Contract administration Flashcards
What is nomination?
Selection of a particular contractor to carry out the works, manufacturer, or supply materials and provides comfort of quality or performance
Do nominated subcontractors get paid separately?
They are paid by the main contractor with sums identified separately
Can a contract object to a nominated subcontractor?
Yes that must be made during the tender process or if there are specific reasons such as insolvency
Who is responsible for the design after novation?
The client must sign off the design at the point of novation and the contract are liable thereafter
What is a principal contractor?
A principal contractor is the contractor with control over the construction phase of a project involving more than one contractor.
What are domestic subcontractors?
Subcontractors appointed by the main contractor
What are named subcontractors?
Subcontractors names by the client but under contract to the main contractor
What would you do if the client advised that they didn’t have enough money to make a payment?
I would advise the client that they are contractually obliged to make payment once a certificate has been raised. It may be possible to defer payment for a couple of days in agreement with the contractor.
Is included within a valuation?
- prelims
- measured works
- materials on/off site
- Variations
- retention
- previous payments
Do you have to pay for materials offsite for variations?
q there is no requirement to pay for materials offsite unless identified within the contract, but I would discuss it with the client before advising the contractor
What is a verbal instruction?
Commonly used if something is urgent or affects the critical part of a project, must be confirmed formally thereafter
What documents would be required in incorporating a CDP supplement into a project?
In a design and build project the documentation to be included with the employers requirements covering scope, specification, drawings, contractors proposals along with any insurances
What is a collateral warranty?
Agreement between a third-party outside of the contract. The collateral warranty is a promise by the contractor to someone else, say a prospective tenant, that they have performed and will perform their obligations under the building contract.
Is an email a contract document?
Yes providing there’s other, acceptance, intention to create a good relations and the respondent email does not vary the conditions
What are all contracts?
A contract made orally which is difficult to enforce as you’re unable to prove the specific terms and conditions of the agreement
JCT vs NEC?
JCT specific to building projects, NEC can cover civils as well
Is the difference between an information requirement schedule and an information release schedule?
The information requirement schedule as the contractor to provide dates when design information is required. The information reschedule informs the contractor when the design information will be available.
What is a defect liability period?
A period at the end of the contract, commonly 12 months, where the contract rectifies any defects advise within the structure at the contract is expense providing they are due to materials or workmanship. On completion, retention is released.
What is the contractual requirements with a latent defect?
A claim can only be brought when the limitation period of the contract of six or 12 years depending on whether it was signed as a deed or underhand. The architect should issue an instruction to the contractor on what to do if identified, possibly telling them to comply with a third-party
If the works all materials are not in accordance with the contract what options does an architect have?
Instruct the contractor to remove defective work or materials at their own expense. Instruct the contractor to open up and test.
What is to be considered when requesting opening up?
The significance of any non-compliance, consequences on public or adjoining properties, time and costs, level of supervision required.
What is a provisional sum?
A sum of money in the contract that has not been accurately costed due to lack of design or detail and must be instructed.
What is a defined versus undefined provisional sum?
A defined provisional sum is where an item has not been completely designed but certain information is available about the works or quantity. An undefined provisional sum is where there is minimal or no information at the time contract.
Can additional time or premiums be added for a provisional sum?
No this must be included when costing. Any significant changes will be considered as a variation