Legal and Statutory 2 Flashcards
Elliott House: What did your appointing owner’s proposals include?
They included a rear extension (S6) and demolition of a rear building which adjoined the stone party fence wall (S3)
Elliott House: What notices were served?
Section 3 - Party Structure - 2 months Notice.
Section 6 - Adjacent Excavation - 1 Month Notice
Elliott House: What was your rationale behind using those notices?
Section 3 - Because the project involved carrying out works to the existing party fence wall.
Section 6 - Because the works involved a new foundation which fell within 3m of the neighbours foundation.
Elliott House: When were your notices served?
The notices were served 2 months prior to the project works in accordance with the Section 3 provisions.
Elliott House: What is included in those party wall notices, tell me about their contents?
We use a standard form of letter which includes:
Details about the parties.
Details about which part of the Act applies to the works (a,b,c,f etc)
Timescales
Drawings (Section and plan for Sec 6 notice)
Elliott House: What drawings were included?
Section 6 requires the inclusion of a plans and details.
I issued foundation details, floor plans and an elevation drawings regarding the proposals with dimensions etc.
Elliott House: What were the adjoining owners options in the notices?
- Consent to the works. (They went for this)
- Dissent appoint me as joint surveyor.
- Dissent appoint own surveyor and appointing owner pays for fees.
Elliott House: Tell me about the timescales regarding a response to the notices.
Issue notices in accordance with the timescales of the sections (i.e. 1 month, 2 month etc)
If not hear back within 14 days, send a reminder letter.
If not hear back within a further 10 days appoint another surveyor on their behalf.
Elliott House: What did you do after receiving consent?
I carried out a Schedule of Condition of both properties in the event their was a dispute.
This offered transparency between all parties.
Elliott House: What would happen if they dissented but appointed you as the agreed surveyor?
Draw up a Party Wall Award, which is a legal document that states what work should happen, how and when works are carried out, and who pays for each part.
The award details proposed works, looks over plans and makes sure work will not affect your property, and determines what happens if your property is damaged.
Schedule of Condition is also carried out and issued to both parties.
Elliott House: What would happen if they dissented and appointed their own surveyor?
Pre-agree third surveyor.
Jointly check that plans will not affect your property, assess how and when works will be carried out, and make any necessary changes to the proposed work. Using this information, both surveyors will produce the joint party wall award based on the findings from their respective properties.
Surveyors carry out a joint schedule of condition
If these two surveyors cannot agree on a suitable party wall award, the document will be decided by an impartial third surveyor.
If you disagree with any of the surveyors’ award, both the owner and neighbour have 14 days to appeal to the County Court against it.
Elliott House: What did you do during your inspection?
Reviewed the proposed drawings to the actual site which determined which neighbours would be affected.
I then obtained the neighbours details utilising Land registry records.
Elliott House: Briefly tell me the party wall process?
- Inspect site to determine proposals
- Issue notices (1/2months) and (14days+10day follow up)
- Consent to works/Dissent to works and appoint own or agreed surveyor.
- Issue party wall award if applicable.
- Carry out SoC
Elliott House: Whats in a party wall award?
Description of work (how, what when) Programme and Working hours Making good costs etc Method statements Extra works to protect property.
Bellway Industrial Estate: Tell me about the provisions of Doc M that you used?
External areas only so only utilised
Section 1 – Access to the building
Section 2 – Access into the building