Manage changes - Prep Questions Flashcards
Exam preparation questions
One month before the project scheduled completion, the customer requested an additional critical requirement. What should the project manager do NEXT?
A. Request management support
B. Inform the customer that the requirement Will be delivered by a future project
C. Obtain approval to move forward with the change
D. Follow the integrated change control process
D. Follow the integrated change control process
Changes should be processed by the change control process.
A key stakeholder requested a change to the project scope. The project management team has thoroughly assessed the change impact. What should be done NEXT?
A. Update the project management plan
B. Implement the change
C. Communicate the change
D. Prepare a change request
D. Prepare a change request
The change has already been identified and assessed. The next step is to record the change.
You are leading a project team that will develop a new application dedicated to the media industry. You are currently defining the change control approach. Which of the following is the best approach for planning change management?
A. There is no point in planning change because changes are not predictable
B. A specific change management approach should be determined for each specific change because each change is unique
C. Better planning avoids the need for changes
D. Establish a common approach to manage changes
D. Establish a common approach to manage changes
The rules used to manage changes are defined in the change management plan. Even though changes are unpredictable, the rules used to manage changes can be defined in advance in a change management plan. Therefore answers A and B are not correct. Answer C is not correct because changes cannot be fully avoided.
You are a senior project manager working in a retail travel agency. The company has just issued a press release announcing a change in its business strategy that can negatively impact your project.
What is the FIRST thing to do?
A. Submit a change request to revise the schedule
B. Meet with the project sponsor to understand how the business change Will impact your project
C. Compress the schedule to finish the project sooner
D. Wait until you can clearly understand how your project Will be impacted
B. Meet with the project sponsor to understand how the business change will impact your project
You should manage changes proactively to increase your ability to influence them (answer B). You may need to change (answer A) or compress the schedule (answer C) but that should not be the first thing to do. Waiting until the change is confirmed (answer D) is a reactive approach that can limit your options.
You are working as a project manager in an assembly line automation project. Your company wants to improve the adopted change control practices. Which of the following statements regarding change management is correct? (Choose three.)
A. The change request status should be updated
B. Changes should be communicated to project stakeholders
C. The project manager does not have the authority to approve project changes
D. The project manager may escalate changes to the sponsor
E. Documenting changes in the assumptions log
A. The change request status should be updated
B. Changes should be communicated to project stakeholders
D. The project manager may escalate changes to the sponsor
Depending on the rules established in the change management plan, the project manager might have the authority to approve some types of change requests (answer C). Changes are not recorded in the assumptions log (answer E). The remaining statements are true.
You have just been hired to manage an engine design project. Two months into the project, the production manager wants to change the engine design. Who should approve the project change?
A. Check the change management plan
B. Project sponsor
C. Steering committee
D. Change control board
A. Check the change management plan
The change management plan should define who should approve project changes
You are taking over an industrial project from a project manager who is retiring. The team is struggling to manage changes. Your main concern when handling the project changes should be to:
A. Control and track the changes
B. Protect the integrity of the project baselines
C. Ensure that the changes are either approved or rejected
D. Encourage beneficial project and organizational changes and discourage disadvantageous changes
D. Encourage beneficial project and organizational changes and discourage disadvantageous changes
All the available answers should be important concerns when handling project changes. Your main concern, however, should be to influence those changes, encouraging beneficial changes and discouraging disadvantageous changes.
You are a customer’s project manager on an urban renewal project. You need to track down changes to specific product element. You should use the project’s:
A. Issue log
B. Change management system
C. Configuration management plan
D. Work authorization system
C. Configuration management plan
The configuration management plan defines formal and specific guidelines and tools to control product specific elements.
You were assigned to a new project that is critical to a critical digital transformation program. You are considering whether your project should adopt a change control board. Which of the following statements regarding a change control board is correct? (Choose three.)
A. Some project changes should not be reviewed by the change control board
B. The change control board should approve major deliverables
C. The change control board role and responsibility is defined in the change management plan
D. The change control board should approve or reject change requests when required
E. The change control board should assess project variances and issue corrective actions as required
A. Some project changes should not be reviewed by the change control board
C. The change control board role and responsibility is defined in the change management plan
D. The change control board should approve or reject change requests when required
The change control board does not approve deliverables (answer B). The change control board does not monitor project variances (answer E). All other statements are correct.
You are leading a project team that will develop a new application dedicated to the media industry. You are currently defining the change control approach. All of the following may be included in the
change management plan, EXCEPT:
A. Which project documents are subject to formal change control
B. Role of the change control board
C. A list of approved change requests
D. Procedure that enables an automatic approval of changes in case of emergency
C. A list of approved change requests
The change management plan includes the rules used to manage changes. Those rules can include procedures (answer D), responsibilities (answer B) and identify which project documents are subject to formal change control (answer A). Answer C is not correct because change requests should not be recorded in the change management plan. They can be recorded in the change log.
Jennifer is managing her first hybrid project. She has just issued a change request to address a significant schedule variance. A change request can be issued to address:
A. Defect repairs
B. Corrective actions
C. Preventive actions
D. All of the above
D. All of the above
Change requests may address defect repair, corrective and preventive actions.
Your company has been awarded a contract to build a shopping mall and you were formally assigned to lead the project team. You want to ensure that the project has the right governance structure.
Which of the following options can BEST describe the role of the change control board?
A. Approve or reject changes to project documents
B. Approve or reject changes to organizational policies and procedures
C. Approve or reject changes to work packages
D. Approve or reject project changes
D. Approve or reject project changes
A change control board is a formal board established to review and validate changes requests. Answers A and C are not correct because changes to project documents and work packages do not necessarily lead to change requests. Answer B is not correct because changes to policies and organization procedures are not manage within the project.
You have just been put in charge of a large infrastructure development project. You are currently defining the change control approach. The project change control system should be used to manage changes to:
A. Deliverables
B. Project documents
C. Project performance baselines
D. All of the above
D. All of the above
The change control system can manage changes to deliverables, project documents and project performance baselines.
You are working as a project manager in an assembly line automation project. Your company wants to improve the adopted change control practices. Which of the following statements are part of integrated change control process? (Choose three.)
A. Ignore changes that are not within the project scope
B. Manage changes to configuration elements
C. Perform a cost-benefit analysis to determine if the change is justifiable
D. Protect the integrity of project baselines throughout the change process
E. Ensure that updates to project documents are recorded as project changes
B. Manage changes to configuration elements
C. Perform a cost-benefit analysis to determine if the change is justifiable
D. Protect the integrity of project baselines throughout the change process
Your sports arena construction project started 18 months ago and is now nearly complete. Senior manager requested a scope change that the team believes will not impact the project timeline and
budget. However, you are concerned because the project must be completed on schedule. What is the BEST thing to do?
A. Implement the change because it does not affect the project timeline and budget
B. Follow the change management plan
C. Inform the manager that the team cannot implement the change because the project is nearly complete
D. Ensure that the change is approved before implementing it
B. Follow the change management plan
Changes should be managed according to the change management plan (answer B). A thorough analysis of the change (answers A and D) may reveal that it can impact several project constraints (e.g., scope, schedule, costs, quality, resources and risks). Changes should be managed, even when the project is nearly complete (answer C).