Q

2 Durham Road: What did the Lease say and what were the Tenants obligations?

A

The Lease was a standard internal repair and decoration only. I did however take some general notes and photographs externally.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
2
Q

2 Durham Road: Why is it important to carry out a SoC prior to a Lease?

A

It provides transparency between all parties and records the condition of the unit before the lease begins. There limiting liability to the Tenant.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
3
Q

Stephenson Building: What had failed within the parapets and how had they failed?

A

Copings – cracked by impact damaged, corroded fixings caused cracking, open joints due to mortar erosion.

Upstand - Details not to a sufficient height (usually 150mm minimum) and the dressed portion was limited allowing delamination.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
4
Q

Stephenson Building: How had the dressed upstands failed?

A

Low heights of below 150mm and limited dressed depth had allowed water to ingress by capillary and splashback, this allowed the upstands to become unsecure.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
5
Q

Stephenson Building: What do weepholes and cavity trays do?

A

Disperse water in the event water/moisture enters the building’s cavities.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
6
Q

Stephenson Building: Why did you recommend further opening up works?

A

To determine the definitive build up of the walls as my inspection was non-invasive from low-level (no mewp)

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
7
Q

Stephenson Building: What apparatus did you use?

A
Binoculars 
Damp meter
Camera
Notepad
PPE
How well did you know this?
1
Not at all
2
3
4
5
Perfectly