Manage Budget - Prep Questions Flashcards
A project has the following performance information:
BAC = 2,000,000
AC = 1,800,000
PV = 1,800,000
EV = 2,000,000
Which of the following statements BEST defines project performance?
A. The project has an unfavorable cost performance
B. The project has finished before its scheduled date
C. The project is late
D. The project should have been completed
B. The project has finished before its scheduled date
The project is completed because EV-BAC. However, the project has finished before its scheduled date because EV > PV.
Senior management places budget limits above other project constraints. In the last status meeting you reported that the project to-complete performance index (TCPI) was 1 .1. What does a TCPI represent?
A. Expected total cost at project completion
B. Ratio between earned value and actual cost
C. Estimate cost to complete the project
D. The performance required in the future to achieve a previously defined objective
D. The performance required in the future to achieve a previously defined objective
TCPI is the performance required in the future to achieve a previously defined objective (the budget or a revised objective).
You are currently planning a project with a clear scope of work. You estimated project costs and defined a cost provision to account for risk. The project has a baseline cost of 100,000, a total funding
of 115,000 and a _________ of 15,000.
A. Management reserve
B. Negative cost variance
C. Contingency reserve
D. Positive cost variance
A. Management reserve
The budget is the sum of the baseline cost plus the management reserve.
Therefore:
Management reserve = Budget - baseline cost = 115,000-100,000 = 15,000
As the planning effort progresses, the team is now able to rely on detailed supporting information, such as a detailed WBS, resource estimates and vendor bids. The team needs to prepare a solid and
precise and cost estimate. Which estimating technique would you recommend?
A. Relative
B. Analogous
C. Decomposition
D. Bottom-up
D. Bottom-up
Bottom-up estimating determines the project costs starting from the lowest levels of the WBS. These detailed estimates, frequently obtained at the activity or work package level, may then be aggregated into an overall estimate (Answer D). The relative estimating (Answer A) and analogous estimating (Answer B)
techniques are not precise. Decomposition is not an estimating technique (Answer C).
You are managing a robotic system project that is well underway. PMO requires you to produce a weekly report forecasting the expected total cost of the project. How should the acceptable range of cost variance change throughout the project?
A. Should decrease, because more work has been completed
B. Should increase, because more risks have been identified
C. Should remain steady throughout the project
D. Should increase, because there is less time to issue cost corrective actions
A. Should decrease, because more work has been completed
The acceptable range of cost variance should decrease throughout the project, as more work is completed.
You are about to move on to determining the budget estimate. All of the following may be used as an input, EXCEPT:
A. WBS
B. Cost baseline
C. Basis of estimate
D. Project schedule
B. Cost baseline
The cost baseline is an output of the determine budget process. All other options can be inputs to the determine budget process.
During the development phase, two team members cannot agree on how to measure the value of the work in progress. One team member insists that the team should use the percent complete with
milestones gates approach and another argues that the team should use a fixed formula. You should tell them that they should:
A. Not be concerned with monitoring and controlling activities
B. Use the earned value management method to measure the value of work in progress
C. Ask the sponsor
D. Check the cost management plan
D. Check the cost management plan
The project should adopt the approaches established in the cost management plan.
You need to estimate the costs of the resources required to complete the project. Which of the following statements regarding cost estimates is correct?
A. Detailed estimates must be aggregated into an overall cost estimate
B. Cost estimates should indicate the range of potential values
C. Costs estimates should be recorded in the cost management plan
D. Each activity cost should incorporate a provision to account for uncertainty
B. Cost estimates should indicate the range of potential values
Range estimates, unlike one-point estimates, provide insight into the estimates’ uncertainty (answer B). Top-down estimates may be prepared at the early stages of the project (answer A). The cost management plan does not record cost estimates (answer C). Contingency reserves may be maintained at the work package, deliverable or project level (answer D).
You just reported that the performance required to complete the project within the cost baseline is 1.3. How would you describe the project performance?
A. The project is overrunning the budget
B. The project is under budget
C. The project is late
D. The project has an unfavorable rate of return
A. The project is overrunning the budget
The project is overrunning the budget because the performance required to complete the project within the cost baseline (TCPI) is greater than 1 .
The project manager is having trouble estimating the costs of a research and development project. Which of the following is the MOST likely cause?
A. The budget has not been approved
B. The scope is not clearly defined
C. Team members have not been fully assigned to the project
D. There are not enough funds
B. The scope is not clearly defined
Unclear scope definition will often lead to difficulties in estimating costs.
The project manager is analyzing the approved version of the project cost objectives. This benchmark used as a reference to assess cost performance can be graphically represented as _______________.
A. A project schedule
B. A cost aggregation curve
C. A S curve
D. An influence curve
C. A S curve
The time-phased cost baseline is also known as the S curve, because its graphical representation usually resemble as “S”.
Olivia is managing an airport extension project that is well underway. She is using earned value analysis to assess project performance. Which of the following is Olivia working on?
A. Planning cost management
B. Estimating costs
C. Determining the budget
D. Controlling costs
D. Controlling costs
The EV management techinique is used as part of cost control.
A project has the following performance data:
AC = 2,000,000
CV = -250,000
SPI = 1.12
BAC = 10,000,000
What is the project planned value?
A. 1,750,000
B. 1,562,500
C. 2,250,000
D. There is not enough information
B. 1,562,500
You have been hired to manage a large project. You are estimating the cost of a deliverable based on the costs of the work packages required to complete it. The estimate costs process is defined as:
A. Rolling up costs along the WBS to create a cumulative time-phase budget
B. Estimating the costs of the resources needed to complete the project
C. Estimating costs at project completion and managing changes to the cost baseline
D. A project management technique for measuring project performance, combining and integrating scope, schedule and cost assessment
B. Estimating the costs of the resources needed to complete the project
The estimate costs process involves estimating all costs according with the resources required. Answer A is referring to the determine budget process. Answer C is referring to the control costs process. Answer D is referring to earned value management.
The deliverable XYZ was scheduled to last two weeks with one team member working with a 50% allocation. When the deliverable actually started, the project manager decided to assign the team
member full time. At the end of the first week, the project manager determined that the deliverable was 25% complete. What is the schedule performance index?
A. 0 25
B. 0 50
C. 1
D. 2
B. 0 50
Halfway through an engineering project, the project management team prepared an EVM report. The project management team reported that the project’s budgeted cost of the work scheduled was
250,000. The budgeted cost of the work scheduled to be completed up to a specific moment in time is known as:
A. Actual cost
B. Earned value
C. Planned value
D. Budget at completion
C. Planned value
The planned value represents the budgeted cost of the work scheduled to be completed up to a specific date.
You are managing a project with a budget of 20,000 spread evenly across 10 months. What is the estimated variance at completion after 4 months if the accumulated actual costs are 10,000?
A. -5,000
B. 4,000
c. 5,000
D. 25,000
A. -5,000
The variance at completion can be calculated as:
VAC = BAC - EAC = BAC - (BAC/CPI) = BAC - (BAC/EV/AC) =
= 20,000 - (20,000/8,000/10,000) = -5,000
In the last status meeting you reported that your project CPI is 1.1 . What does that mean?
A. There is a negative cost variance
B. The estimate at completion is larger than the budget at completion
C. The estimate at completion is smaller than the budget at completion
D. There is a negative variance at completion
C. The estimate at completion is smaller than the budget at completion
The project has a favorable cost performance. Therefore, the estimate at completion (EAC) is smaller than the budget at completion (BAC). The remaining statements are incorrect.
The team is ready to start estimating the project costs. Which of the following is LEAST reliable?
A. Lessons learned from past projects
B. External databases on resource productivity
C. Team knowledge
D. Cost records of previous projects
C. Team knowledge
Team knowledge is subject to personal subjective elements, such as attitude, interests, memory and agenda. Therefore, it is a less reliable source of information.
A business process reengineering project was budgeted for 500,000 and was scheduled to be completed in 6 months. 3 months after the project start, the project is 40% complete and has spent 300,000. Which of the following statement best describes the project’s performance?
A. Over budget and behind schedule
B. Over budget and ahead of schedule
C. Under budget and behind schedule
D. Not enough information
D. Not enough information
The project’s CP’ can be calculated as CPI=EV/AC = 0.66. Therefore, the project is over budget. However, we do not have information regarding the planned value. Therefore, we cannot assess schedule
performance.
A project should cost 100,000 and take 10 months. After 5 months the project is 25% complete and the actual costs are 20,000. What is the project estimate do complete (ETC)?
A. 40,000
B. 60,000
C. 80,000
D. 100,000
B. 60,000
The project earned value (EV) is $25,000, because 25% of the total budget at completion (BAC) has been completed. Therefore the project CPI is EV/AC 25,000 / 20,000 = 1.25. Assuming a typical estimate, the estimate at completion (EAC) is BAC/CPI = 100,000 / 1.25 = 80,000. Therefore, the project estimate to complete (ETC) EAC-AC 80,000 - 20,000 = 60,000
Olivia is managing an airport extension project that is well underway. She is using earned value analysis to assess project performance. She determined the following performance metrics:
EV = 700
AC = 750
PV = 680
What is the schedule variance (SV)?
A. 70
B. -70
c. 680
D. 20
D. 20
A project manager is leading a telecommunications project that is overrunning the budget. The project manager should concentrate on ______________ costs to respond to the cost variance.
A. Direct and variable
B. Indirect and variable
C. Fixed and variable
D. Direct and fixed
A. Direct and variable
A project manager is rescheduling future work to reconcile the rate of expenditures with the funds committed to the project. In which process is the project manager working on?
A. Estimate costs
B. Determine budget
C. Control costs
D. Monitor and control project work
B. Determine budget
Dubious question: assuming the PM is doing so during the Determine Budget process.
The project manager is reconciling funding requirements which is part of the determine budget process.
Halfway through an engineering project, the project management team is preparing an EVM report. The project was budgeted for 500,000, having completed work budgeted for 400,000. If the current
CPI is 0.85 and the SPI is 0.8, what Will be the schedule variance at the end of the project?
A. (125,000)
B. 0
C. 1
D. Not enough information
B. 0
At the end of the project the schedule variance is always zero, because the earned value will equal the planned value.
Your plant extension project is running behind schedule and overrunning the budget. It’s the end of the design phase and the steering committee must decide on whether to proceed with the project. All of the following should be taken into consideration, EXCEPT:
A. Cost Performance Index (CPI)
B. Sunk costs
C. Forecasted benefits
D. Estimate to Complete (ETC)
B. Sunk costs
Sunk costs have already been spent and cannot be avoided or undone (answer B). The remaining options can influence the project decision.
You are starting a new waste management project that seeks to reduce industrial, household and municipal waste. You and your project team estimated the project costs considering the resources
required to complete the project work. What should you do before moving on to the next planning process?
A. Determine the project’s Cost Performance Index (CPI)
B. Define the funding requirements needed to support the project expenditures
C. Establish the cost baseline
D. Document the basis of estimates
D. Document the basis of estimates
You should document the basis of estimates, as additional details and assumptions that support and explain these estimates. Determine the project CPI (answer A) is part of cost control. Defining the funding requirement (answer B) and establishing the cost baseline (answer C) are part of determining the budget.
Four months into the project, the project EV is 30,000, the PV is 35,000 and the AC is 40,000. What is the project SV?
A. -5.000
B. -10.000
c. 0.87
D. 5.000
A. -5.000
The customer is considering whether to upgrade the existing manufacturing system or to use the existing system that has proven to be costly to maintain. Life cycle costing improves project decisions
by ___________ .
A. Considering the costs required to develop, operate, maintain and discontinue the product
B. Considering the project life cycle costs
C. Considering the operational costs
D. Progressively detailing the project costs as the project moves toward completion
A. Considering the costs required to develop, operate, maintain and discontinue the product
Life cycle costing considers all the costs required to develop, operate, maintain and discontinue the product.
You are leading a software development project that is critical to a program milestone. You are considering the approaches that will be used to measure the value of work in progress. Which of the following options would you use to assess the performance of a work package that spans one single control period?
A. Weighted milestones
B. Percentage complete with milestones gates
C. Fixed formula
D. Level of effort
C. Fixed formula
A fixed formula may be applied to small work packages that have durations of less than one or two performance measurement periods. Weighted milestones (answer A) and percentage complete with milestones gates (answer B) are typically used in larger work packages. Level of effort (answer D) is used when we want to measure performance indirectly by the performance of another work package, or proportionally to the elapsed time.
You recently joined a consulting company and were assigned to a social media application project. The sponsor requested a 10% budget cut while assessing the project budget. How should you
proceed?
A. Revisit the project WBS to meet the 10% budget cut target
B. Submit an accurate budget for approval
C. Adjust the cost estimate to meet the sponsor’s expectations and update the risk register to record the associated risks
D. Adjust the project cost contingency reserve to meet the sponsor’s expectations
B. Submit an accurate budget for approval
The project manager should provide an accurate budget for approval (answer B). The most cost-effective project WBS (answer A) should already have been prepared before determining the budget. You should provide realistic estimates (answers C and D).
Matthew is managing the company’s Oil and gas project. He is rescheduling project activities to adapt the rate of resource consumption to available funds. Which of the following activity is Matthew performing?
A. Resource smoothing
B. Resource levelling
C. Funding limit reconciliation
D. Crashing
C. Funding limit reconciliation
Funding limit reconciliation compares and adjusts the use of funds with the existing financial constraints.
The project manager has prepared a performance report where the following data regarding the design phase of a large IT project: BAC= 120,000, EV = 60,000, AC = 80,000, PV = 40,000 and EAC = 110,000. How can you BEST describe the performance of the design phase?
A. The design is ahead of schedule and under budget
B. The design is ahead of schedule and over budget
C. The design is behind schedule and over budget
D. The performance report data are inconsistent
D. The performance report data are inconsistent
CPI is lower than 1, therefore the EAC should be greater than BAC.
You are using EVM to forecast future performance. You assume that current cost performance would not continue in the future. Which formula should you use to determine the project estimate to complete (ETC)?
A. ETC = BAC/CPI
B. ETC = BAC -EV
C. ETC = (BAC/CPI)-AC
D. ETC = (BAC-EV)/CPI
B. ETC = BAC -EV
Atypical estimate to complete (ETC) is determined by (BAC-EV).