vendor (answer C) and does not need to administer the supplier’s
expenditures (answer D).

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
15
Q

Your IT project needs to contract the service of a quality assurance consulting company to ensure that the software meets proper industry standards. Which of the following would be a reason to adopt a fixed-price contract instead of a cost-reimbursable contract?

A. The buyer does not need to administer the supplier’s expenditures
B. Tends to be less expensive than a cost-reimbursable contract
C. Can be negotiated faster than a cost-reimbursable contract
D. It is a flexible contract that can easily incorporate changes

A

A. The buyer does not need to administer the supplier’s expenditures

The fixed price contract ensures the buyer does not need to administer the
supplier’s expenditures (answer A). The remaining answers represent incorrect
statements.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
16
Q

A potential supplier is proposing a contract where all authorized costs would be reimbursed up to 100,000 plus, plus a fixed amount of 10,000 and an additional 2% for each week in advance. Which contract type is being proposed?

A. CPIF
B. FPIF
C. CPFF
D. A combination of CPFF and FFP

A

A. CPIF

In a cost plus incentive fee contract (CPIF), all allowable costs are reimbursed,
plus a fixed fee, plus an incentive fee linked to performance objectives.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
17
Q

Five months into an industrial automation project, the vendor produced a deliverable that does not meet the contract statement of work. After conducting an extensive analysis, the customer’s project manager concluded that the deliverable actually meets the business need and that the contract statement of work is inconsistent. How should the customer’s project manager proceed?

A. Formally accept the deliverable because it meets the business need
B. Reject the deliverable because it does not meet the contract statement of work
C. Request a change to the contract statement of work
D. Accept the deliverable and update the project requirements documentation to ensure that the requirements are consistent and address the business need

A

C. Request a change to the contract statement of work

The customer’s project manager should request a change to the contract
statement of work to ensure that it addresses the business need (answer C).
Formally accepting the deliverable (answer A) and updating the project
requirements documentation (answer D) are not viable answers because the
deliverable would not be delivered according to contract requirements.
Rejecting the deliverable (answer B) would not address the business need.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
18
Q

You were assigned to manage a refurbishment project that needs to procure design services. You received a large number ofvendor proposals after advertising the procurement process in local newspapers. Which of the following can help the MOST in the supplier selection process?

A. Assess potential suppliers using the source selection criteria
B. Conduct a market research
C. Check the list of prequalified sellers
D. Assess potential suppliers using the adopted screening system

A

A. Assess potential suppliers using the source selection criteria

Source selection criteria provide a logical, transparent and justifiable supplier
selection process (answer A). Market researches (answer B) should have been
performed before receiving the vendor’s proposals as part of procurement
management planning. The prequalified sellers (answer C) and the screening
system (answer D) could help but they should not drive the supplier selection
process.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
19
Q

A senior manager wants to know which products or services Will be procured from an external vendor. You should refer the senior manager to the:

A. Project WBS
B. Procurement management plan
C. Procurement statement of work
D. Project scope statement

A

C. Procurement statement of work

The procurement statement of work describes the products or services that Will
be procured from an external vendor.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
20
Q

A supplier has just been informed that the customer has no more funds available to finance the project. What should the buyer do FIRST?

A. Stop all work and request a contract change
B. Strongly reduce expenditures and begin negotiations
C. Document lessons learned
D. Initiate contract closure procedures

A

D. Initiate contract closure procedures

The control procurement process should manage the contract early termination
by following the adopted closure procedures.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
21
Q

The seller has failed to provide the buyer a contracted deliverable. How should the buyer proceed?

A. Send a letter formalizing the default and meet with the supplier to identify a corrective action
B. Send a letter formalizing the default
C. Inform the supplier that such conduct is unacceptable
D. Request a contract change to remove the deliverable from the contract

A

A. Send a letter formalizing the default and meet with the supplier to identify a corrective action

When there is a breach, the other party should issue a letter formalizing it.
Additionally, the buyer should work collaboratively with the supplier so that the
breach can be corrected.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
22
Q

A company needs to establish a long-term contract with a vendor to build a number of warehouses. What contract would you recommend, to protect the customer from cost risk with a well-defined scope?

A. Fixed Price Incentive Fee (FPIF)
B. Firm Fixed Price (FPP)
C. Cost plus incentive fee
D. Fixed Price with Economic Price Adjustment Contract (FP-EPA)

A

D. Fixed Price with Economic Price Adjustment Contract (FP-EPA)

The FP-EPA contract is a type of fixed-price contract, usually used in multi-years
procurements, where the price is defined but may be adjusted yearly.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
23
Q

The procurement process faced many issues from the beginning. The team now wants to prevent that the same issues can happen in a future procurement process. Which of the following is the BEST option?

A. Perform a quality audit
B. Perform a procurement audit
C. Organize a team meeting to discuss what could be improved in the future
D. Remove the supplier from future source selection processes

A

B. Perform a procurement audit

The final purpose of a procurement audit is to identify lessons learned and
improve future procurement initiatives.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
24
Q

The project team is struggling to prepare the procurement performance report because they do not know which procurement performance metrics should be used. Which of the following options would be of MOST help?

A. Procurement audit
B. Bid documents
C. Prequalified sellers
D. Procurement management plan

A

D. Procurement management plan

The procurement management plan can include metrics used to assess the
suppliers’ performance.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
25
Q

You are the project manager for a product development project that is procuring services from a consulting firm. The contractor has just reported that it could not meet the contract schedule. What is the best course of action?

A. Proceed to contract early termination
B. Adjust the adopted procurement management approach
C. Pay the contractor according to the contract terms
D. Pay the contractor but subtract the impact of the schedule delay from the invoice amount

A

C. Pay the contractor according to the contract terms

Payments should be made according to the contract payment terms (answer C).
We don’t have enough information to assume that there is a contract breach
(answer A), that the procurement management approach should be adjusted
(answer B), or that any financial compensation is due (answer D).

26
Q

You are working as a customer’s project manager on a ship repairing project. You are currently engaged in planning procurement management. Which of the following options is part of procurement management planning?

A. Defining the procurement strategy and source selection criteria
B. Advertising the procurement process and deciding to make or buy
C. Incorporating the statement of work into a signed contract
D. Negotiating and awarding contracts

A

A. Defining the procurement strategy and source selection criteria

The procurement strategy and source selection criteria are determined as part
of procurement management planning (answer A). Advertising the procurement
process (answer B), incorporating the statement of work into a signed contract
(answer C), and negotiating and awarding contracts (answer D) are not part of
procurement management planning.

27
Q

You were assigned to manage a refurbishment project that needs to procure design services. The seller agreed to deliver a product at an established contract price plus a predefined fee for exceeding selected project objectives. Which contract was adopted?

A. FPIF
B. Firm Fixed Price
C. CPIF
D. FPAF

A

A. FPIF

A fixed price incentive fee contract defines a fixed-price plus an incentive
mechanism. Incentives are adjusted to mutually agreed-upon performance
objectives.

28
Q

An insurance company decided that an ongoing IT infrastructure deployment project is no longer justifiable, and that the existing procurement agreement with the vendor Will be closed. Which of the following activities may be performed? (Choose three.)

A. Issue a letter of intent
B. Collect the vendors’ proposals
C. Negotiate open claims
D. Deal with outstanding payments
E. Prepare a final performance report

A

C. Negotiate open claims
D. Deal with outstanding payments
E. Prepare a final performance report

29
Q

The team used as a benchmark to verify if the supplier’s response was adequate and the procurement statement of work (SOW) was well understood. Which of the following did the team used?

A. Independent estimates
B. Contract
C. Source selection criteria
D. Screening system

A

A. Independent estimates

Significant variances between the buyer’s estimate and the independent
estimate may indicate that the supplier’s response is not adequate, or that the
procurement statement of work (SOW) was not well defined

30
Q

You are asked to make a presentation on the contract performance. During the presentation, one stakeholder made an incorrect statement regarding procurement control. Which one was it?

A. The control procurement process is performed by buyer and supplier
B. The buyer may inspect and audit the supplier’s work
C. The supplier may issue claims
D. The project manager is the main responsible for contract change management

A

D. The project manager is the main responsible for contract change management

The project manager is not accountable for procurement management
activities.

31
Q

Halfway through your construction project, the customer has been informed that the vendor has used defective materials on the building foundations. As a result, the project objectives have been definitively compromised. How should the customer proceed?

A. Compel the supplier to complete the project as specified in the contract
B. Meet with the supplier and document an issue on the issue log
C. File a change order
D. File a suit for the damages generated bythe material breach

A

D. File a suit for the damages generated bythe material breach

When a material breach occurs, the non-breaching party can compel the other
party to complete performance as agreed upon or collect damages. In this case,
project objectives have been definitively compromised. Therefore, the buyer
should file a suit for the damages generated by the material breach.

32
Q

You are managing a project under a fixed-price contract. Which activity Will enable you to have a formal assessment of the supplier’s capacity to perform the project according to contract conditions?

A. Source selection
B. Procurement audit
C. Quality audits
D. Procurement performance reviews

A

D. Procurement performance reviews

A procurement performance review is a formal assessment of the supplier’s
capacity to perform the project according to contract conditions.

33
Q

At the end of the contract, the seller was reimbursed for all authorized costs, but received a high fee based on subjective criteria that had been defined in the contract. What type of contract was adopted?

A. Cost Plus Fixed Fee (CPFF) contract
B. Fixed Price Award Free (FPIF) contract
C. Cost Plus Incentive Fee (CPIF) contract
D. Cost Plus Award Fee (CPAF) contract

A

D. Cost Plus Award Fee (CPAF) contract

A cost plus award fee (CPAF) contract is a cost-reimbursable type of contract
that reimburses all allowable costs , plus a fixed fee, plus an award fee based on
performance.

34
Q

The project manager is involved in a procurement negotiation with a potential supplier. Which of the following should be done NEXT?

A. Establish the bid documents
B. Establish a performance bond in the contract
C. Prepare a statement of work
D. Prepare the procurement management plan

A

B. Establish a performance bond in the contract

A performance bond is a contract tool that guarantees satisfactory completion
of a project’s contract. Establishing a performance bond contract term would
still be part of the conduct procurement process.

35
Q

You are trying to decide which contract to use in a specific procurement process. All of the following are good reasons to choose a cost-reimbursable instead of a fixed-price contract, EXCEPT:

A. It requires less time to prepare
B. The price is usually cheaper
C. Shifts the cost risk to the vendor
D. Is more flexible

A

C. Shifts the cost risk to the vendor

The cost-reimbursable contract requires a considerable administration effort
from the buyer, because the buyer has to make sure that the supplier is only
using the resources absolutely needed and is only invoicing the resources
used.. All other options are advantages of a cost-reimbursable contract.

36
Q

The procurement strategy established that the project must adopt a CPIF contract during its procurement process. How is the vendor’s profit determined when adopting a CPIF contract?

A. It is fully established up front
B. It is determined bythe contract’s fixed fee and incentive fee
C. It is determined by the contract’s target fee
D. It is determined by the difference between the actual cost and the target cost

A

B. It is determined bythe contract’s fixed fee and incentive fee

In a cost plus incentive fee contract (CPIF) the vendor’s profit equals the fixed
fee plus the incentive fee.

37
Q

You were hired by a company to manage a critical project that Will be partially outsourced to a large vendor. The sponsor pointed out that a fixed price contract Will be used in all procurement processes. All of the following are advantages of using fixed price contract, EXCEPT:

A. It is a flexible contract
B. It is easierto plan how the project Will be funded
C. The cost risk is low
D. The buyer does not need to administer the supplier’s expenditures

A

A. It is a flexible contract

The fixed price contract is more rigid than other alternative contract types.

38
Q

Your company has prepared a contract statement of work with limited scope definition. What contract would you recommend, to protect your company from cost risk?

A. Cost plus fixed fee
B. Purchase order
C. Fixed price plus incentive fee
D. Time & materials

A

A. Cost plus fixed fee

There is scope, therefore it cannot be a time & material contract, nor a purchase
order. Since there is a limited scope definition, the fixed price contract is not
recommendable.

39
Q

You are the customer project manager for a surface mining project. The vendor issued a written demand calling for monetary compensation. Which of the following is LEAST relevant when reviewing a procurement claim?

A. Negotiation meeting minutes
B. Approved contract changes
C. Contract
D. Procurement management plan

A

A. Negotiation meeting minutes

All decisions prior to the contract, that were not included or specified by the
contract, do not legally bind the parties.

40
Q

A team member is unsure of the purpose of controlling the procurement process. You should explain that the primary objective of the process is to:

A. Define the contract change management procedures
B. Ensure that the buyer and seller meet contract requirements
C. Collect the vendors’ proposals and negotiate procurement agreements
D. Manage the contract early termination

A

B. Ensure that the buyer and seller meet contract requirements

The control procurement process assesses the seller’s and buyer’s performance
to ensure they meet contract requirements (answer B). Defining the contract
change management procedures (answer A), collecting the vendors’ proposals
and negotiating procurement agreements (answer C) are part of the conduct
procurement process. Managing the contract early termination (answer D) is
part of the control procurement process but it is not its main purpose.

41
Q

You have just been put in charge of a business process reengineering project. The procurement department has asked you to negotiate the contract terms and conditions with the selected supplier. What should be your main concern during the negotiation?

A. Remain positive and establish a mutually beneficial contract
B. Establish a clear statement of scope
C. Settle outstanding claims
D. Bargain for the best price

A

A. Remain positive and establish a mutually beneficial contract

The main purpose of negotiating procurement agreements is to establish a
mutually beneficial contract that may sustain a partnership relationship.

42
Q

You were tasked with managing a project that Will procure software development services from an external source. The request for proposal requires that the vendor project manager must be accredited by an international organization. Upon receiving the proposals, you excluded all the potential suppliers that did not meet this mandatory requirement. Which of the following did you use?

A. Weighting system
B. Screening system
C. Performance requirement
D. Waiver

A

B. Screening system

A screening system eliminates from the selection process those suppliers that
do not meet the source selection criteria.

43
Q

You have been hired by a company that has been doing business for over 30 years. A new project was initiated to build electronical devices for consumers. Who Will be accountable for the overall procurement process considering that you work in a weak matrix organization?

A. Team members performing procurement management activities
B. The project manager
C. Management
D. Procurement specialists

A

D. Procurement specialists

Due to the technical specialization and juridical nature of procurement
management work, the procurement manager is accountable for procurement
management activities.

44
Q

You are starting a new waste management project that seeks to reduce industrial, household and municipal waste. You selected a supplier without consulting other alternatives. Which of the following is the buyer’s main concern in a sole-source procurement process?

A. Using the source selection criteria correctly
B. Defining a fixed price contract
C. Vendor’s qualifications to deliver the procured product or service
D. Vendor’s financial status

A

C. Vendor’s qualifications to deliver the procured product or service

The buyer chose to select a supplier without consulting other alternatives. The
main risk of sole-source procurement is assuming that a previous positive
experience implies good performance in the future.

45
Q

Senior management is concerned with the level of cost risk of your construction infrastructure project. In which of the following contract types Will the buyer bear most of the cost risk?

A. Cost plus fixed fee (CPFF)
B. Firm fixed-price (FFP)
C. Fixed-price incentive fee (FPIF)
D. Cost plus incentive fee (CPIF)

A

A. Cost plus fixed fee (CPFF)

With a cost plus fixed fee contract, the supplier is reimbursed for all allowable
actual costs plus a profit fee. Thus, the buyer bears most of the cost risk
(answer A). With a fixed price contract, the buyer has a limited cost risk
(answers B and C). Incentive mechanisms (answer D) limit the buyer’s cost risk.

46
Q

The contracting officer wants to exempt the company from fulfilling their obligations should unforeseeable causes occur. The contract should:

A. Specify unknown unknowns
B. Include a force majeure clause
C. Include a termination for convenience cause
D. Include an incentives system

A

B. Include a force majeure clause

Force majeure is a contract clause that releases parties from contract
obligations when a predefined uncontrollable event occurs.

47
Q

A consulting company has recently started to decentralize its procurement management practices. Which of the following are valid reasons to decentralize the procurement process? (Choose two.)

A. Improve negotiating position
B. Gain more access to people performing procurement management activities
C. Adapt contracting decisions to project’s interests
D. Fixed-price contracts can be used
E. Improve flexibility

A

C. Adapt contracting decisions to project’s interests
E. Improve flexibility

48
Q

You are about to develop the bid documentation and send it to potential suppliers. You wish to receive a response with an approach and a price. Which of the following should you prepare?

A. Requestfor proposal
B. Invitation for bid
C. Request for quote
D. Proposal

A

A. Requestfor proposal

A request for proposal is used when the buyer wishes to receive a solution and
a price for a specific need.

49
Q

You need to procure a standard material, equally available from a number of suppliers. Which bid document should be prepared?

A. RFQ
B. IFB
C. RFP
D. RFI

A

A. RFQ

The request for quotation (RFQ) is the document used to request a price for a
standardized item.

50
Q

You are starting a new game development project as project manager. What Will be your main responsibility in the procurement process?

A. Establish a bridge between the procurement business function and the project
B. Prepare bid documents
C. Establish source selection criteria
D. Approve changes

A

A. Establish a bridge between the procurement business function and the project

Project managers are not typically accountable for the procurement
management activities. They do not usually have the authority to legally bind
the organization by awarding, changing or closing contracts. The project
managers’ responsibility is to establish a bridge between the procurement
business function and the project, ensuring the contract meets the project’s
needs, confirming that the procurement management policies are carried out
and assisting the procurement department as required.

51
Q

You are the project manager for a military project that needs to procure a highly specialized service. Your company decided to adopt fixed-price contract to manage cost risk. What was the adopted risk response strategy?

A. Transfer
B. Explore
C. Workaround
D. Avoid

A

A. Transfer

The company transferred the cost risk to the supplier.

52
Q

You are working as a project manager on an infrastructure development project. An external team conducted an independent structured assessment of the project’s procurement management practices to ensure that they comply with adopted procedures and the organization’s policies. You are reviewing their report to determine how to implement their recommendations. Which of the following activities is being performed?

A. Defect repair
B. Quality audit
C. Procurement audit
D. Procurement inspection

A

C. Procurement audit

The external team conducted a procurement audit.

53
Q

You have completed the procurement management plan and issued a request for proposal. You will now need to do the work required to to award the contract. Which of the following activities may you perform?

A. Authorize contract payments
B. Negotiate with suppliers
C. Compare the supplier’s estimate to an independent estimate
D. Authorize the start of the supplier’s work
E. Rate the supplier’s performance
F. Place adverts to attract potential vendors

A

B. Negotiate with suppliers
C. Compare the supplier’s estimate to an independent estimate
F. Place adverts to attract potential vendors

54
Q

While planning procurement management, you are trying to decide which contract would best fit your project needs. Which of the following should you recommend if you want to protect your company from cost risk, with a limited scope definition?

A. Cost Plus Incentive Fee Contracts (CPIF)
B. Time & material(T&M)
C. Firm Fixed Price (FFP)
D. Fixed Price Incentive Fee Contracts (FPIF)

A

A. Cost Plus Incentive Fee Contracts (CPIF)

With limited scope, a buyer should not choose a fixed price contract. A T&M
contract is not an option since there is contract scope.

55
Q

You were hired to manage a energy infrastructure project that Will be outsourced to a global vendor. The procurement strategy requires that fixed price contracts are used in all procurement processes. Which of the following would minimize the buyer’s cost risk if the project scope is well known?

A. Cost Plus Incentive Fee
B. Fixed Price Incentive Fee
C. Firm Fixed Price
D. Cost plus Percentage of Cost

A

C. Firm Fixed Price

A firm fixed price contract minimizes the buyer’s risk if the project scope is well
known.

56
Q

You scheduled a meeting with potential vendors to review the bid documents, clarify questions and collect improvement suggestions. What should be your main concern during the meeting?

A. Ensure that the supplier’s work meets contract requirements
B. Negotiate mutually beneficial conditions that may sustain a partnership relationship
C. Ensure that every decision is formally documented
D. Ensure that procurement information is equally shared among bidders

A

D. Ensure that procurement information is equally shared among bidders

In a bidder conference, the buyer should ensure that the procurement
information provided to individual suppliers is equally shared with the
remaining bidders.

57
Q

You are overseeing a production line automation project. Most of the design work is being performed by an external contractor working under a fixed price contract. Which of the following sets of activities may you perform as part of procurements control?

A. Administering claims and conducting market research
B. Reviewing contract changes and reporting procurement performance
C. Preparing a procurement strategy and ensuring that the supplier meets contract requirements
D. Awarding the contract and conducting procurement audits

A

B. Reviewing contract changes and reporting procurement performance

Reviewing contract changes and reporting procurement performance (answer
B) are part of procurements control. Conducting market research (answer A)
and preparing a procurement strategy (answer C) are part of procurement
management planning. Awarding the contracts (answer D) is part of the
conduct procurements process.

58
Q

You are working as a supplier’s project manager on a bridge construction project. The customer sent conflicting specification instructions which resulted in additional work for your design team. You now need to formally request monetary compensation. How should you proceed?

A. Issue a letter of default
B. Request compensation for breach of warranty
C. Issue a letter of intent
D. File a claim

A

D. File a claim

A claim is a written demand of one of the contract parties calling for monetary
compensation.

59
Q

You want to ensure that the team uses a logical, transparent and justifiable supplier selection process. You decided to adopt a weighting system because you want to:

A. Select the supplier quickly
B. Exclude vendors that do not meet mandatory source selection criteria
C. Prioritize vendors according to predefined criteria
D. Contact a short list of qualified vendors

A

C. Prioritize vendors according to predefined criteria

The weighting system uses the source selection criteria, previously established
in procurement management planning, to rank and select suppliers. A
screening system excludes potential vendors that do not meet mandatory
source selection criteria.

60
Q

You are overseeing a production line automation project. Most of the design work is being performed by an external contractor working under a fixed price contract. Which of the following activities may be performed as part of procurements control? (Choose three.)

A. Providing a formal written notice accepting that the contract is closed
B. Issuing a statement of work
C. Auditing on the procurement process
D. Implement post-project recommendations
E. Authorizing payments

A

A. Providing a formal written notice accepting that the contract is closed
C. Auditing on the procurement process
E. Authorizing payments