Emily is starting a new digital transformation project as project manager. She wants to ensure that the project has the resources required to perform the project activities and produce the expected
outcome. How should Emily determine the team requirements?
A. Select the best resources from the existing pool of candidates
B. Decompose your project requirements to get a detailed understanding the required skillset
C. Determine the number of resources required for each project phase
D. Conduct face-to-face meetings with resource candidates to assess their skills and confirm their availability
B. Decompose your project requirements to get a detailed understanding the required skillset
Resource requirements will typically be collected at the detailed level to provide an understanding of the required skillset.
You are acquiring resources for your back office system implementation project. Which of the following sets of activities may you perform?
A. Selecting the most appropriate resource candidates and updating resource calendars to reflect resource allocation
B. Collecting resource requirements, negotiating resources and handling issues that can negatively influence the team’s performance
C. Updating the team directory to reflect how resources were pre-assigned to the project and approving a change
request to adapt the schedule to the resources that were actually acquired
D. Relying on virtual teams to fulfill resource requirements and organizing team building exercise
A. Selecting the most appropriate resource candidates and updating resource calendars to reflect resource allocation
Selecting the most appropriate resource candidates and updating resource
calendars to reflect resource allocation are part of acquiring resources (answer
A). Managing team members’ issues (answer B), approving a change request to
adapt the schedule to the resources that were actually acquired (answer C) and
organizing team building exercises (answer D) are not part of acquiring resources.
In the early planning stages of the project, you are preparing a project schedule considering the resources required to complete the project work. You need to access information about the team members’ availability and planned vacation time. Where can you find that information?
A. Gantt chart
B. Resource management plan
C. Resource calendars
D. Resource requirements
C. Resource calendars
Resource calendars document when team members are available to work on project activities.
A team member wants to know what his project responsibilities are. You should tell the team member to check the:
A. Responsibility management plan
B. Resource breakdown structure (RBS)
C. Responsibility assignment matrix
D. Team charter
C. Responsibility assignment matrix
The responsibility assignment matrix ensures that responsibilities are properly defined.
You were assigned to a global project with teams scattered across five countries. You are currently planning how resources will be managed. Which of the following activities may you perform as part of resource management planning? (Choose three.)
A. Describe roles and responsibilities
B. Assess the team performance
C. Define reporting hierarchies
D. Clarify how staff Will be acquired to the project
E. Acquire the people required to complete the project
A. Describe roles and responsibilities
C. Define reporting hierarchies
D. Clarify how staff Will be acquired to the project
The project manager may assess the team performance (answer B) and acquire
the people required to complete the project (answer E) to implement the
resource management plan. The remaining options are part of resource
management planning.
You are working closely with your project sponsor to complete a preliminary project schedule. What will you do NEXT?
A. Obtain the people required to complete the project
B. Submit the project schedule for approval
C. Update resource calendars to reflect resource assignment
D. Determine how to acquire the required resources
D. Determine how to acquire the required resources
During the early stages of planning, the project manager will prepare a
preliminary schedule based on preliminary resource availability information.
Later, a resource management plan will determine how to acquire the required
resources. Options A, B and C Will be performed after option D.
You are coaching a junior project manager Who is managing her first project. She needs to prepare a responsibility assignment matrix (RAM). How should she proceed?
A. Define role and responsibilities
B. Describe resources availability
C. Define project hierarchies
D. Identify the skills set o the resources required to complete the project
A. Define role and responsibilities
The responsibility assignment matrix is used to define the team member’s
responsibilities.
You were assigned to a global project with teams scattered across five countries. You are currently planning how resources will be managed. Which of the following activities may you perform as part of resource management planning? (Choose three.)
A. Look for potential resource candidates and select the most appropriate
B. Define the required specific set of skills of each role
C. Clarify resource security authorizations
D. Estimate the cost of the resources
E. Ensure that resources are allocated according to plan
F. Define how the project will adapt to existing resource management policies and regulation
B. Define the required specific set of skills of each role
C. Clarify resource security authorizations
F. Define how the project Will adapt to existing resource management policies and regulation
The project manager may look for potential resource candidates and select the
most appropriate (answer A) when acquiring resources. Estimating the cost of
the resources (answer D) is part of estimating costs. Ensuring that resources are
allocated according to plan (answer E) is part of controlling resources.
When the project was authorized, the program manager immediately assigned several team members to the project. The team members are considered:
A. Unallocated
B. Iteratively assigned
C. Pre-assigned
D. Virtually assigned
C. Pre-assigned
Pre-assignment refers to assigning resources to the project in advance before
the resource management plan is developed.
Resource-related issues are threatening the project performance. Team members are unclear about “who owns what activity,” “who does what” and “who should decide.” A project manager is determining how resources Will be managed. A responsibility assignment matrix can be used to assign:
A. Work packages to organizational units
B. Team members to the project schedule
C. Requirements to team members
D. Team members to work packages
D. Team members to work packages
A responsibility assignment matrix assigns WBS work packages to team
members to clearly define responsibilities.
When the project started, a few team members had already been assigned to the project team according to a specific customer request. This is an example of:
A. Resource negotiation
B. Colocation
C. Ground rules
D. Pre-assignment
D. Pre-assignment
In pre-assignment, resources are selected for the project without any type of
negotiation with the project manager.
A team member is not clear about to whom she should report to within the project. You should direct the team member to the:
A. Responsibility assignment matrix
B. Organizational breakdown structure
C. Project organization chart
D. Communications management plan
C. Project organization chart
A project organization chart displays the reporting hierarchy between team
members.
To deal with a problem of resource over allocation, the project manager is performing resource leveling. Which of the following would best help the project manager?
A. Project schedule
B. Staffing management plan
C. Resource histogram
D. Resource assignment matrix
C. Resource histogram
The resource histogram is a graphical representation of a time-phased resource
allocation, usually through vertical bars. The chart can include the available
capacity and the resource allocation and Will enable an analysis on resource
over alocation.
Resource-related issues are threatening the project performance. Team members are unclear about “who owns what activity,” “who does what” and “who should decide.” You decided to prepare a RACI chart. A RACI charts classifies responsibilities as:
A. Review, Accountable, Communicated and Informed
B. Responsible, Approval, Consulted and Independent
C. Review, Approval, Communicated and Ignored
D. Responsible, Accountable, Consulted and Informed
D. Responsible, Accountable, Consulted and Informed
You want to be able to analyze cost variances by organizational units. Which of the following resource management tools can assist you?
A. Control account
B. Work breakdown structure
C. Resource breakdown structure
D. Organizational breakdown structure
D. Organizational breakdown structure
In large projects and programs, setting up an organizational breakdown
structure can help to assess variances by organizational units.