Group 6.E - Curtain Wall Manual, Part II: Importance of Tolerances and Clearances in Wall Construction Flashcards

1
Q

A _________ is a permissible permissible amount of deviation from a specified or nominal characteristic, whether it is a dimension, color, shape, composition or other quality.

clearance
factor
coefficient
tolerance

A

tolerance

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
2
Q

A _______ is a space or distance purposely provided
between adjacent parts, either to allow for
movements or for anticipated size variations, to
provide working space, or for other reasons.

clearance
factor
coefficient
tolerance

A

clearance

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
3
Q

Curtain wall designs should be designed with an effort to ______ tolerances tighter than those given in the referenced standards.

require
minimize
encourage
eliminate

A

minimize

eliminate

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
4
Q

It must be understood, however, that the wall can be
installed within the tolerances established only if:

  1. The building frame (or contiguous
    construction) is built within the tolerances
    specified for that work
  2. The tolerances allowed and clearances provided are minimized within the modules of the building frame
  3. The clearance necessary for installation of the wall is coordinated with the wall design and the limits of
    adjustment permitted by its anchorage details.
  4. The clearance dimensions shown on the
    architect’s drawings provide adequate
    working space, based on the tolerances allowed
A

1 and 4

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
5
Q

Tolerances established by the designer should be both _____ and _____.

precise and minimal
reasonable and practical
general and generous
tight and challenging

A

reasonable and practical

or realistic

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
6
Q

the nominal clearance shown to beams
and columns on architectural details never be _______.

Greater than 2”
Greater than 1”
Less than 1”
Less than 2”

A

Less than 2”

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
7
Q

The nominal clearance dimension shown on the
drawings, should be _______ the actual clearance
required, (taking access to anchors and minimum fire-safe thickness into account), _____ the outward
tolerance permitted for the adjacent construction.

half of / plus
equal to / minus
equal to / plus
half of / times

A

equal to / plus

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
8
Q

Drawings and specifications are ___________ documents and information contained in one _______ duplicated in the other.

overlapping / is typically
complementary / should not be
cross-referencing / must be
collaborative / is always

A

complementary / should not be

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
9
Q

________ and ________ are the two basic
documents which the architect develops to convey
the information needed for the construction of any
structure.

details and sketches
drawings and contracts
details and elevations
drawings and specifications

A

drawings and specifications

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
10
Q

Drawings and specifications are ___________ documents and information contained in one _______ duplicated in the other.

overlapping / is typically
complementary / should not be
cross-referencing / must be
unrelated / are never

A

complementary / should not be

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
11
Q

Drawings and specifications are ___________ documents and information contained in one _______ duplicated in the other.

overlapping / is typically
complementary / should not be
cross-referencing / must be
unrelated / is never

A

complementary / should not be

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
12
Q

In the drawings and specifications a ______ must be made between ground floor the storefront areas and the other areas of the wall, as these are ____ installed by the same contractor.

structural connection / always
continuous design / never
non-moving connection / sometimes
clear delineation / often not

A

clear delineation / often not

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
13
Q

In the drawings and specifications a ______ must be made between the ground floor storefront areas and the other areas of the wall, as these are ____ installed by the same contractor.

structural connection / always
continuous design / never
non-moving connection / sometimes
clear delineation / often not

A

clear delineation / often not

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
14
Q
Curtain wall drawings must show all of the following except the: 
complete curtain wall system
glazing type and coatings
grid framework, panels and fixed glass 
accurate dimensions
operating windows, doors
frame material and section modulus
A

glazing type and coatings

frame material and section modulus

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
15
Q

Curtain wall drawings must show all of the following except the:
connections between the wall and the building structure
wind loads and thermal expansion
connection at storefronts, roofs, floors
ceilings, partitions
a precise indication of where the curtain wall scope starts and stops
section weight and alloys of all materials
section drawings sufficient to clearly define the
product requirements

A

wind loads and thermal expansion

section weight and alloys of all materials

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
16
Q

Drawings should show the _____of and define the ____ sealants referenced in the specifications.

color / elongation requirements for
location / contractor responsible for
shore A hardness / material of
location / total linear footage of

A

location and contractor responsible for

17
Q

Consideration of thermal movement in the design is necessary to avoid all but which of the below:

sealant failure
material deformation
damage to adjacent finishes
catastrophic failure
measles
failing the FM exam
angry clients
attorneys
A

measles

18
Q

Q1:
In wall construction, tolerance is:

interchangeable with clearance
never accepted on the construction site since it can alter appearance
permissible amount of deviation from a specified or nominal characteristic
space or distance between adjacent parts

A

permissible amount of deviation from a specified or nominal characteristic.

19
Q

Q2:
In wall construction, clearance is:

interchangeable with tolerance
never accepted on the construction site since it can alter appearance
permissible amount of deviation from a specified or nominal characteristic
space or distance between adjacent parts

A

space or distance between adjacent parts

20
Q

Q3:
Limiting tolerance to less than those in referenced standards often leads to

increased costs
energy efficient buildings
LEED certification
seismic tolerance

A

increased costs

21
Q

Q4:
Drawings must show all except:

complete curtain wall system
alternate anchorage systems
the grid framework
components of the system

A

alternate anchorage systems

22
Q

Q5:

The following is true for thermal expansion of building materials:

al building materials will expand at similar rates
all steel types will expand at similar rates
all building materials will expand but at different rates
the color of the paint won’t have any impact

A

all building materials will expand but at different rates