Hitosa, Ethiopia water supply scheme Flashcards
1
Q
successes
A
- construction completed on time
- still worked after 20 years
- only small amount charged for water which goes to maintaining infrastructure
- project completely managed by local communities
- 65,000 people 25L a day
2
Q
problems
A
- pipeline may be too costly to repair after its expected lifetime of 30years (UK supplied originally)
-hygiene around the tap stands has been neglected which has increased waterbourne diseases - availability of clean water has increased migration so now the scheme is expected to support many more people - threatens sustainability
3
Q
what does the scheme involve
A
taking water from the permanent springs on Mount Bada and transporting it using only gravity to over 100 public water points